Pages

Search

How do I start task A before tasks B & C Microsoft Project

How do I start task A before tasks B & C Microsoft Project


How do I start task A before tasks B & C

Posted: 14 Mar 2006 03:40 AM PST

Hi,

You must make B and C dependant on A (FS), and set A's constraint to As Late
As Possible.
HTH

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Julian Griffin" <microsoft.com> schreef in
bericht news:com... 
in 
any 
must 
A, I 
FF, 
until 
BOTH 
message 
predecessors. 
other 
list 


Mark project plan as readonly

Posted: 13 Mar 2006 05:38 PM PST

Under File, Save as there is a Tools button in the top right corner.
Click on it and select General Options
Enter a write password. That way anyone can open it, but only someone with
the password can save it.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more


"GM" <com> wrote in message
news:googlegroups.com... 


resource available from dates

Posted: 13 Mar 2006 05:34 PM PST

Sorry, never seen this. When yoiu set Available To in the first lmine,
Available From on the secind line becomes D+1, but the way you put it, never
seen.
Do not hesitate to send the file if you want me to look at it

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"la0d0g" <microsoft.com> schreef in bericht
news:com... 
the 
'available 
Am 
options 


Resource planning (hours need per week, per project)

Posted: 13 Mar 2006 02:07 PM PST

In article <com>,
Justin <microsoft.com> wrote:
Justin,
See below 
Leveling and contouring are two completely different things. In your
initial post you mentioned something about a resource starting at x%,
ramping up to y% and then back to x%. That contour might relate to
either a "Bell" or "Turtle" shaped assignment profile. Contours can also
be custom generated by directly massaging the Work field in one of the
Usage views.

Leveling on the other hand is a Project function wherein Project
attempts to move the schedule around to eliminate overallocated
resources. Tasks can be given a priority level to help the leveling
algorithm know which tasks should not be moved and which can be moved.
Leveling can be done on various timescales (e.g. day-to-day,
week-to-week, etc.). The message you saw relates to Project detecting
overallocation of a resource and therefore suggests that that resource
should be leveled 
It sounds like you are confusing contour profiles with leveling. See the
answer to question 1.

John
Project MVP 

Timescale distortions

Posted: 13 Mar 2006 12:35 PM PST

Jack,
Thanks for your reply. I wish this was the case, that I had the wrong
format, unfortunately I think I do. The dates work fine for the beginning of
the timescale and then changes as you look to the end of the timescale. In
addition, the timescale is correct until you print it out. That is to say,
what you read on the screen is changed when you print it out.
--
Thank you.


"JackD" wrote:
 

Resources with multiple calendars

Posted: 13 Mar 2006 12:28 PM PST

Ah... That helps somewhat. I still can't convince Project that it needs to
do something different with a task that uses a resources that has a different
calendar than the project.

Where do I go to find the answers to questions like this? It's very
frustrating to try to use Project and have it do non-intuitive things to me.

Jack

How To Track Estimated Time but Create A Window Of Time to Do It

Posted: 13 Mar 2006 12:19 PM PST

There are several ways one could handle your scenario. Duration, first of
all, is the time that elapses between when work is first done on the task
and when it is complete. It is NOT the "window" in which you might do the
task. Duration is always a period of observable physical activity. In the
case of your phone call, whenever you make that call you're not going to be
doing anything else at the same time and you're not going to keep the other
party on the phone for 2 days. You're going to make the call, talk for 30
minutes, and then you're done. That's a 30 minute duration task with you
working on it 100%, doing .5 man-hours of work. If you have in hand all the
information you need to carry out the conversation on Monday morning you
could make the call as early as Monday 8am. You need to have done it
sometime before the end of the day on Tuesday. My preferred way of handling
that would be to show the call as a 30 minute duration task, perhaps with a
Start No Earlier Than contraint of Monday 8am, and a finish Deadline of
Tuesday 5pm. The only time I'd show it as a 2 day duration task would be if
I intended to have it done in little bits and pieces spread out over the two
days with the first little piece starting Monday at 8am and the last bit
finishing Tuesday at 5pm. If the nature of the work was such that you could
spread it out over two days, it started on Monday at 8am and you finished it
Tuesday at 5pm, doing it so the work actually did spread out over the two
days, it would be a 2 day duration (16 hours) task with 0.5 hours of work
and you would be working on it at a rate of little over 3%.

HTH

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



"Na Tanya" <Na microsoft.com> wrote in message
news:com... 

Multiple resources on task need to be scheduled the same time

Posted: 13 Mar 2006 11:38 AM PST

Hi,

First, do use leveling, it is nonsence to use a software and not use part of
it.
Leveling has an option (see below in the leveling window) "Leveling can
adjust individual assignments on a task": check that off.
The parameter also exists on task level: insert the column "Level
Assignments"

HTH

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"iSeriesTechie" <microsoft.com> schreef in bericht
news:com... 
per 
engineers 
resource 
even 


Start / Finish Date Calculation Erros

Posted: 13 Mar 2006 11:25 AM PST

Sometime anomolies in start and end dates when moving files between
computers can be traced to the hours per day settings on the Tools Options
menu, Calendar page.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"Jerry H." <microsoft.com> wrote in message
news:com... 

Time scaled Baseline does not roll up

Posted: 13 Mar 2006 11:00 AM PST

I'm using the latest version, Project Pro 2003 SP1 (11.1.2004.1707.15).

This is isolated to just one project, other projects are copying the project
summary task time scaled data appropriately to the Baseline time scaled data.

For Rick, when I refer to time scaled data, I am referring to the right side
of a Usage view. When I am referreing to table data, I am referring to the
left side. The table view is reporting baseline correctely the time scaled
view is not but only incorrectly at the project summary task. All other
summary tasks are copied appropriately.

Greg



"Rod Gill" wrote:
 

problems with work contours

Posted: 13 Mar 2006 10:12 AM PST

If you want the result, better consider the solution :-))

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Guy" <com> schreef in bericht
news:googlegroups.com... 


Links ignore logic

Posted: 13 Mar 2006 09:40 AM PST

It's a good idea to have to option set to automatically recalculate rather
than relying on F9 in the future.


--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



"Clare" <microsoft.com> wrote in message
news:com... 

Generic schedules

Posted: 13 Mar 2006 09:23 AM PST

Also, through Format, Timescale, you can show D1.... D50 as a timescale
label.
HTH

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"KimC" <microsoft.com> schreef in bericht
news:com... 
Day 


Roll-up tasks by person?

Posted: 13 Mar 2006 07:55 AM PST

In article <com>,
Ali <microsoft.com> wrote:
 

Ali,
I've never used the rollup macro but a quick look at the code shows it
basically identifies rolled up tasks at the summary level (i.e. creates
what I mentioned in the original response). Not what you want.

And yes, from time to time in the newsgroup users have requested various
ways to show multiple things on a single line. Most of them relate to
showing more detail at the summary level, similar to the rollup macro.
For your specific need, it must be done outside of Project.

John

Inserting a Time Scale

Posted: 13 Mar 2006 07:40 AM PST

In article <com>,
Michael <microsoft.com> wrote:
 
Michael,
Sounds like you're all set.

John 

Critical Path through multiple Projects

Posted: 13 Mar 2006 07:21 AM PST

In article <com>,
BigFish311 <microsoft.com> wrote:
 

BigFIsh311,
It's been a long time since I worked with critical path in a
consolidated master (way back to Project 4.x) but there is [generally]
always a reason for Project showing what it does. I agree it would be
much better to actually see your file and play with it a bit. I would be
willing to do that if you don't mind sending it via e-mail although I
may not be able to look at it for a several hours. If you want to send
it, here is my address.

If you decide to send it, please detail the area of question.

John
jensenj6atatcomcastdotdotnet
remove obvious redundancies 

Updating hammock tasks

Posted: 13 Mar 2006 07:07 AM PST

No, Dale - you said the hammock runs for the duration of the project. The
project summary task would seem to do exactly what you wanted. If you must
have another hammock, you will have to enter Actual data like %Complete as I
don't see how Project can determine this. It would seem to be possible to
use vba to achieve this result: try the developer newsgroup if you want to
do down this route.

Mike Glen
Project MVP

Dale N wrote: