% complete vs. % work complete? Microsoft Project |
- % complete vs. % work complete?
- How do I save a Project file with only schedule data?
- Resource Usage View Precision
- How can I disable "Work Contour" automatic updates in MS Project?
- Formulas-customize fields
- Assigning costs to various resources and material to one task
- Non-Effort-Driven schedules
- Correct Formula
- Problem with Gantt View
- Resource Usage Chart (how to NOT display zero hours worked)
% complete vs. % work complete? Posted: 16 Jan 2006 09:23 PM PST Adding a bit to Mike's explanation - Looking beyond the immediate question and trying to get to what you boss is actually looking for, comparing percent complete at some point to what your schedule if followed to the letter says you'd be at that point doesn't really tell you whether you're on-schedule or on-budget or not because in itself it's an incomplete picture. If the goal is to monitor progress, to see if you're on-target or falling behind, you should look a little deeper into something called Earned Value which monitors work actually achieved and dollars actually spent by a selected status date versus what you originally had scheduled to occur by that date and it gives you some tools to extrapolate those values to come up with a predicted actual completion date and predicted actual cost. There's a good discussion under Earned Value in the Project help files to get you started in the right direction. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "AlisonH" <microsoft.com> wrote in message news:com... |
How do I save a Project file with only schedule data? Posted: 16 Jan 2006 03:52 PM PST Thanks, you answered my question though I was hoping for something more transparent and built in by MS. I will check out the Scrub VBA in detail. The Scrub description looks like it is a little different than what I want but could be modified for my needs. However, I have run into a problem sometimes when deleting resource assignments in that it changes my schedule by the formula. It looks like it only happens to tasks that were already in progress. So I have to figure out how to set up tasks so that their schedule is not affected by deleting the assigned resources. I'm just a little surprised this isn't built in to MS Project because it seems like something any company that works with layers of subcontractors would want so all the subcontractors can provide Project files that get integrated into a prime contractor's master schedule. Without each subcontractor divulging their individual pay rates, resource assignments, etc... Thx Ed "John" wrote: |
Posted: 16 Jan 2006 12:41 PM PST In article <com>, "MikeR" <microsoft.com> wrote: Mike, Just a followup to Catfish's reply. You might want to take a look at the "yze timescale data in Excel" utility/add-in found on the "ysis" toolbar. You will get slightly different results (i.e. format) by exporting from either the Resource or Task Usage views. Of course with a custom VBA macro, Project data can be exported and formatted in virtually any form needed. John Project MVP |
How can I disable "Work Contour" automatic updates in MS Project? Posted: 16 Jan 2006 06:56 AM PST I suggest you change the task type to "Fixed Units" and have 4 columns: Start, Actual Start, Finish & Actual Finish. I give the task an actual start then I can either change the duration to project a finish or type in a projected "Finish" date. Good Luck "Carine" wrote: |
Posted: 16 Jan 2006 04:51 AM PST Thank you for your answer. I have two follow up questions for you. Can you describe what you mean with: "prone to corruption...." It this method unstable or is it other problem you have experienced. And the next question: The solution using VBA code. Is it difficult to make? I have done some VBA-coded macros in Excel before where I teached myself using record functions and learned the code from these automatic functions. Can you give me some advice or list some functions I will need. Eg. how to get access to alter Projects basic fields..... and how to automaticly run macros when changing values in certain fields. John skrev: |
Assigning costs to various resources and material to one task Posted: 15 Jan 2006 08:48 PM PST In article <com>, "Freeman" <microsoft.com> wrote: Freeman, You're welcome. John |
Posted: 15 Jan 2006 05:00 PM PST You're welcome, MJ and thanks for the feedback. :-) Mike Glen MS Project MVP mjkahn wrote: |
Posted: 15 Jan 2006 03:34 PM PST David, Thanks so much for your help with this. You have been a life saver. It6 really would be nice if Microsoft added these features to the Program. It would be so useful as a presentation tool for my clients that aren't versed in the program and have only a basic knowledge of a schedule. Regards, Charles "DavidC" wrote: |
Posted: 14 Jan 2006 10:16 AM PST Hi TDK, Glad you got it sorted. :) SR2 is the Service Release 2 (SR1 corrected an indenting bug). Mike Glen Project MVP TKD wrote: |
Resource Usage Chart (how to NOT display zero hours worked) Posted: 13 Jan 2006 08:20 AM PST I fully understood what you wanted, Kellie, but a sound project file has nothing at all in the cells unless you put it there. All mine are blank which leads me to believe there's something wrong with your file. Try a new project and see if you get zeros all over the place. Mike Kellie F. wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |