Task Definitions Microsoft Project |
- Task Definitions
- Circular relationship - cannot find task
- renaming the fields in project web access
- How do I convert Microsoft Project Gantt chart to .pdf format?
- Modifying RBS in Project Prof 2003 Global Template.
- Filter the start by two weeks starting the current date
- Resouce Names in Alphabetical Order
- Migration of EPM from Server to Server
- Automatically update projects when their base template changes
- Integrating Microsoft Project and Microsoft Excel
- When I link dependencies, dates/Gantt bars do not shove out
- Master File
- how do i integrate project professional 2003 with outlook 2003
- Glossary
- Monday to Friday default working hours?
Posted: 22 Feb 2005 06:01 AM PST A couple of things to know about. First of all, note the basic equation Project always follows W=U*D, Work equals Units times Duration. This is always - always - going to be true. 32 man-hours Work = 32 hours Duration * 100% Units or it could also be 64 hours Duration * 50% Units or some other combination. Second, if you assign 2 resources to a task at 30% and 70% respectively, it does NOT mean that they are splitting the work 30/70. 30% means that 30% of the time the resource is spending on the task is converted to useful work. If the task duration was 3 days, 24 hours, and you assign a resource to it at 30%, his attention is divided between the task at hand and other things and so he will do 8 man-hours of work on this particular task over a three day period. In other words, he will get done in 3 days what he COULD have done in 1 day if he didn't have any distractions. Third, the task type determines what happens when you EDIT resource assignments that have already been made. I have Joe assigned 100% to a task that takes 5 days, 40 hours. Becuase he's assigned 100%, the work he's producing is also 40 man-hours. But never ever forget that hours of work and hours of duration are two completely different, albeit related, critters. I now edit his assignment, changing the Units to 50%. I could be doing that for a couple of reasons. One is that it is really a 20 man-hour task but I don't need it done any sooner than Friday so I'll let him work on it at his leisure over the 5 days duration. Makes the task Fixed Duration, change the assignment, and Project recalculates Work. Or it could be that this task really does require 40 man-hours of work but I have some other priorities and prefer Joe to work 4 hours a day on this task and 4 hours a day on something else. I make the task Fixed Work, edit the assignment, and Project recalculates the Duration to be 10 days - it'll take him longer to get the work done but my other priorities dictate I'll just have to live with it. So to your example. Before going further the first question to ask is what do you mean by it being a 32 hour task, if it's work how do you KNOW it's a 32 man-hour task and where did you enter that fact into Project? When you want to split the work between the two resources do you want one guy to work on it for a while and then the other take over or do you want them to work together until the first guy finishes his part of the work and then the other works on alone or do you want the 70% guy to work full speed while the other works part of each day along with him, or just what are you looking for in the schedule? It's possible to do all of those things but you have to decide first where you want to end up. In other words, 32 man-hours split 70/30 isn't enough information to set up the scenario. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "JohnB" <microsoft.com> wrote in message news:com... |
Circular relationship - cannot find task Posted: 22 Feb 2005 03:49 AM PST Hi, You are looking at a resource pool, not the project file. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Vivek ARORA" <Vivek microsoft.com> schreef in bericht news:com... the blank. views. +1 2090 |
renaming the fields in project web access Posted: 22 Feb 2005 12:59 AM PST P.hamsa -- This is no possible. Sorry. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "P.hamsa" <microsoft.com> wrote in message news:com... |
How do I convert Microsoft Project Gantt chart to .pdf format? Posted: 21 Feb 2005 07:57 PM PST Hi, The wizard is a 2003 feature. It is not very useful since clicking the camera icon does about the same. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Kenneth Gorelick" <net> schreef in bericht news:BE40972B.37C5%net... Excel", powerpoint, be no presentation |
Modifying RBS in Project Prof 2003 Global Template. Posted: 21 Feb 2005 11:25 AM PST Mark -- You may need to set new values for some or all the resources in the Enterprise Resource Pool. Each project should be reopened and published. The next time the OLAP cube rebuilds, the new values in the RBS field will be reflected in any Portfolio Analyzer views you have created. Just some thoughts. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "Mark Byington" <com> wrote in message news:com... |
Filter the start by two weeks starting the current date Posted: 21 Feb 2005 11:01 AM PST Hello Gérard Yes, I am doing the date range. But each time my stakeholder have to specify the current date which is the from date. I am not sure if I can write the code. Please advise Thanks "Gérard Ducouret" wrote: |
Resouce Names in Alphabetical Order Posted: 21 Feb 2005 07:49 AM PST Hi Carrie, 1. View Resource sheet; Project, Sort, Sortby... Name and check ON "Permanently renumber resources" 2. Not very important I'm afraid. There is a grouping option "By resource group" but for everything else it is not more important than f.i. Text1 HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Carrie" <microsoft.com> schreef in bericht news:0aef01c5182c$f095e470$gbl... |
Migration of EPM from Server to Server Posted: 21 Feb 2005 06:29 AM PST Mark -- One approach would be to back up the test database and then restore it to your production database. This way, you would retain your Enterprise Global (including all enterprise Fields, Views, Tables, Filters, Groups, Reports, etc.), your Enterprise Resource Pool, the RBS, and all Project Server settings. I will invite others to comment as well. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "Mark Byington" <com> wrote in message news:com... |
Automatically update projects when their base template changes Posted: 20 Feb 2005 12:49 PM PST When you build a project file from a template all it does is make a copy of the template and change the extension. There is no persistent link remaining after the new file is created. Sorry, you're going to have to edit the subprojects by hand individually. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "WilsonJ" <microsoft.com> wrote in message news:com... |
Integrating Microsoft Project and Microsoft Excel Posted: 20 Feb 2005 10:33 AM PST Thanks!! John "John" wrote: |
When I link dependencies, dates/Gantt bars do not shove out Posted: 20 Feb 2005 06:53 AM PST Jan, Thank you. That is what it was. I have not worked with MSP in almost 3 months and am having to again. I had forgotten about the calculation tab in Tools-Options. Thank you, thank you, thank you. obvious idea that Calculation) does relationship between want to move. fiddle with dates verify. |
Posted: 19 Feb 2005 10:28 PM PST Thanks "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message news:phx.gbl... tasks, a and |
how do i integrate project professional 2003 with outlook 2003 Posted: 19 Feb 2005 08:17 PM PST Thanks for the information. I still have a small problem now. I have done all that was mentioned in the knowledge base on editing the registry and adding the workgroup key. But the link to workgroup is not displayed in project or for that matter theres no additional link that is visible after editing. is there something else that i am missing out other than editing the registry and installing the add in. Thanks "Steve House [MVP]" wrote: |
Posted: 19 Feb 2005 08:52 AM PST Hi , Welcome to this Microsoft Project newsgroup :-) Search Help for Glossary and there is an option to Print. I've never done this so I don't know if it prints just the page you're viewing or the whole thing! FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :-)) Mike Glen MS Project MVP The Empowerment Group wrote: |
Monday to Friday default working hours? Posted: 19 Feb 2005 07:00 AM PST Pretty much to make your life easier, you should make all of your calendar changes to the "change working time" dialog. Remember, there are possibly 3 calendars that can affect the scheduling of your task, the task calendar if you give it a specific one (if not it defaults to the standard calendar), a resource calendar if you have resources assigned to your task, and the project calendar. HTH "Mykl" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |