Show differences from baseline? Microsoft Project

Show differences from baseline? Microsoft Project


Show differences from baseline?

Posted: 03 Feb 2005 07:01 AM PST

You're welcome Bill. Thanks for the feedback.
Julie

"Bill Meacham" wrote:
 

Does Project 2000 have a reader?

Posted: 03 Feb 2005 06:23 AM PST

The easiest solution is to use Adobe Acrobat or a freeware pdf writer to
save selected views as a pdf file to then distribute the the users.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"Briarpatch" <microsoft.com> wrote in message
news:com... 

Why can't I display the "Duration" field in "Resource Usage" view?

Posted: 03 Feb 2005 06:13 AM PST

Hiya:

I suppose it could but I wonder what it would mean in terms of the project
metrics. Does knowing that Joe's duration is 3 days and Bill's duration is
5 help me meet the schedule requirements? Certainly it impacts the resource
work load and hence the cost but the usage views already include the work
and cost data so it seems redundent.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message
news:%phx.gbl... 

If compared to NIKU's open workbench,

Posted: 02 Feb 2005 09:25 PM PST

I haven't seen any market share numbers for scheduling software in
years. But I doubt they've changed much. At that time, Project was
between 80 and 85%. Doesn't leave much for all the others! I believe
this was U.S. numbers. Don't recall seeing any other numbers.

looking for picture that decribes *yes*.

Posted: 02 Feb 2005 06:15 PM PST

There are the traditional Happy and Sad faces. Also the red circle with a
slash through it is fairly well recognized.

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

..
"jenrow" <microsoft.com> wrote in message
news:com... 


Adjust dates Macro

Posted: 02 Feb 2005 02:07 PM PST

You're welcome, 57chevy :-) and thanks for your kind words. For the benefit
of others, here's the link you mentioned: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23

Mike Glen
MS Project MVP



57chevy wrote: 



Exporting tasks to Excel, but not summaries

Posted: 02 Feb 2005 01:19 PM PST

As I mentioned earlier, you should explicitly filter for summary tasks using

Summary equals no.

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

..
"RTucker" <microsoft.com> wrote in message
news:com... 
up 
no 
the 
the 
request 


Team Member updating remaining work after task completion date

Posted: 02 Feb 2005 01:03 PM PST

Stephen --

This is definitely a training and performance issue. Teach your people to
do it right and then hold them accountable for this behavior. Hope this
helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"


"Stephen Smith" <Stephen microsoft.com> wrote in message
news:com... 


Successor task not immediately following predecessor task.

Posted: 02 Feb 2005 12:29 PM PST

Hi Tom,

Glad to have helped - however indirectly. Thanks for the feedback and let
us know if we can help again.

Julie

"Tom" wrote:
 

Exporting

Posted: 02 Feb 2005 12:06 PM PST

Hi Garry,

Welcome to this Microsoft Project newsgroup :-)

Please see FAQ Item: 16. Project Viewer.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP



Garry Murry wrote: 



Update

Posted: 02 Feb 2005 09:31 AM PST

Dale,
With an user admin im Approve timesheets I save de timesheets but desapear
in updates, I cannot update project plan, how update the project plan?

can you help me?

"Dale Howard [MVP]" wrote:
 

Task Queues

Posted: 02 Feb 2005 09:01 AM PST

Excellent! - the business implications of process decisions like that are
always best answered by someone who is intimately familiar with your current
business processes and can give you educated advice based on that in-depth
knowledge. The best we can do at a distance is generic discussions of
recommended best practices.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Howard Alsdorf" <microsoft.com> wrote in message
news:com... 

Scanned documents

Posted: 02 Feb 2005 08:15 AM PST

This group is for discussions on MS Project project managment software.
You'll have better luck getting an answer in groups devoted to Word or
imaging.


"emckay" <microsoft.com> wrote in message
news:com... 

Lead name after delegating task

Posted: 02 Feb 2005 06:39 AM PST

Daniel --

No. Sorry.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"


"Daniel Zitter - Matan Consulting" <cc> wrote in message
news:com... 


Text wrapping in the Task Name Field

Posted: 02 Feb 2005 06:29 AM PST

Hi,

Glad to have helped and thanks for the feedback.

Julie

"sfarris7" wrote: