Urgent: SharePoint team services 2003 and Project 2000 Microsoft Project |
- Urgent: SharePoint team services 2003 and Project 2000
- MS Project recurring tasks
- Problems with Projectserver 2003...
- Hiding group totals in Project 2003
- How do I show multiple resources on one graph in Project?
- with publisher how do i insert a flash object into a web page?
- Help me please.....
- stop task durations from changing!
- stop task splitting
- Task Scheduling and leading zeros
Urgent: SharePoint team services 2003 and Project 2000 Posted: 07 Nov 2005 07:10 AM PST Why are you supporting this configuration? It dosen't work, Apples and oranges. Or in this case, rotten apples which is the world of XML. "Judy" <microsoft.com> wrote in message news:com... |
Posted: 07 Nov 2005 05:56 AM PST Hi Peggy I am trying to recreate the scenario you have described but I do not get the same results I have created a recurring task - every monday for the next 5 weeks I have expanded the recurring tasks by clicking the + symbol I have created a task that has a dependency on the first instance of the recurring tasks (in the predecssors column I can see the specific reference to the individual instance) The task that is dependent on the individual instance starts as soon as that instance is scheduled to finish Have you done anything different to this for your project? Hope this helps ... -- Regards Chris Marriott - PMP MCSE MCDBA UK - EPM Consultant & Trainer "Peggy" wrote: |
Problems with Projectserver 2003... Posted: 07 Nov 2005 03:49 AM PST You're welcome, Arne :-) Mike Glen MS Project MVP Arne Styve wrote: |
Hiding group totals in Project 2003 Posted: 07 Nov 2005 03:21 AM PST Chris Thanks for your reply. Someone I know with Project 2000 is able to do this by formatting the summary start/finish/days to the same colour as the background, but in Project 2003 when I try to do this it won't let me format individual cells in the group summary. Cheers Gary "Chris Marriott" wrote: |
How do I show multiple resources on one graph in Project? Posted: 06 Nov 2005 11:38 PM PST Hi Skiffie, Welcome to the Microsoft Project newsgroup :-) Please see FAQ Item: 38. Combined Resource Graph FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Hope this helps - please let us know how you get on:-) Mike Glen Project MVP Skiffie wrote: |
with publisher how do i insert a flash object into a web page? Posted: 05 Nov 2005 05:28 PM PST Sorry Moe ... you have selected the wrong group .... publisher is one floor up -- Regards Chris Marriott - PMP MCSE MCDBA UK - EPM Consultant & Trainer "Moe" wrote: |
Posted: 05 Nov 2005 10:27 AM PST Hi toofan, You can't change the information *directly* in the Relationship Diagram view in the bottom pane, but you can modify task link types (FS, SS etc.) in the Task Form View. When you initially split from the Gantt Chart view, the Task Form is the view in the bottom pane. Click in the bottom pane and choose Format > Details, and you can display Predecessors and Successors in the task form. As far as changing the color of task cells, I'm afraid that is impossible. Unlike Excel, there is no "fill" color to change the background of a task cell. You can change text color, size, etc through Format > Font. I hope this helps. Let us know how you get along. Julie "toofan" <microsoft.com> wrote in message news:com... |
stop task durations from changing! Posted: 04 Nov 2005 06:23 PM PST Hi, John Thanks. Yes, I periodically highlight the whole column of tasks, go to the task dialog/advanced, and set the task type to fixed duration. It seems to work to change it for all the tasks. Nonetheless, MS project changes durations and splits tasks. The doentation says it will change duration if you have resource calendars, etc., so I also tried to put all that on the same calendar. No joy. Anyhow, I soled the problem by brute force: created a new file, adjusted the standard calendar, and copied over one column at a time as text. It solved all three problems. It now resource levels, does not split the tasks, and does not change the task duration. So, something must have gotten corrupted in the original file that I could not change. Regards, Larry "John" wrote: |
Posted: 04 Nov 2005 06:16 PM PST Hi, Jan I don't think holidays were the problem, but the overall calendar use appeared to be causing the trouble. I started a new file with first resetting the standard calandar, and then pasted all the stuff from the broken file. It works fine now, without splitting or changing the durations. Thanks for your thoughts. Larry "Jan De Messemaeker" wrote: |
Task Scheduling and leading zeros Posted: 04 Nov 2005 12:25 PM PST In article <com>, "WhyIsEverythingSoConfusing" <com> wrote: Justin, The only way I can te your scenario is if the 9/10/05 task has an Actual Start date of 9/10/05. That effectively says the task has "started" even though there are no resource hours. I suspect the task has NOT started and the entry in the Actual Start field was either inadvertent or manually inserted without really understanding what Actual Start means. Normally, leveling is applied prior to the project start (i.e. the user is trying to adjust the schedule so no resource overallocations exist), or it is applied to resolve overallocations that have crept in over a period of time. In the latter case, task splits are to be expected (if the option to split is selected under Tools/Options/Schedule tab). In the absence of an entry in the Actual Start field, leveling WILL adjust task start dates. In your case, the 9/10/05 task will indeed be slipped out to 9/13/05 when the resources are available. Hope this helps. John Project MVP |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |