Pages

Search

Using Cusotm Fields (Date and Duration) to Track Progress Microsoft Project

Using Cusotm Fields (Date and Duration) to Track Progress Microsoft Project


Using Cusotm Fields (Date and Duration) to Track Progress

Posted: 09 Nov 2005 06:50 AM PST

In article <com>,
"kimmerj" <microsoft.com> wrote:
 


Kimmerj,
You're welcome.

John

duration confusion

Posted: 08 Nov 2005 07:29 PM PST

Hi Allison,

No but you can create one.
Customize a duration field using the ProjDateDiff formula.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Allison" <microsoft.com> schreef in bericht
news:com... 
day 
assign 
have 

hours 
14 
days. 


URGENT -- Resources, Duration and Start/End Date Problem

Posted: 08 Nov 2005 03:16 PM PST

In article <com>,
"myoregon" <microsoft.com> wrote:
 


Debra,
You're welcome.

John

Can the deadline be set to match the date of another task?

Posted: 08 Nov 2005 02:46 PM PST

There is only one deadline field. How you access it is irrelevant.
Insert the column "Deadline" to see deadline cells you can paste in.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Jabir" <microsoft.com> schreef in bericht
news:com... 
'Deadline:' 
specifically 
just 
of a 
This 


Calanders

Posted: 08 Nov 2005 02:01 PM PST

Hi,

What exactly do you mean?
Microsoft Project does not open "with a calendar"
Each Project has several calendars one of them being the project calendar
I told you how to make a calendar you make the project calendar for each new
project.
What else do you want?

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Tony F" <microsoft.com> schreef in bericht
news:com... 

Thanks 
with? I 
able 

the 
task 
caalulated 
dates. 


can project autoassign?

Posted: 08 Nov 2005 11:44 AM PST

In article <#phx.gbl>,
"Andy Barnhart" <andyDOTbarnhart@ciincDOTcom> wrote:
 

Andy,
Dave is correct, Project doesn't have an "auto-assign" feature but that
functionality could be developed as a VBA macro. As long as you can
develop the assignment algorithm, the VBA code can do the rest. Granted,
this approach isn't of much use to someone new to Project, particularly
if you have no VBA experience, but it nonetheless is an option.

John
Project MVP

how do i use a timeline based on minutes and secounds

Posted: 08 Nov 2005 10:53 AM PST

That's what I was afraid of; thanks and I appreciate the response, Jack.

"JackD" wrote:
 

Is it possible to run multiple versions of Project on one machine?

Posted: 08 Nov 2005 10:48 AM PST

In article <com>,
"Jmaestan" <microsoft.com> wrote:
 


Jmaestan,
During the Project 2003 install process, the installer will give some
options to preserve or overwrite previous installations. Pick the option
that allows Project 2000 to remain.

John
Project MVP

change color of task font to show when it is overdue

Posted: 08 Nov 2005 10:29 AM PST

Go to the project mvp site and look at the vba references.
http://mvps.org/project

also both of my sites have information and examples

--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
"Tina S" <com> wrote in message
news:com... 
learn. 
with 
say...RED, 
when 


How do I keep WBS numbers from restarting when I insert a subproje

Posted: 08 Nov 2005 08:50 AM PST

In article <com>,
"Mg" <microsoft.com> wrote:
 


Mg,
You're welcome. If those suggestions don't work or you need additional
help, please post again.

John
Project MVP

Total Cost

Posted: 08 Nov 2005 08:01 AM PST

In article <com>,
Deb <microsoft.com> wrote:
 

Deb,
I'm not sure what you mean by, "...cost resulting from the work and
duration...". Cost is not related to duration in any way. In Project
costs are either, Work x resource rate, Material units x material rate,
or Fixed Costs.

Again, without knowing the exact fields you reference (e.g. are you
looking at Baseline Cost?), it is hard to tell what is going on although
Jan's suggestion that there are separate costs on the Summary Lines is a
very real possibility.

John
Project MVP

Custom field formula #error

Posted: 08 Nov 2005 06:46 AM PST

In article <com>,
"sylva" <microsoft.com> wrote:
 

Sylva,
You didn't specify if you are using the Deadline field for your deadline
data but try this formula:
IIf(isdate([Deadline]-10),"yes","no")

Hope this helps.
John
Project MVP

Master / Sub Projects - Help with Setup & Update Process needed

Posted: 08 Nov 2005 04:02 AM PST

In article <com>,
"Ian Gray" <microsoft.com> wrote:
 


Ian,
Think about that "great minds and great ideas" axiom.

I suggested Excel because almost everybody either has it or a compatible
alternative. Not everybody has Project. By all means, if all
stakeholders in your organization have Project, then updating their
separate plans would allow more flexibility.

John
Project MVP
Great ideas aren't worth a damn unless there are people to implement
them.

Work vs Actual Work

Posted: 07 Nov 2005 10:59 PM PST

Gérard,

Thanks for the speedy response. However you seem to have overlooked the
first question:

Where can I find a detailed description of, and the logic relating to, how
the Work field is affected when I enter values into the Actual Work field?

Regards
Peter

"Gérard Ducouret" wrote:
 

Read Only Enterprise Custom Field?

Posted: 07 Nov 2005 02:23 PM PST

Ok thanks, I'll try posting there