Start date Project 98 Microsoft Project |
- Start date Project 98
- Military Time - 24 hour clock
- Working Days and Non-Working Days
- Relationship of Task Type and Effort Driven
- Project file as a web page
- MS Project lacks basic project management features!
- Hide the Duration, Start & Finish data of Project Summary Tasks?
- is it possible to make the link lines run diagonally
- Project 2003 reporting experiences
- Admin projects - Use and best practice
- Truly Zoom Out Columns--See all Tasks on One Screen
- Extracting data from Project Server
- Is it possible to customize Network Diagram boxes?
- How to keep duration and work fixed
- Displaying a full calendar year although Project is smaller
- Can't change row height in standard Gantt Chart
- Rebaselining tasks
- Are there any UK MSP focus groups?
- MS Project linking from other .mpp source file
- Who, how & where can actual hours be entered for a missing resourc
- How do I set a What-If scenario based on 150% remaining work?
- Task Bar Sizes
- MPP files
- scheduled work till the status date
Posted: 15 Jan 2006 08:56 AM PST You're welcome, Docschmo :-) Mike Glen MS Project MVP Docschmo wrote: |
Posted: 14 Jan 2006 10:17 AM PST Hi SheriTingle, Project will accept an entry of 13:00 without any change required. It will display as 1:00 pm however. You can change the format to military time through the Control Panel > Regional and Language options. On the Regional Options tab click the Customize button. In the Customize Regional Options click the Time tab and select the date form HH:mm:ss or H:mm:ss. This will apply to all programs. I hope this helps. Let us know how you get along. Julie "SheriTingle" <microsoft.com> wrote in message news:com... |
Working Days and Non-Working Days Posted: 14 Jan 2006 07:55 AM PST In article <com>, "Mike" <microsoft.com> wrote: Mike, Depending on how many of the non-working days you want to be working, you can use one of two approaches. Either go to Tools/Change Working TIme and make the necessary modifications, or select a 24 Hours Calendar for your project. Hope this helps. John Project MVP |
Relationship of Task Type and Effort Driven Posted: 13 Jan 2006 12:56 PM PST Hi BJH, Welcome to this Microsoft Project newsgroup :) You might like to have a look at my series on Microsoft Project in the TechTrax ezine, particularly #11 - Task Types, at this site: http://tinyurl.com/2xbhc or this: http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 (Perhaps you'd care to rate the article before leaving the site, :) Thanks.) FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP BJH wrote: |
Posted: 13 Jan 2006 11:23 AM PST Hi Abe, Make sure some of the Gantt Chart is actually showing on the screen. Mike Glen Project MVP Abe wrote: |
MS Project lacks basic project management features! Posted: 13 Jan 2006 08:29 AM PST Hi Ace, Welcome to this Microsoft Project newsgroup :) I think the problem exists because of a different understanding of the word "Project". In MS Project's design is the universal definition of a project being a unique undertaking with a clearly definable start and finish, requiring the management of money materiel and men. It thus uses the Critical Path Method for project scheduelling. In your case, you seem to be running a production line of some sort. MS Project is designed to help plan and schedule for production of the first bird house or wedding cake, but not a series of them. For that you need production software of some sort. That does not mean you can't use Project for what you're doing, but you will run in to the sorts of problems you're seeing. There's no inventory control, no means of Project guessing which resource to use (you have to do that) and certainly no optimization facilities other than trial and error. MS Project is just not designed for that. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Ace Frahm wrote: |
Hide the Duration, Start & Finish data of Project Summary Tasks? Posted: 13 Jan 2006 05:56 AM PST Yes! (Assuming your background is also white!) Mike Glen Project MVP Trevor Rabey wrote: |
is it possible to make the link lines run diagonally Posted: 13 Jan 2006 12:16 AM PST Garath wrote: It's not possible in Project to make the link lines diagonal in the Gantt view. That's what the Network Diagram is for. Unfortunately, it is not formatted very well in default settings and is confusing. A bit of playing with it to simplify it makes a big difference. Hope this helps in your world. |
Project 2003 reporting experiences Posted: 12 Jan 2006 10:12 PM PST Thanks Rod - I appreciate your feedback. Would you consider this task (as I outlined previously) difficult for someone with only basic visual basic scripting knowledge, more importantly would I need high VBA skill levels to take this on? Thankyou. Nick "Rod Gill" wrote: |
Admin projects - Use and best practice Posted: 12 Jan 2006 03:03 PM PST Hi Nock, Try posting on the server newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Mike Glen Project MVP Nock wrote: |
Truly Zoom Out Columns--See all Tasks on One Screen Posted: 12 Jan 2006 01:56 PM PST Hi Cory, Could you possibly filter the project to show summaries only? Or perhaps different outline levels? At least this would give the overview without the detail, which you woul'd be able to decipher anyhow. Mike Glen Project MVP Cory Siansky wrote: |
Extracting data from Project Server Posted: 12 Jan 2006 01:21 PM PST Hi John, Next time, try posting on the server newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Mike Glen Project MVP johnschmitt wrote: |
Is it possible to customize Network Diagram boxes? Posted: 12 Jan 2006 11:06 AM PST You're welcome and thanks for the feedback. Julie "Baggy" <microsoft.com> wrote in message news:com... |
How to keep duration and work fixed Posted: 12 Jan 2006 10:22 AM PST Tools, Options, Schedule type and select default task type. However in over a decade of using Project I still find Fixed Units to be the most flexible type. -- Rod Gill Project MVP Visit www.msproject-systems.com for Project Companion Tools and more "MikeR" <microsoft.com> wrote in message news:com... |
Displaying a full calendar year although Project is smaller Posted: 12 Jan 2006 09:17 AM PST Hi Darren, You're welcome and thanks for the feedback. Don't feel silly at all. It's somewhat of an odd place to put it. Most would look in the Page Setup dialog box. Julie "Darren Broadhead" <microsoft.com> wrote in message news:com... |
Can't change row height in standard Gantt Chart Posted: 12 Jan 2006 08:21 AM PST Hi Dave, You are very welcome and thanks for the spirited feedback. ;-D Julie "Dave_in_Delaware" <microsoft.com> wrote in message news:com... |
Posted: 12 Jan 2006 07:30 AM PST Hi Dave, You're welcome and thanks for the feedback and clarification. I have tried to quickly reproduce the problem you describe and have been unable to. I am using Project 2003 with SP2 installed. You can check your installation SP by choosing Help > About Microsoft Office Project. On the top line of the dialog box, after the Microsoft Office Project release information you should also see Service Pack info. I don't know of any option that would cause a rebaseline to change the % complete of any task. I'll keep hacking about and if I can reproduce the problem I'll post again. Julie "Dave" <microsoft.com> wrote in message news:com... |
Are there any UK MSP focus groups? Posted: 12 Jan 2006 05:37 AM PST Hi Betina, Welcome to this Microsoft Project newsgroup :) As a Brit, I regularly attended the original Project User Group (PUG) which was started in the UK and was very active. However, it has since been taken over by the later MSPUG in the sUSA. It is now just a chapter of the MSPUG and, as far as I know, is now defunct in the UK. If you find any active PUGs in the UK, I would like to know :) FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP jspargo wrote: |
MS Project linking from other .mpp source file Posted: 12 Jan 2006 05:29 AM PST Hi Frank, You're welcome for the assistance thus far and thanks for the additional information. If you only wish to show information on "main" tasks in one file, it may be a whole lot easier to just work with filters in the one file to filter out the tasks you don't wish to see. Take a look at the filter called Summary Tasks. You can also choose which level of tasks (Outline Level 1 - the "main" or top level summary tasks, Outline Level 2 - next level tasks down, etc) by selecting the Outline level from the Show drop down on the Formatting toolbar. Again, if this is only from one project, it is much more efficient to work with just the one file. If you want to see "main" tasks from several files, you can create a master through Insert > Project and still use the filtering or Outline level option as needed. I hope this helps. Let us know how you get along. Julie "Frank" <microsoft.com> wrote in message news:com... |
Who, how & where can actual hours be entered for a missing resourc Posted: 11 Jan 2006 03:11 PM PST I appeciate the information and will try it. Thanks "Dale Howard [MVP]" wrote: |
How do I set a What-If scenario based on 150% remaining work? Posted: 11 Jan 2006 11:19 AM PST In article <googlegroups.com>, "IMAFriend" <net> wrote: Doug, In Project Work and Duration are two separate things. Duration is the time span during which a task is performed. In Project it is usually expressed in working time (assuming a normal calendar with 8 hour days and 5 day weeks). On the other hand, Work is the total effort expended by one or more resources to actually accomplish the task. If a single resource is assigned full time to a given task, then and only then, the Duration and Work will be the equal. So adding 50% to the remaining workload is not necessarily the same as adding 50% to the remaining duration. Trying to read between the lines, it sounds like your boss simply wants to capture the original plan so it can be compared to the current working schedule as the plan is executed. This is called baselining and any good planning/scheduling application (e.g. MS Project) has this feature built-in. It also sets up the basis for classical earned value metrics. None of this requires any customizing of spare fields. You might be interested in fellow MVP, Mike Glen's series on Project lessons and techniques. A link to Mike's lessons can be found on: http://project.mvps.org/links.htm Hope this helps. John Project MVP |
Posted: 11 Jan 2006 10:02 AM PST In article <com>, "RA" <microsoft.com> wrote: RA, You're welcome. John |
Posted: 11 Jan 2006 09:21 AM PST Hi RJS and Babar, Just to clarify. Project Professional is not required -- Project Standard will do. It will need to be installed on all machines (home and work) to be able to read the Project (MPP) files. Julie "Babar" <com> wrote in message news:googlegroups.com... |
scheduled work till the status date Posted: 11 Jan 2006 05:11 AM PST You're welcome Michael and thanks for the feedback. Julie "Hans Wurst" <microsoft.com> wrote in message news:com... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |