Pages

Search

Uninstall Project 98 without the CD Microsoft Project

Uninstall Project 98 without the CD Microsoft Project


Uninstall Project 98 without the CD

Posted: 02 Dec 2005 01:57 PM PST

Hi Mike,

I don't have a pat answer. Do you know anyone who has the CD? You could
delete all reference to Project 98 from the registry, if you're happy with
registry editing, and then delete all the folders. Or just delete the
program folders.

Mike Glen
Project MVP

Mike Del Duke wrote: 



See link projects with only Milestones

Posted: 02 Dec 2005 09:31 AM PST

hi,

One way to achive this is to copy the milestones and use PASTE SPECIAL and
click the link option while pasting to a master file all the milestones. You
will have to manually copy and paste the milestones into a new master file,
but once done, your updates to individual files will reflect in the master
file.

Regards,
----------------
Haris
http://www.manage-systems.com
---------------------------------------

"SMThomas" wrote:
 

Resource Usage View to Gantt Chart View

Posted: 02 Dec 2005 09:24 AM PST

Hi Inuit,

Open your pool with the third option ("and all sharer files") and your
master project is there for the taking. No macro, standard Project.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Big_Bad_Yellow_Eskimo" <microsoft.com>
schreef in bericht
news:com... 
far, 
(clear 
tasks 
about 
week 
wrote 
it. 
if 
Gantt 
consolidate 


Creating a project object to insert in a Word document

Posted: 02 Dec 2005 08:39 AM PST

Yikes! I had most of the column displayed (I could read all the text) but not
quite all of it. How finicky, but now it works. Thanks
--
carolyn


"Gérard Ducouret" wrote:
 

Order of resources in shared resource pool file

Posted: 02 Dec 2005 06:48 AM PST

Hi wacntn,
Glad to know the fix worked. Thanks for the feedback and elevation to angel
status ;-)

Julie
"wacntn" <com> wrote in message
news:phx.gbl... 


Filter applies on file open

Posted: 02 Dec 2005 06:38 AM PST

I checked that and it wasn't set on. Wierd one.

wacntn
"John" <com> wrote in message
news:microsoft.com... 


freeze planes so I always see task name

Posted: 02 Dec 2005 03:59 AM PST

Brill

Thanck you very much

"Gérard Ducouret" wrote:
 

Setting a time field for project

Posted: 01 Dec 2005 02:50 PM PST

You are welcome and thanks for the feedback.

Julie
"TheJoneser" <microsoft.com> wrote in message
news:com... 


calendar & baseline

Posted: 01 Dec 2005 01:53 PM PST

Thanks. That's what I need to know.

"Rod Gill" wrote:
 

page numbering

Posted: 01 Dec 2005 01:53 PM PST

Select File, Page Setup and edit the Footer

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more


"Smiley" <microsoft.com> wrote in message
news:com... 


Traffic light Indicators

Posted: 01 Dec 2005 12:36 PM PST

atouchet --

Use the [Finish Variance] field as your formula in a custom Duration field.
The Finish Variance field automatically calculates the difference between
the current Finish date and the original Baseline Finish date. Then use the
following rules to generate the stoplights:

Is greater than 10d Red
Is greater than 2d Yellow
Is less than or equal to 2d Green

Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


"atouchet" <microsoft.com> wrote in message
news:com... 


Rate of production vs workload

Posted: 01 Dec 2005 12:15 PM PST


No worries

I'll work out the durations for each task based on what I know to be the
amount of production to be achieved and take it from there....
I thought that that was a realatively common requirement of a schedule and
so it was just a matter of learning how to do it. I was hoping that if i
knew the maximum rate of production, and the amount of work to be produced,
that somewhere I could have everything done automatically.
Thanks though.

I'll make a spreadsheet and obtain draft durations.

/kw



"Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message
news:phx.gbl... 


How do I reset the project start date?

Posted: 01 Dec 2005 11:24 AM PST

Was any of the work entered as done?
In that case you cannot automaticallly reset the start date (Project is very
willing to update your plan, but it won't change history - only kings did
that in the past) but the good news is that you can automatically reschedule
the unfinished work to after a certain date:
Tools, tracking, Update Project, it is well explained there.
HTH


Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Jean" <microsoft.com> schreef in bericht
news:com... 


Viewing effort by resource

Posted: 01 Dec 2005 10:24 AM PST

You are welcome Carolyn and thanks for the feedback.
Julie
"carolyn" <microsoft.com> wrote in message
news:com... 


Please list how one is to use the prioirty field in your help guid

Posted: 01 Dec 2005 08:55 AM PST

Let me add what I have learned. Priority is used when resource leveling a
project. The higher the number the higher the priority. Priority is from 1 to
1,000.
If you use 1,000 MS Projects will not level task with this priority number.
You might want to use 1,000 on contractor schedules you receive. Do not put
1,000 on summary task. This will cause MS Projects to become confused.
You can also go to View, Resource Sheet. Here you can add a column "Can
Level" - YES/NO. This will also turn off the leveling.
You also need to set your resource max units and assign resource calendars
for this to work.


"Gérard Ducouret" wrote:
 

Progress lines don't work with milestone summary tasks

Posted: 01 Dec 2005 07:20 AM PST

Could you give the milestone a duration of, say, 1 minute? This might
overcome your problem.


Mike Glen
Project MVP

FleurH wrote: 



Identifying Split Tasks in Schedule

Posted: 01 Dec 2005 04:58 AM PST

Wow! I never would have approached it like this! It's amazing and thanks
for the input!

Sannas

"Gérard Ducouret" wrote:
 

Project and DotNet Framework v2

Posted: 30 Nov 2005 11:59 PM PST

Hi Rod Gill,

Thank you for your response.

Yes, I did a new project installation on another computer with framework v2
installed which does not have a Project 2003. The same result happen when I
run the program. I did a detect and repair without ecountering any error
response. The result remained the same.

I also did a new installation on another computer running Windows 2000
Professional without Framework v2 installed. The program runs fine.

Beside this, I did encounter another problem, When I make the new
installation of Project 2003 on the computer with Framework v2. It's also
ed up my outlook profile, I noticed it when I ran my Office Outlook 2003
and was prompt for a new profile. What happen to my existing profile? no
idea. Luckily, I always put all my emails into other datafiles in other
directory, so I did not actually lose any emails, I hope.

I also noticed from time to time, new installation can actually ed up
Office program, eg requesting for reinstallation of program. This happen to
Excel once.

Seb

"Rod Gill" wrote:
 

Who Does What When Report Modification ??

Posted: 30 Nov 2005 07:28 PM PST

If I understand your problem: Take one of your Text columns and define the
"project" in each cell. Go to the report and edit the way it's sorted. Sort
by Text (Project) first. Let we know how this worked.

"Capitol Mike" wrote:
 

how do calculate FTEs in MS Project?

Posted: 30 Nov 2005 01:01 PM PST

Sorry, I know how to change the time scale. What I needed was to display work
and also # of FTEs (Full Time Employees) the work represented. My solution
only works if you are not using the Cost piece of the resources. If you enter
..2/d in the rate for each resource, then Cost which can be displayed as a
line under work contains the FTEs.

Thanks anyway for your help.

"JulieS" wrote: