Using Cusotm Fields (Date and Duration) to Track Progress Microsoft Project |
- Using Cusotm Fields (Date and Duration) to Track Progress
- duration confusion
- URGENT -- Resources, Duration and Start/End Date Problem
- Can the deadline be set to match the date of another task?
- Calanders
- can project autoassign?
- how do i use a timeline based on minutes and secounds
- Is it possible to run multiple versions of Project on one machine?
- change color of task font to show when it is overdue
- How do I keep WBS numbers from restarting when I insert a subproje
- Total Cost
- Custom field formula #error
- Master / Sub Projects - Help with Setup & Update Process needed
- Work vs Actual Work
- Read Only Enterprise Custom Field?
Using Cusotm Fields (Date and Duration) to Track Progress Posted: 09 Nov 2005 06:50 AM PST In article <com>, "kimmerj" <microsoft.com> wrote: Kimmerj, You're welcome. John |
Posted: 08 Nov 2005 07:29 PM PST Hi Allison, No but you can create one. Customize a duration field using the ProjDateDiff formula. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Allison" <microsoft.com> schreef in bericht news:com... day assign have I hours 14 days. |
URGENT -- Resources, Duration and Start/End Date Problem Posted: 08 Nov 2005 03:16 PM PST In article <com>, "myoregon" <microsoft.com> wrote: Debra, You're welcome. John |
Can the deadline be set to match the date of another task? Posted: 08 Nov 2005 02:46 PM PST There is only one deadline field. How you access it is irrelevant. Insert the column "Deadline" to see deadline cells you can paste in. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Jabir" <microsoft.com> schreef in bericht news:com... 'Deadline:' specifically just of a This |
Posted: 08 Nov 2005 02:01 PM PST Hi, What exactly do you mean? Microsoft Project does not open "with a calendar" Each Project has several calendars one of them being the project calendar I told you how to make a calendar you make the project calendar for each new project. What else do you want? -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Tony F" <microsoft.com> schreef in bericht news:com... I Thanks with? I able a the task caalulated dates. |
Posted: 08 Nov 2005 11:44 AM PST In article <#phx.gbl>, "Andy Barnhart" <andyDOTbarnhart@ciincDOTcom> wrote: Andy, Dave is correct, Project doesn't have an "auto-assign" feature but that functionality could be developed as a VBA macro. As long as you can develop the assignment algorithm, the VBA code can do the rest. Granted, this approach isn't of much use to someone new to Project, particularly if you have no VBA experience, but it nonetheless is an option. John Project MVP |
how do i use a timeline based on minutes and secounds Posted: 08 Nov 2005 10:53 AM PST That's what I was afraid of; thanks and I appreciate the response, Jack. "JackD" wrote: |
Is it possible to run multiple versions of Project on one machine? Posted: 08 Nov 2005 10:48 AM PST In article <com>, "Jmaestan" <microsoft.com> wrote: Jmaestan, During the Project 2003 install process, the installer will give some options to preserve or overwrite previous installations. Pick the option that allows Project 2000 to remain. John Project MVP |
change color of task font to show when it is overdue Posted: 08 Nov 2005 10:29 AM PST Go to the project mvp site and look at the vba references. http://mvps.org/project also both of my sites have information and examples -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. "Tina S" <com> wrote in message news:com... learn. with say...RED, when |
How do I keep WBS numbers from restarting when I insert a subproje Posted: 08 Nov 2005 08:50 AM PST In article <com>, "Mg" <microsoft.com> wrote: Mg, You're welcome. If those suggestions don't work or you need additional help, please post again. John Project MVP |
Posted: 08 Nov 2005 08:01 AM PST In article <com>, Deb <microsoft.com> wrote: Deb, I'm not sure what you mean by, "...cost resulting from the work and duration...". Cost is not related to duration in any way. In Project costs are either, Work x resource rate, Material units x material rate, or Fixed Costs. Again, without knowing the exact fields you reference (e.g. are you looking at Baseline Cost?), it is hard to tell what is going on although Jan's suggestion that there are separate costs on the Summary Lines is a very real possibility. John Project MVP |
Posted: 08 Nov 2005 06:46 AM PST In article <com>, "sylva" <microsoft.com> wrote: Sylva, You didn't specify if you are using the Deadline field for your deadline data but try this formula: IIf(isdate([Deadline]-10),"yes","no") Hope this helps. John Project MVP |
Master / Sub Projects - Help with Setup & Update Process needed Posted: 08 Nov 2005 04:02 AM PST In article <com>, "Ian Gray" <microsoft.com> wrote: Ian, Think about that "great minds and great ideas" axiom. I suggested Excel because almost everybody either has it or a compatible alternative. Not everybody has Project. By all means, if all stakeholders in your organization have Project, then updating their separate plans would allow more flexibility. John Project MVP Great ideas aren't worth a damn unless there are people to implement them. |
Posted: 07 Nov 2005 10:59 PM PST Gérard, Thanks for the speedy response. However you seem to have overlooked the first question: Where can I find a detailed description of, and the logic relating to, how the Work field is affected when I enter values into the Actual Work field? Regards Peter "Gérard Ducouret" wrote: |
Read Only Enterprise Custom Field? Posted: 07 Nov 2005 02:23 PM PST Ok thanks, I'll try posting there |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |