Best Practice for Using lags Microsoft Project |
- Best Practice for Using lags
- Fixed duration given, but changes
- Wrap text in columns
- copy a task
- Meaning of total slack in a project scheduled from end date
- Critical task definitions
- Total slack not correct
- how can I set up an ongoing alphabetical film library list
- Network diagram and the Web
- Restrict work per day
- Error importing excell worksheet as a new project
Posted: 14 Nov 2005 01:41 PM PST Gerard, Thank you for your insight. I appreciate your help. Alone "Gérard Ducouret" wrote: |
Fixed duration given, but changes Posted: 14 Nov 2005 11:11 AM PST Hi Steve, May be I misunderstood your statement: <<With effort driven task, adding or removing bodies causes the duration to change and the work to pro-rated. >> I don't think so : With effort driven [Fixed Duration] task, adding or removing bodies causes the Units to change. Gérard Ducouret "Steve House [Project MVP]" <send.hotmail.com> a écrit dans le message de news:phx.gbl... can't is the one-week Joe resources setting |
Posted: 14 Nov 2005 08:56 AM PST Jim Glad it helped ... but there is not automatic way to do this as far as I know ... -- Regards Chris Marriott - PMP MCSE MCDBA UK - EPM Consultant & Trainer "Jim" wrote: |
Posted: 14 Nov 2005 07:11 AM PST In article <com>, "wjBigSax" <microsoft.com> wrote: wjBigSax, Well there's nothing like the complete story. A master with subprojects makes all the difference. Understand that the subprojects in a master are not physically part of the master. Rather, the master only contains a pointer to the subproject file (that's why the task IDs in a master start at "1" for each inserted subproject). The only subproject "task" that actually belongs to the master is the insertion point summary line. Given that information, copying and pasting a task from the master to a subproject or vice versa will in fact result in a totally new task in the destination file. The original links are lost and depending on where the task is inserted into the other file, it may take on new links (i.e. if the task is pasted into a chain of linked tasks even though the Tools/Options/Schedule tab option to autolink inserted tasks is not checked). I hope this clarifies what you are seeing. John Project MVP |
Meaning of total slack in a project scheduled from end date Posted: 13 Nov 2005 01:17 PM PST Really thank you Steve for reading me. I totally agree with your general arguments. Anyway the point of my initial question was related to a more specific aspect, if you want, a marginal aspect, but, as i told before, an aspect that Microsoft should consider to improve so that Project would be a better product(even if little better). Thanks a lot anyway for your answer Best regards Michele "Steve House [Project MVP]" ha scritto: |
Posted: 13 Nov 2005 09:46 AM PST Thank you for reading me. Forgive me but what you say is not related to my question. Thanks a lot anyway for answering Best regards Michele "Catfish Hunter" ha scritto: |
Posted: 13 Nov 2005 09:36 AM PST Your habit is surely the best way to approach and to manage a project even because, like u say, no software can't aviod us to use our minds. I totally agree with you. Best regards Michele "John" ha scritto: |
how can I set up an ongoing alphabetical film library list Posted: 13 Nov 2005 08:38 AM PST Adding to John's reply ... What you describe is a classic application for a database management system and Access is tailor-made for that sort of thing. "Bambi" <microsoft.com> wrote in message news:com... |
Posted: 11 Nov 2005 04:44 PM PST Why doesn't the "copy to GIF" work? Graphics on a webpage - drawings, pictures, diagrams, whatever - need to be in a gif, jpg, or png file format to be processed by the web browser that is visiting your site. Remember that the actual page the viewer sees is constructed by his web browser in his own machine, constructed locally according to the instructions in the html file downloaded to him from the web site he's viewing. Something like the Network Diagram must be in picture form for his browser to know what to do with it. If you're saying the "copy to gif" isn't working because the resulting file is too big for practical downloading (a common occurance) the solution is to load it into an image editing program such as Photoshop or similar and resize it to more workable dimensions for posting. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Andronica" <microsoft.com> wrote in message news:com... |
Posted: 11 Nov 2005 12:20 PM PST I have done this but the same resource will be scheduled to work double shifts instead of Day OR Night shifts. "Chris Marriott" wrote: |
Error importing excell worksheet as a new project Posted: 10 Nov 2005 05:32 PM PST Hi Ice, In the Save As... dialog, select from the Type pick list: "Microsoft Excel Workbook *.xls" (You'll have to scroll down to find it.) Click Save, and Next in the Wizard, and then select "Project Excel Template"... etc. Mike Glen MS Project MVP Ice wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |