Pages

Search

Calculating Custom fields Microsoft Project

Calculating Custom fields Microsoft Project


Calculating Custom fields

Posted: 09 Jun 2004 12:20 PM PDT

On top of this, you may encounter problems when one calculated field refers
to another.
Imagine what happens when one calculates before the other.
I suggest that you write the formula for C so that it is independent of A
and B.
For example if:

A = [Finish]-[Start]
B = [Baseline Finish] - [Baseline Start]

then I'd write C so that:

C = 100*([Finish]-[Start])/([Baseline Finish] - [Baseline Start])

-Jack

"JulieS" <microsoft.com> wrote in message
news:1a77801c44e70$15bf51a0$gbl... 


HELP for old 95 user with Resources for 2003

Posted: 09 Jun 2004 11:04 AM PDT

 
options and the schedule 
decimal 
crashed and I have 
but I had to 
get the Resources 
software I can't get the 
actual crew size. How 
number for the Resource 

How do some of the column relationships work?

Posted: 09 Jun 2004 08:48 AM PDT

Jack,

Thanks for the lead but I am looking for some sort of diagram or a design doc.

I have been using MS Project for about 5 years now and I am aware of how the fields work but at times I would input some updates and Project goes and makes some obscure changes like if I update the % complete and the end date Project changes my duration from 4 days to 1.67. Now in the past I didn’t really care I went back and manually changed it back to what it was supposed to be. But now I took a position where the front end of the project is driven by an excel spreadsheet and tracking the overall progress is done in Project. So before I can link all the cells and have the inputs updated by several team members I want to understand some of MSP calculation methods.

I would appreciate any additional help


"JackD" wrote:
 

mail merge

Posted: 09 Jun 2004 05:52 AM PDT

Cathy,

I suggest posting this request in microsoft.public.word newsgroup. This
newsgroup is for Microsoft Project which is a scheduling software.

-Jack

"cathy" <microsoft.com> wrote in message
news:com... 
merge, 
can anyone help thanks.


Error in Project calculation?

Posted: 08 Jun 2004 01:53 PM PDT

Thanks a lot, Sarah

The split view that you suggest is indeed a great way to
work and have the best overview of all parameters. I also
like to add the Work column up in the Gantt part.

I can see the logic applied by Project is indeed the way
you describe. The "fixed work" is fixed also at resource
level rather than only at task level (which is what I expected).





"Sarah" <com> wrote in message
news:google.com...
| Jerry,
|
| When you're going to make changes like this to your schedule, I would
| suggest that you split the screen and show the Resource Work view of
| the Task Form on the bottom part, with the Gantt Chart on the top.
| Select the task in the Gantt, then in the bottom you can adjust the
| resources individually. If you initially have one resource assigned at
| 100% for 16 hours, then add another resource without making any other
| changes, Project assumes that the two resources will split the work,
| so each gets 8 hours. Then you tell Project that the second resource
| is only available 25% of the time, so Project schedules that resource
| at 2 hours per day. The 8 hours then takes that resource 4 days to
| accomplish.
|
| Sarah
|
| > | "Jerry" <com> a écrit dans le message de
| > | news:phx.gbl...
| > | > I am new to Project, and it might be my lack of knowledge, but:
| > | >
| > | > If I have a task (fixed work, effort driven) of 16 hours work, and
| > assign
| > | > 1 person 100%, MS Project correctly calculates duration of 2 days.
| > | > If I add a second person at 100%, duration is (correctly) set to one
| > day.
| > | > But if I assign first person 75%, and the other 25%, the duration
| > | > is 4 days! Should be 2, shouldn't it? A bug?


Formatting cells for word wrap

Posted: 08 Jun 2004 01:35 PM PDT

Hello Hall,

You can do it for the whole project : select the whole project with a mouse
click on the grey square at the top left of the project sheet.
Then do the same way that you did for a single row : drag the bottom line
downward with the mouse.

Gérard Ducouret [Project MVP]
PragmaSoft ® - Paris

"Hall" <org> a écrit dans le message de
news:phx.gbl... 


Help on Custom Formulas

Posted: 08 Jun 2004 01:16 PM PDT


"RTG Manager" <microsoft.com> wrote in message
news:com... 
formulas, such as ProjDateDiff and Date Diff? Nothing appears in the online
help or the manual (Inside Out Project 2003).

Besides the help that Gerard mentioned you can find a couple of common
questions and answers here:

http://masamiki.com/project/customfieldFAQ.htm

-Jack


Creating TBD dates with in MSP

Posted: 08 Jun 2004 11:51 AM PDT

Rob,

Thanks for the note. But if you saw my original post the problem is that the plan is scheduled for 2 years and all tasks are identified but the LOE’s are not. So in the project plan I need to put a “TBD”

Thanks for any additional help.


"AK" wrote:
 

saving export map

Posted: 08 Jun 2004 11:42 AM PDT

Jeff,
Yes, you can. With a small VBA procedure that you can write by automatic
recording :
Tools / Macro / Record new macro
Do the job as usual...
Tools / Macro / Stop recording

Gérard Ducouret [Project MVP]
PRagmaSoft ® - Paris

<microsoft.com> a écrit dans le message de
news:19b2a01c44d98$0c2fe650$gbl... 


How to see all notes on screen at one time

Posted: 07 Jun 2004 10:04 PM PDT


Martin,
The method Rod suggested will work fine as long as there are no line
feeds in the Notes text or the total number of characters in the Notes
field is 256 characters or less. If there are line feeds or more than
256 characters, you will need to either manually copy and paster, use an
export map, or create a VBA macro to get the complete text of the Notes
field to another application (e.g. Word, Excel, etc.).

John

Compatibility between MS Project 2000 and 2003

Posted: 07 Jun 2004 04:06 PM PDT

Haven't tested that, but haven't heard of any problems. The worst Project
2003 standard problem has been that on some PC's you've been unable to out
some tasks. There is however a hotfix for that problem now if you encounter
it.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
"JulieD" <net.au> wrote in message
news:%phx.gbl... 
2003 
2003 


Conditional Task

Posted: 04 Jun 2004 08:07 AM PDT

IMHO, a project schedule is just that - a plan of what you are actually
going to do. So how to handle the contingency scenario? Decide whether it
is most likely that you'll need to restore one or more servers or not and
build your plan based on that assumption, but with the understanding that
you may have to modify it later if circumstnaces evolve differently. Same
sort of idea as planning to drive from point A to point B via C but with an
alternate route through D in mind if road construction forces a detour
enroute.

--
Steve House [MVP]
MS Project Trainer/Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Day Tripper" <microsoft.com> wrote in message
news:185fb01c44a45$99e77c20$gbl...