|   How do I start task A before tasks B & C     Posted: 14 Mar 2006 03:40 AM PST Hi,
 You must make B and C dependant on A (FS), and set A's constraint to As Late
 As Possible.
 HTH
 
 --
 Jan De Messemaeker, Microsoft Project Most Valuable Professional
 http://users.online.be/prom-ade/
 For FAQs: http://www.mvps.org/project/faqs.htm
 "Julian Griffin" <microsoft.com> schreef in
 bericht news:com...
 in
 any
 must
 A, I
 FF,
 until
 BOTH
 message
 predecessors.
 other
 list
 
 
 
 | 
    |   Mark project plan as readonly     Posted: 13 Mar 2006 05:38 PM PST Under File, Save as there is a Tools button in the top right corner.Click on it and select General Options
 Enter a write password. That way anyone can open it, but only someone with
 the password can save it.
 
 --
 
 Rod Gill
 Project MVP
 Visit www.msproject-systems.com for Project Companion Tools and more
 
 
 "GM" <com> wrote in message
 news:googlegroups.com...
 
 
 
 | 
    |   resource available from dates     Posted: 13 Mar 2006 05:34 PM PST Sorry, never seen this. When yoiu set Available To in the first lmine,Available From on the secind line becomes D+1, but the way you put it, never
 seen.
 Do not hesitate to send the file if you want me to look at it
 
 --
 Jan De Messemaeker, Microsoft Project Most Valuable Professional
 http://users.online.be/prom-ade/
 For FAQs: http://www.mvps.org/project/faqs.htm
 "la0d0g" <microsoft.com> schreef in bericht
 news:com...
 the
 'available
 Am
 options
 
 
 
 | 
    |   Resource planning (hours need per week, per project)     Posted: 13 Mar 2006 02:07 PM PST In article <com>,Justin <microsoft.com> wrote:
 Justin,
 See below
 Leveling and contouring are two completely different things. In your
 initial post you mentioned something about a resource starting at x%,
 ramping up to y% and then back to x%. That contour might relate to
 either a "Bell" or "Turtle" shaped assignment profile. Contours can also
 be custom generated by directly massaging the Work field in one of the
 Usage views.
 
 Leveling on the other hand is a Project function wherein Project
 attempts to move the schedule around to eliminate overallocated
 resources. Tasks can be given a priority level to help the leveling
 algorithm know which tasks should not be moved and which can be moved.
 Leveling can be done on various timescales (e.g. day-to-day,
 week-to-week, etc.). The message you saw relates to Project detecting
 overallocation of a resource and therefore suggests that that resource
 should be leveled
 It sounds like you are confusing contour profiles with leveling. See the
 answer to question 1.
 
 John
 Project MVP
 
 | 
    |   Timescale distortions     Posted: 13 Mar 2006 12:35 PM PST Jack,Thanks for your reply.  I wish this was the case, that I had the wrong
 format, unfortunately I think I do.  The dates work fine for the beginning of
 the timescale and then changes as you look to the end of the timescale.  In
 addition, the timescale is correct until you print it out.  That is to say,
 what you read on the screen is changed when you print it out.
 --
 Thank you.
 
 
 "JackD" wrote:
 
 
 | 
    |   Resources with multiple calendars     Posted: 13 Mar 2006 12:28 PM PST Ah...  That helps somewhat.  I still can't convince Project that it needs todo something different with a task that uses a resources that has a different
 calendar than the project.
 
 Where do I go to find the answers to questions like this?  It's very
 frustrating to try to use Project and have it do non-intuitive things to me.
 
 Jack
 
 | 
    |   How To Track Estimated Time but Create A Window Of Time to Do It     Posted: 13 Mar 2006 12:19 PM PST There are several ways one could handle your scenario.  Duration, first ofall, is the time that elapses between when work is first done on the task
 and when it is complete.  It is NOT the "window" in which you might do the
 task.  Duration is always a period of observable physical activity.  In the
 case of your phone call, whenever you make that call you're not going to be
 doing anything else at the same time and you're not going to keep the other
 party on the phone for 2 days.  You're going to make the call, talk for 30
 minutes, and then you're done.  That's a 30 minute duration task with you
 working on it 100%, doing .5 man-hours of work.  If you have in hand all the
 information you need to carry out the conversation on Monday morning you
 could make the call as early as Monday 8am.  You need to have done it
 sometime before the end of the day on Tuesday.  My preferred way of handling
 that would be to show the call as a 30 minute duration task, perhaps with a
 Start No Earlier Than contraint of Monday 8am, and a finish Deadline of
 Tuesday 5pm. The only time I'd show it as a 2 day duration task would be if
 I intended to have it done in little bits and pieces spread out over the two
 days with the first little piece starting Monday at 8am and the last bit
 finishing Tuesday at 5pm.  If the nature of the work was such that you could
 spread it out over two days, it started on Monday at 8am and you finished it
 Tuesday at 5pm, doing it so the work actually did spread out over the two
 days, it would be a 2 day duration (16 hours) task with 0.5 hours of work
 and you would be working on it at a rate of little over 3%.
 
 HTH
 
 --
 Steve House [MVP]
 MS Project Trainer & Consultant
 Visit http://www.mvps.org/project/faqs.htm for the FAQs
 
 
 
 "Na Tanya" <Na microsoft.com> wrote in message
 news:com...
 
 
 | 
    |   Multiple resources on task need to be scheduled the same time     Posted: 13 Mar 2006 11:38 AM PST Hi,
 First, do use leveling, it is nonsence to use a software and not use part of
 it.
 Leveling has an option (see below in the leveling window) "Leveling can
 adjust individual assignments on a task": check that off.
 The parameter also exists on task level: insert the column "Level
 Assignments"
 
 HTH
 
 --
 Jan De Messemaeker, Microsoft Project Most Valuable Professional
 http://users.online.be/prom-ade/
 For FAQs: http://www.mvps.org/project/faqs.htm
 "iSeriesTechie" <microsoft.com> schreef in bericht
 news:com...
 per
 engineers
 resource
 even
 
 
 
 | 
    |   Start / Finish Date Calculation Erros     Posted: 13 Mar 2006 11:25 AM PST Sometime anomolies in start and end dates when moving files betweencomputers can be traced to the hours per day settings on the Tools Options
 menu, Calendar page.
 
 --
 Steve House [MVP]
 MS Project Trainer & Consultant
 Visit http://www.mvps.org/project/faqs.htm for the FAQs
 
 "Jerry H." <microsoft.com> wrote in message
 news:com...
 
 
 | 
    |   Time scaled Baseline does not roll up     Posted: 13 Mar 2006 11:00 AM PST I'm using the latest version, Project Pro 2003 SP1 (11.1.2004.1707.15).
 This is isolated to just one project, other projects are copying the project
 summary task time scaled data appropriately to the Baseline time scaled data.
 
 For Rick, when I refer to time scaled data, I am referring to the right side
 of a Usage view. When I am referreing to table data, I am referring to the
 left side. The table view is reporting baseline correctely the time scaled
 view is not but only incorrectly at the project summary task. All other
 summary tasks are copied appropriately.
 
 Greg
 
 
 
 "Rod Gill" wrote:
 
 
 | 
    |   problems with work contours     Posted: 13 Mar 2006 10:12 AM PST If you want the result, better consider the solution :-))
 --
 Jan De Messemaeker, Microsoft Project Most Valuable Professional
 http://users.online.be/prom-ade/
 For FAQs: http://www.mvps.org/project/faqs.htm
 "Guy" <com> schreef in bericht
 news:googlegroups.com...
 
 
 
 | 
    |   Links ignore logic     Posted: 13 Mar 2006 09:40 AM PST It's a good idea to have to option set to automatically recalculate ratherthan relying on F9 in the future.
 
 
 --
 Steve House [MVP]
 MS Project Trainer & Consultant
 Visit http://www.mvps.org/project/faqs.htm for the FAQs
 
 
 
 "Clare" <microsoft.com> wrote in message
 news:com...
 
 
 | 
    |   Generic schedules     Posted: 13 Mar 2006 09:23 AM PST Also, through Format, Timescale, you can show D1.... D50 as a timescalelabel.
 HTH
 
 --
 Jan De Messemaeker, Microsoft Project Most Valuable Professional
 http://users.online.be/prom-ade/
 For FAQs: http://www.mvps.org/project/faqs.htm
 "KimC" <microsoft.com> schreef in bericht
 news:com...
 Day
 
 
 
 | 
    |   Roll-up tasks by person?     Posted: 13 Mar 2006 07:55 AM PST In article <com>,Ali <microsoft.com> wrote:
 
 
 Ali,
 I've never used the rollup macro but a quick look at the code shows it
 basically identifies rolled up tasks at the summary level (i.e. creates
 what I mentioned in the original response). Not what you want.
 
 And yes, from time to time in the newsgroup users have requested various
 ways to show multiple things on a single line. Most of them relate to
 showing more detail at the summary level, similar to the rollup macro.
 For your specific need, it must be done outside of Project.
 
 John
 
 | 
    |   Inserting a Time Scale     Posted: 13 Mar 2006 07:40 AM PST In article <com>,Michael <microsoft.com> wrote:
 
 Michael,
 Sounds like you're all set.
 
 John
 
 | 
    |   Critical Path through multiple Projects     Posted: 13 Mar 2006 07:21 AM PST In article <com>,BigFish311 <microsoft.com> wrote:
 
 
 BigFIsh311,
 It's been a long time since I worked with critical path in a
 consolidated master (way back to Project 4.x) but there is [generally]
 always a reason for Project showing what it does. I agree it would be
 much better to actually see your file and play with it a bit. I would be
 willing to do that if you don't mind sending it via e-mail although I
 may not be able to look at it for a several hours. If you want to send
 it, here is my address.
 
 If you decide to send it, please detail the area of question.
 
 John
 jensenj6atatcomcastdotdotnet
 remove obvious redundancies
 
 | 
    |   Updating hammock tasks     Posted: 13 Mar 2006 07:07 AM PST No, Dale - you said the hammock runs for the duration of the project.  Theproject summary task would seem to do exactly what you wanted.   If you must
 have another hammock, you will have to enter Actual data like %Complete as I
 don't see how Project can determine this.  It would seem to be possible to
 use vba to achieve this result: try the developer newsgroup if you want to
 do down this route.
 
 Mike Glen
 Project MVP
 
 Dale N wrote:
 
 
 
 
 |