Timescale Duration Bars = Actual Duration? Microsoft Project |
- Timescale Duration Bars = Actual Duration?
- Enterprise Project Management
- New file, adding resources changes duration, why?
- Issue with Task Report cutting off task name description
- Assigning holiday time
- Maximum number of selected tasks
- Assign duration for 24 hour calendar
- How do i lock the Baseline Start Column?
- How to Create Master "Key Driver" Milestones copied from subprojec
- Filtering more than one resource assigned to the same task
Timescale Duration Bars = Actual Duration? Posted: 25 Oct 2005 08:52 AM PDT In article <phx.gbl>, "Holland" <com> wrote: Holland, By timescale bars I assume you mean the Gantt bars. My first question is, are you sure that is what you really want to do? The Duration field shows working time based on a default 5 day work week at 8 hours per day. However, elapsed time can be shown in the Duration column by either changing the default calendar (and some options) to a 24 hour work day or by simply entering duration values in elapsed time (e.g. 10ed for 10 elapsed days). On the other hand, the Gantt bars normally show elapsed time. They can be configured to show working time but it would be very confusing. For example, let's say a task starts on Monday and has a duration of 10 days (i.e. goes through Friday of the following week). The normal Gantt bar will show a bar from Monday through Friday of the following week. However, if the Gantt bar was showing working time, it would go from Monday through Wednesday of the following week. That's because the Gantt bars always including non-working time - in this case the weekend. Now, it that really what you want to do? John Project MVP |
Posted: 25 Oct 2005 08:06 AM PDT Robert -- In the future, please post all Project Server questions to the microsoft.public.project.server newsgroup, as this newsgroup is devoted to questions about the Microsoft Project desktop application only. To answer your question, if the PM manually enters progress in the actual Microsoft Project plan, he/she must do the following to "push" the changes to each user's timesheet in PWA: 1. Click Collaborate - Publish - Republish Assignments 2. Select the "Overwrite actual work entered by resources" option 3. Click OK Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com http://www.projectserverexperts.com "We wrote the book on Project Server" "Robert" <microsoft.com> wrote in message news:com... |
New file, adding resources changes duration, why? Posted: 25 Oct 2005 07:07 AM PDT Hi, Resource working toimes are different from Project calendar working times. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Milind" <fm> schreef in bericht news:#phx.gbl... of |
Issue with Task Report cutting off task name description Posted: 25 Oct 2005 06:31 AM PDT Julie, How do I do the custom view and custom table? I don't see a selection for them in the drop down menus. Dave "JulieS" wrote: |
Posted: 25 Oct 2005 06:26 AM PDT I didn't know you are using Project Server. Of course, with Project Server, the resource sharing is permanent. In Project Server, there is the Administrative project feature for that. You don't need a Master Project. Gérard Ducouret "WSH" <microsoft.com> a écrit dans le message de news:com... Project You resources wouldn't show mean. to resource. and |
Maximum number of selected tasks Posted: 25 Oct 2005 02:16 AM PDT Martin It is exactly the same in Project 2003 You can increase the range if any of the selections can be shift clicked first. -- Regards Chris Marriott UK - EPM Consultant & Trainer "Martin Wilkinson" wrote: |
Assign duration for 24 hour calendar Posted: 24 Oct 2005 01:38 PM PDT JulieS, Thanks so much for your extra help. You are exactly correct when you say "How would anyone looking at a schedule be able to know if a day is 24 hours or 8 hours? It would vary depending upon which resource was assigned." This is precisely what I want. Becuase the duration of my 24hr/7day per week resource is 45 days (24 hour days), I don't want to list this duration as 1080 hours (management won't understand how long that is without a calculator...). If they saw 45 days and looked at the resource they would immediatly know that these are 24 hour days. With many other parallel tasks on-going during this 45 day period with normal 8 hour per day resources , I cannot change my entire project chart to 24 hour days. So how can I clearly express these durations? Any help? Thomas "JulieS" wrote: |
How do i lock the Baseline Start Column? Posted: 24 Oct 2005 10:59 AM PDT Go to the insert menu, select column and choose one of the available text columns select your baseline column (baseline finish for example) by clicking on the column head. Copy. select your text column paste. Now the two are equivalent. Select the text column and delete it (this just hides it from view) Now if they change the baseline it will be different from the values in the text column. To check if they are equivalent, it is easiest to use a flag field. Insert one of the flag fields. Right click the column header. Select customize fields. Click on the formula button enter a formula like iif([Baseline Finish]=[Text1],"Yes", "No") Now that field will show no for any tasks where the baseline has been changed. Finally, create a filter. Set it for all tasks which have a Flag1 value of "No". An alternative is to use the compare projects add-in. -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. "Jitin" <microsoft.com> wrote in message news:com... for to the visit there to change my |
How to Create Master "Key Driver" Milestones copied from subprojec Posted: 24 Oct 2005 09:01 AM PDT John, thanks for the links, I'll make good use of them! "John" wrote: |
Filtering more than one resource assigned to the same task Posted: 24 Oct 2005 08:40 AM PDT In article <com>, WSH <microsoft.com> wrote: WSH, You're welcome. It's a good thing I'm in a different time zone. This way you solved it yourself and all I had to do was hear about the result. John |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |