Displaying duration in hours Microsoft Project |
- Displaying duration in hours
- How to change work without affecting duration
- Newbie: Report of Total Hours
- Problem with first task
- Planned work over a time period
- Transfering MS Project98 data to another PC
- SWITCH Formula
- Project measured in hours
- Science Lab Scheduling?
- Tasks causing overallocated resources
- Dates that change by themselves on emailed schedules
- splitting the task only lengthens the bar
- Filters on Text Fields
Posted: 07 May 2004 12:55 PM PDT Worked like a charm. Thanks! "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in message news:phx.gbl... can entered |
How to change work without affecting duration Posted: 07 May 2004 09:34 AM PDT You're welcome, David :-) Mike Glen MS Project MVP David Morrison wrote: |
Posted: 07 May 2004 09:32 AM PDT Hi Mark, Assign a dummy resource 100% to each task, then Work=duration Duration is never rolled up Alternative: set a formula dina field such as duration1 =[Duration] and have the summaries rolled uop. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Mark Jerde" <no.spam.net> schreef in bericht news:phx.gbl... |
Posted: 07 May 2004 08:20 AM PDT What time is it set to start? One "day" is 8 working hours by the standard calendar settings. If your task starts Wed at some time into the workday instead of right at the start of the day, and if the calendar shows hours of work less than 8 hours, one "day" of work won't be completed until well into the following day. The project calendar should show that actual hours of work while the value for hours per day in the Tools Options Calendar page should conform the the hours designated in the project calendar. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Chris" <uk.com> wrote in message news:c7g9gl$5q9$1$demon.co.uk... the |
Planned work over a time period Posted: 07 May 2004 04:32 AM PDT You didn't indicate how much or how little detail you want. Here's a start: 1. View | Resource Usage. RightMouseButton on the right side of the display and set the popup menu so that there is only a tick against Work. 2. RightMouseButton on the timescale at the top of the display, click on TimeScale and set the display to show months (I did it by setting both the middle and bottom tier Units to Months and the middle and bottom tier Count to 1. 3. Project | Group By ... and choose Work vs. Material. 4. The figures on the line labelled "Type:Work" are the numbers you want. You said you wanted days or man-months ... you'll have to some simple math to go from hours to days (divide by 8). JLB, PMP "Fredrik Sjoo" <microsoft.com> wrote in message news:9c6301c43426$f5fa9c20$gbl... |
Transfering MS Project98 data to another PC Posted: 06 May 2004 06:14 PM PDT All the data about a specific project is stored in one (large) file with the extension "mpp". If you have inserted projects and/or a resource pool file, those are normal mpp files as well linked to the project file. Templates are in files with the extension mpt. Global objects and personal settings are stored in the file GLOBAL.MPT. To locate the folders where your files reside in your computer, use the Windows Search utility and scan for all files with the filename "*.mpp". -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Jerry" <microsoft.com> wrote in message news:9a4c01c433e3$1dbb3f60$gbl... |
Posted: 06 May 2004 02:36 PM PDT "LUIS" <microsoft.com> wrote in message news:com... resources associated each one to a diferent number. The thing is i have a list of at least 45 resources and the formula marks an error and i think it is because the number of charachters. Is there another formula that i can use? Is there another way to lookup this values in a table? Here is what I would do. Open the resource view (the one with all the resources listed) insert one of the text columns. Put the number for each resource in the text column. Now the question is what are the numbers for and which context are they used in. If they are used in some sort of a resource view then you are done. If you are trying to use them in a task view you need to do something else, where the "something else" is to write a small visual basic macro to put the number where you need it. If you can tell us what the number is used for and why then the next step is easy. -Jack |
Posted: 06 May 2004 01:52 PM PDT Thanks! "Gérard Ducouret" <fr> wrote in message news:phx.gbl... dd/mm/ day/hour day. |
Posted: 06 May 2004 12:31 PM PDT Questions lead to questions...:-) First, No I don't know a good (or any) "production" scheduling tools - I havn't been in that business for some time - Google away and see what you come up with. Now regarding your projects - what are the limitations you would like to eliminate. There are lots of project gurus that hang out here. They or I might be able to help. Given the scope (size in terms of effort, duration, number of people, network complexity etc.) of your projects, the white board (or Excel) may be the way to go... In my work with teams, we ALWAYS start with post-it notes to ID deliverables/activities then sequence the post-its into a network. Some of those projects make it to MSP - some don't need to... so it is, to some extent a judgement call. Does putting the project into MSP add value? If so do it. If not don't. Unfortunatley, only you can answer that question. Mark "Conrad Santiago" <microsoft.com> wrote in message news:com... we are using the right tool for our project scheduling purposes. Using MSP, we are scheduling hundreds of projects a year. These projects have fixed due dates (although, many do slide). However, I do see limitations in MSP that would make my life easier. At times, I've felt using a white board to layout the projects would be more effective for me to plan in the future. as number it a (once can in an production board" wonder chances... classes that feasible and task |
Tasks causing overallocated resources Posted: 06 May 2004 11:18 AM PDT Thanks for your help everyone. I tried looking at the Resource Usage View again and tried to see if the tasks would be red if they were using overallocated resources. Again it only shows me the days a resource is overallocated and lists all the tasks under it, even if they don't really conflict. (I'm using Project 2002) I was hoping project would show me the exact tasks that overuse a resource and that overlap down to the minute. Here it lists them all if they just fall on the same day. Mitch, I tried that Oasys Scheduler add-in and it seems to work pretty good. It colors the tasks causing the overallocations red in the Gantt Chart View. Exactly what I wanted! It also has a resource leveling feature which seems to work better than the one that comes with Microsoft Project. I tried it on a huge project (1000+ tasks) and it actually leveled it. Project's leveling would just hang and do nothing. Thanks again. "Steve House" <send.hotmail.com> wrote in message news:<#phx.gbl>... |
Dates that change by themselves on emailed schedules Posted: 06 May 2004 11:00 AM PDT I had that problem once, and I believe it had something to do with settings on individual's computers. Do either of you have automatic leveling checked? tasks and are dates of the tasks dates of the tasks either of you connect Also been |
splitting the task only lengthens the bar Posted: 06 May 2004 06:29 AM PDT Hi John, Have a look at the Task Usage view and check for zeros where the split is occurring. You could try deleting and re-inserting the offending tasks. Otherwise, we need to discover whether your project is at fault, whether it is Project at fault, or whether it's your PC. Does the symptom occur with other projects on this PC? Does it occur with this project on other PCs? Does it occur with other projects on other PCs? Does your backup (you do have one don't you? :) ) have the same symptom? Mike Glen MS Project MVP microsoft.com wrote: |
Posted: 05 May 2004 02:51 PM PDT Justine, Gee with all that excitement maybe its a good thing I wasn't there. Glad I could help. John |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |