RAG reporting/Graphical indicators Microsoft Project |
- RAG reporting/Graphical indicators
- Total resources per day
- How to allowing view (or read) access to all projects?
- Underallocation of resource
- Replying to workgroup emails
- Can I import data from Excel into Project?
- Past Due Tasks
- Need help with resources
- Total Resource Cost
- Where'd my resources go?? Help!
RAG reporting/Graphical indicators Posted: 11 Jan 2006 05:31 AM PST Hi Paul, You're welcome and thanks for the feedback. Sorry, no, I know nothing about the other product. Julie "paul" <microsoft.com> wrote in message news:com... |
Posted: 10 Jan 2006 07:48 PM PST In article <com>, 3326ubb <com> wrote: 3326ubb, Project's leveling function can be limited to a selected span of time but not for a specified number of resources. So to answer your direct question, "no", but . . . there is generally always a way if you are willing and able. I'm not sure it would be worth the effort, but there should be a way to use a VBA macro to either, a) selectively employ time based leveling, or b) te the leveling function with a custom algorithm. If I were doing it, I would use the latter. I'm not sure this would help, but can you break the overall project into sections or phases wherein there are 40 or fewer resources associated with each? It will still require a significant amount of effort to monitor everything but then that's what a Project Manager does. Hope this helps. John Project MVP |
How to allowing view (or read) access to all projects? Posted: 10 Jan 2006 07:32 PM PST Nock -- In the future, please post your Project Server questions to the microsoft.public.project.server newsgroup, as this newsgroup is devoted to the Microsoft Project desktop application only. To answer your question, refer to the following FAQ: http://www.projectserverexperts.com/Shared%20Doents/OpenOtherProjectsReadOnly.htm Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com http://www.projectserverexperts.com "We wrote the book on Project Server" "Nock" <microsoft.com> wrote in message news:com... |
Posted: 10 Jan 2006 01:39 PM PST Hi Tim, You're welcome for the assistance thus far and thanks for the additional information. The scenario you describe about contoured work for a resource frequently comes about as a result of tracking actual data. For example: a resource is initially assigned at 80% to a 5 day duration tasks, the planned work is 6.4 hours per day. If I record 5 hours of actual work on day 1 the percent allocation for that day drops to 63% -- the resource didn't work the original hours scheduled and the remaining 1.4 hours of work is scheduled into day 6 at an allocation of 18%. Even if I change the contour of the assignment back to flat, it does not affect any actual work recorded. The splits you are seeing may be as a result of either resource leveling (leaving the option "Leveling can create splits in remaining work" enabled) or by using the Update Project command and rescheduling incomplete work. I hope this helps. Please post again if this doesn't describe your scenario. Julie "TimB" <microsoft.com> wrote in message news:com... |
Posted: 10 Jan 2006 12:03 PM PST Hi Megan, See: http://support.microsoft.com/kb/316884/en-us for info on Project 2000. I hope this helps. Let us know how you get along Julie "MeganP" <microsoft.com> wrote in message news:com... |
Can I import data from Excel into Project? Posted: 10 Jan 2006 10:41 AM PST Hi slwaite, No sorry. The import from Excel to Project does not link the data. As Dave mentioned you can paste link data from Excel to Project but those links are fragile and may easily become corrupt. You can track the hours spent working on tasks within Project directly instead of tracking in Excel and trying to transfer the data back to project. Hope this helps. Let us know how you get along. Julie "slwaite" <microsoft.com> wrote in message news:com... |
Posted: 10 Jan 2006 10:28 AM PST Although, this solution is not automatic, it will definitely work. I appreciate it. James "Eric Vergne" wrote: |
Posted: 10 Jan 2006 09:56 AM PST Eric Vergne wrote: Glad you got it worked out. As you work with Project, you'll find that many things are order dependent. Do the same steps but in a different order will give entirely different results. It's the nature of the beast. And once you've assigned a resource to a task, if you change the assignment or add more resources, you get very different results. When I work with my clients, particularly in the area of resource assignments, after I figure out what results they want, I create a protocol of how to get that result. I then tell them to always follow that exact protocol if they want that result. Avoids a lot of problems! Hope this helps in your world. |
Posted: 10 Jan 2006 08:47 AM PST You're welcome Walter and thanks for the feedback. Please post with additional questions should you need to. Julie "Walter Isley" <microsoft.com> wrote in message news:com... |
Where'd my resources go?? Help! Posted: 10 Jan 2006 08:41 AM PST "Rod Gill" wrote: WARNING: You are making heavy use of DDE technology (old and flaky). NEVER: Thanks Rod - I found the little buggers, They were on permanant coffee break. Of course, this begs the question: If this is old and flaky technology - then what is the better way to handle this type of thing? |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |