Pages

Search

Urgent: SharePoint team services 2003 and Project 2000 Microsoft Project

Urgent: SharePoint team services 2003 and Project 2000 Microsoft Project


Urgent: SharePoint team services 2003 and Project 2000

Posted: 07 Nov 2005 07:10 AM PST

Why are you supporting this configuration?
It dosen't work, Apples and oranges. Or in this case, rotten apples
which is the world of XML.

"Judy" <microsoft.com> wrote in message news:com... 


MS Project recurring tasks

Posted: 07 Nov 2005 05:56 AM PST

Hi Peggy

I am trying to recreate the scenario you have described but I do not get the
same results

I have created a recurring task - every monday for the next 5 weeks

I have expanded the recurring tasks by clicking the + symbol

I have created a task that has a dependency on the first instance of the
recurring tasks (in the predecssors column I can see the specific reference
to the individual instance)

The task that is dependent on the individual instance starts as soon as that
instance is scheduled to finish

Have you done anything different to this for your project?

Hope this helps ...
--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer


"Peggy" wrote:
 

Problems with Projectserver 2003...

Posted: 07 Nov 2005 03:49 AM PST

You're welcome, Arne :-)

Mike Glen
MS Project MVP


Arne Styve wrote: 



Hiding group totals in Project 2003

Posted: 07 Nov 2005 03:21 AM PST

Chris

Thanks for your reply. Someone I know with Project 2000 is able to do this
by formatting the summary start/finish/days to the same colour as the
background, but in Project 2003 when I try to do this it won't let me format
individual cells in the group summary.

Cheers
Gary

"Chris Marriott" wrote:
 

How do I show multiple resources on one graph in Project?

Posted: 06 Nov 2005 11:38 PM PST

Hi Skiffie,

Welcome to the Microsoft Project newsgroup :-)

Please see FAQ Item: 38. Combined Resource Graph

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on:-)

Mike Glen
Project MVP
Skiffie wrote: 



with publisher how do i insert a flash object into a web page?

Posted: 05 Nov 2005 05:28 PM PST

Sorry Moe ... you have selected the wrong group .... publisher is one floor up
--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer


"Moe" wrote:
 

Help me please.....

Posted: 05 Nov 2005 10:27 AM PST

Hi toofan,

You can't change the information *directly* in the Relationship Diagram view
in the bottom pane, but you can modify task link types (FS, SS etc.) in the
Task Form View. When you initially split from the Gantt Chart view, the
Task Form is the view in the bottom pane. Click in the bottom pane and
choose Format > Details, and you can display Predecessors and Successors in
the task form.

As far as changing the color of task cells, I'm afraid that is impossible.
Unlike Excel, there is no "fill" color to change the background of a task
cell. You can change text color, size, etc through Format > Font.

I hope this helps. Let us know how you get along.

Julie
"toofan" <microsoft.com> wrote in message
news:com... 


stop task durations from changing!

Posted: 04 Nov 2005 06:23 PM PST

Hi, John

Thanks. Yes, I periodically highlight the whole column of tasks, go to the
task dialog/advanced, and set the task type to fixed duration. It seems to
work to change it for all the tasks. Nonetheless, MS project changes
durations and splits tasks.

The doentation says it will change duration if you have resource
calendars, etc., so I also tried to put all that on the same calendar. No joy.

Anyhow, I soled the problem by brute force: created a new file, adjusted the
standard calendar, and copied over one column at a time as text. It solved
all three problems. It now resource levels, does not split the tasks, and
does not change the task duration. So, something must have gotten corrupted
in the original file that I could not change.

Regards,
Larry

"John" wrote:
 

stop task splitting

Posted: 04 Nov 2005 06:16 PM PST

Hi, Jan

I don't think holidays were the problem, but the overall calendar use
appeared to be causing the trouble.

I started a new file with first resetting the standard calandar, and then
pasted all the stuff from the broken file. It works fine now, without
splitting or changing the durations.

Thanks for your thoughts.

Larry

"Jan De Messemaeker" wrote:
 

Task Scheduling and leading zeros

Posted: 04 Nov 2005 12:25 PM PST

In article <com>,
"WhyIsEverythingSoConfusing" <com> wrote:
 


Justin,
The only way I can te your scenario is if the 9/10/05 task has an
Actual Start date of 9/10/05. That effectively says the task has
"started" even though there are no resource hours. I suspect the task
has NOT started and the entry in the Actual Start field was either
inadvertent or manually inserted without really understanding what
Actual Start means.

Normally, leveling is applied prior to the project start (i.e. the user
is trying to adjust the schedule so no resource overallocations exist),
or it is applied to resolve overallocations that have crept in over a
period of time. In the latter case, task splits are to be expected (if
the option to split is selected under Tools/Options/Schedule tab).

In the absence of an entry in the Actual Start field, leveling WILL
adjust task start dates. In your case, the 9/10/05 task will indeed be
slipped out to 9/13/05 when the resources are available.

Hope this helps.
John
Project MVP