Days in a Month... Microsoft Project |
- Days in a Month...
- How do I compare actual to planned completion times
- Snapshot 10-line maximum
- Locating a circular reference
- Major problem
- Project File Size using MS Project 2000
- import from outlook to project
- Help! all project tasks are starting on the same day-
- Automatically level resources unit work
- Part time resources? (newbie question)
- Updating schedules sharing resource pools
- Can't Restore Outline Structure
- I want to write Project code - need ideas!
- Breakup Projects in Master File
- Tracking costs by percent complete does not work!!
- How do I unhide the 'Task Name' column in Project 2003 ?
- Monthly Report
- How do I contact microsoft without paying $35?
- WBS elements - I recall they are never to be below 40 hours????
- Project Plan Protaction
- why did task line change to blue in MSP2003 ?
- Can you change the Duration to Calendar Days?
- No resources in resource center,how to add?
Posted: 01 Mar 2006 07:16 PM PST Hey, I can do that. Good idea! "Rod Gill" wrote: |
How do I compare actual to planned completion times Posted: 01 Mar 2006 10:33 AM PST Hi Jeff, Welcome to this Microsoft Project newsgroup :) You might like to have a look at my series on Microsoft Project in the TechTrax ezine, particularly #25 on Tracking, at this site: http://tinyurl.com/2xbhc or this: http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 (Perhaps you'd care to rate the article before leaving the site, :) Thanks.) FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Jeff Budau wrote: |
Posted: 01 Mar 2006 09:43 AM PST Hi Rachello, Welcome to this Microsoft Project newsgroup :) Try using a Flag field to identify what you want and then filter for that flag. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Rachello wrote: |
Posted: 01 Mar 2006 08:27 AM PST In article <com>, "Andrew K" <microsoft.com> wrote: Andrew, The only reason I can think of for an intermittent circular reference is if calculation is set to manual. The error will only show when the schedule attempts to calculate. Did you try the interative build of the master? If so, how did it go? John Project MVP |
Posted: 01 Mar 2006 08:05 AM PST In article <googlegroups.com>, "TBA" <com> wrote: TBA, You may get a better response by posting to our sister newsgroup that deals with Project Server. Try, microsoft.public.project.server John Project MVP |
Project File Size using MS Project 2000 Posted: 01 Mar 2006 06:22 AM PST In article <googlegroups.com>, "textron.com" <textron.com> wrote: breppucc, You're right, for a Project file with 2000 lines, several megabytes is definitely bloated. You said the methods in FAQ 43 don't work for you. Does that mean you are unable to save as a .mpd and re-open as .mpp or simply that doing so has no noticeable effect on the file size? You said you convert the file every week for your customer. The word "convert" bothers me. Are you really converting the file or simply doing a "Save As" to a .csv? If it's the latter then I see no problem but if you are actually converting and re-opening the file between .mpp and ..csv, I'd say that is an process that is ripe for causing corruption. The fact that you get a Winproj.exe error tells me there might be a problem with Project itself. Before the IT folks show up I'd try running Detect and Repair found under the Project menu. However you need the installation CD to run that repair and if the IT folks are the only people who have the CD then you have to wait for them anyway. It sounds like the calendar and link issues are related to .csv conversion. I'd dispense with all the converting, get the file squared away and then re-configure the calendar and links as necessary. Then just work with the file as a standard .mpp. Use a "save as" for the customer's .csv but keep that conversion one-way. John Project MVP |
import from outlook to project Posted: 01 Mar 2006 06:11 AM PST It is pretty easy using VBA code. See http://www.outlookcode.com/codedetail.aspx?id=1165 There you will find two macros I wrote. They sort of do the opposite of what you are trying to do - one of them exports your Project tasks to Outlook tasks, the other retrieves status information from Outlook and updates your Project file. If you are familiar with VBA, you should be able to use the code in these two macros to create one that does what you want. Email me if you have any questions. Good luck, Rick Williams "Mireillea" <microsoft.com> wrote in message news:com... |
Help! all project tasks are starting on the same day- Posted: 01 Mar 2006 06:11 AM PST One more thing, Go to Tools>Options>Calculation and turn the calculation to Automatic. As you make logic ties the task will move in time. It might be helpful to add the Task Form on the view. Right moust click in the graphic area and click on Split. The task form will pop up. Now right mouse click in the task form area and then click on one of the options. Good Luck. "Kathleen" wrote: |
Automatically level resources unit work Posted: 01 Mar 2006 05:37 AM PST Hey Steve, Thanks for all that info! It has really helped. I understand Levelling a bit more now! "Steve House [Project MVP]" wrote: |
Part time resources? (newbie question) Posted: 01 Mar 2006 01:32 AM PST Thanks Steve for answering! (Actually I found out the answer by myself 10 minutes ago - Sometimes lost, but not always...) /Jarl |
Updating schedules sharing resource pools Posted: 01 Mar 2006 12:00 AM PST Hi Sue OZ, You are welcome. Glad to know it worked and thanks for the feedback. Julie "Sue OZ" <microsoft.com> wrote in message news:com... |
Can't Restore Outline Structure Posted: 28 Feb 2006 10:06 PM PST Jan, Apparently MSP has a problem with a projector, which is what caused the problem. I was connected to a computer projector when I booted up. When I made the switch to the screen, the problem occurred. Solution: disconnect everything and reboot, THEN connect the projector to the computer, THEN make the screen switch if necessary. TomCat "Jan De Messemaeker" wrote: |
I want to write Project code - need ideas! Posted: 28 Feb 2006 05:42 PM PST Hi Glenn! This will be no problem. Email me at net and we can discuss it. Thanks, Rick Williams "Glenn Bosch" <Glenn microsoft.com> wrote in message news:com... |
Breakup Projects in Master File Posted: 28 Feb 2006 03:41 PM PST In article <com>, "annbklyn" <microsoft.com> wrote: Ann, Well, I think your issue is different from Hadi's. Hadi needs to break up a master file, it sounds like you need to create one. It also looks like DavidC has provided a couple of viable approaches. If you have further questions, please let us know. John |
Tracking costs by percent complete does not work!! Posted: 28 Feb 2006 03:33 PM PST In article <googlegroups.com>, com wrote: eganders, I have to apologize for my opening comment in my original reply. After I wrote it and hit send, I realized that it wasn't very professional. I'm sorry. But something you mentioned above really caught me off guard. You mean 9 women can NOT do a baby in 1 month? Wow, I need to rethink my whole view of family planning ;-) One way to work around the case of material cost "polluting" the total cost is to create separate task lines for labor and material. The total cost value at the top level will of course include all cost types, but at least at the task level, labor is isolated, and its also possible to use the Grouping feature to sum costs up separately. The reason 100% complete gives 100% value is because 100% in the % Complete field guarantees the % Work Complete field is also 100%. That same relationship may or may not hold for values less than 100%. If a resource is assigned at 100% for the full time the task spans the the two % complete fields will track one for one. For example let's say a task is 40 hours duration and Joe is assigned to work it at 100%. The Work field then also becomes 40 hours and 50% entered into the % Complete field or the % Work Complete field will yield a value of 50% in the Cost field for that task, assuming the task has labor only. Hopefully this clarifies it further. John Project MVP |
How do I unhide the 'Task Name' column in Project 2003 ? Posted: 28 Feb 2006 02:19 PM PST Maybe, Trevor, but it certainly isn't the first time it's been asked :) Mike Glen Project MVP Trevor Rabey wrote: |
Posted: 28 Feb 2006 01:41 PM PST Hi I need to produce a weekly/monthly report by Client, project and resources allocated to the project of the Client. What's the best reporting format i can use in the Report Tool? Do i have to customized? Currently my project plan is in this hierarchy: 2006 Scope of Work-1st level Audi (Client) - 2nd level Project 1- 3rd level Project 2- 3rd level Project 3- 3rd level Time Warner (Client) - 2nd level Project 1- 3rd level Project 2- 3rd level Project 3- 3rd level I will assign resources for each project and resources are shared. How can i report on this for the Client to see how each project is doing and how many hrs the resources are working for each project. Help! THanks, Ann -- Thanks! "Jermyca" wrote: |
How do I contact microsoft without paying $35? Posted: 28 Feb 2006 12:41 PM PST Hi daredo222 , Welcome to this Microsoft Project newsgroup :) What's your problem? Can we help? FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP daredo222 wrote: |
WBS elements - I recall they are never to be below 40 hours???? Posted: 28 Feb 2006 11:11 AM PST Hi, I doubt this is ever published as a guidance. It may be true in most projects but some projects (like moving and reinstalling a server room) sometime must be done within 48 hours - with tasks averaging 1 hour. HTH -- Jan De Messemaeker, Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ For FAQs: http://www.mvps.org/project/faqs.htm "ProjectMGR" <microsoft.com> schreef in bericht news:com... that |
Posted: 28 Feb 2006 07:42 AM PST John, Thanks yet again for your advise. Regards Figen "John" wrote: |
why did task line change to blue in MSP2003 ? Posted: 28 Feb 2006 06:30 AM PST In article <com>, "canus86" <microsoft.com> wrote: canus86, Wow, I like the easy ones, and, you're welcome. John |
Can you change the Duration to Calendar Days? Posted: 28 Feb 2006 05:57 AM PST Perfect. That is exactly what I needed. Thanks a lot!! "John" wrote: |
No resources in resource center,how to add? Posted: 28 Feb 2006 05:00 AM PST Hi Stefan, Try posting on the server newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Mike Glen Project MVP Stefan wrote: |