Project Experts: Need Your Help Microsoft Project

Project Experts: Need Your Help Microsoft Project


Project Experts: Need Your Help

Posted: 02 Nov 2005 04:47 PM PST

I second Brian's comment - there is a massive amount of user knowledge behind
this newsgroup and it is, I would suggest, the most efficient way of dealing
with queries.
It also means that other users will benefit from the posts.

"Anne Troy" wrote:
 

Cannot open project files - Doesn't anyone have a solution?

Posted: 02 Nov 2005 05:30 AM PST

It won't help you today but in future, you can set MS Project to
automatically create a backup for you. That way, you never need to worry if
you have a backup or not or how long it will take tech support to restore it
for you.

"Kevin Newman" wrote:
 

Rate Column

Posted: 02 Nov 2005 05:17 AM PST

Hi,

Using custom field in calculations requires VBA programming.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"whatzzup" <microsoft.com> schreef in bericht
news:com... 
for 
Sheet 
see 
like 


20 Hours over 5 days

Posted: 01 Nov 2005 03:53 PM PST

Hi glpeters,

Welcome to this Microsoft Project newsgroup :)

Also, you might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #11 - Task Types, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

net wrote: 



File Format for importing multiple resources per task

Posted: 01 Nov 2005 12:35 PM PST

In article <com>,
"J. Maloney" <microsoft.com> wrote:
 

J,
Why did you try to concatenate all that stuff (i.e. resource name, ID
and Work)? Data from other apps needs to be mapped into fields in
Project. If you concatenate the resource names as the assignments for
each task then you will be ting the text string of the Resource
Names field in a task view. You could add the allocation values also.
For example:
Joe[50%],Fred[30%]

It does work - I tried it before I suggested it.

John

Resources as a percentage

Posted: 01 Nov 2005 11:30 AM PST

Hello,

View / Resource Usage
Right click on a yellow cell
Select Detail Styles...
In the "Available fields" list (lefthand) select Percent Allocation. OK
May be, hide the Work field.
Double click the time scale ans set the Bottom Tier units to Months (before
that you enlarged the Middle tier too)

Hope this helps,

Gérard Ducouret

"SBakerNYC" <microsoft.com> a écrit dans le message de
news:com... 


MPP shouldn't allow 0d milestones on resource calendar holidays.

Posted: 01 Nov 2005 10:02 AM PST

Give it a 1 min duration and mark the (to be inserted) milestone column as
"Yes"

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"elisey" <microsoft.com> schreef in bericht
news:com... 
milestones 
when 
this 
http://www.microsoft.com/office/community/en-us/default.mspx?mid=2eeef5d8-17
b4-4018-b5bd-8ed02481614d&dg=microsoft.public.project


Budget, Actual Time, Percentage Completion

Posted: 01 Nov 2005 08:01 AM PST

Hi Lillian,

Welcome to this Microsoft Project newsgroup :)

When you enter the Actual Work, enter the Remaining work as zero and Project
will set it at 100% for you - that should do what you want.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

Lillian wrote: 



Totalling Resources as a Percentage

Posted: 01 Nov 2005 07:42 AM PST

Thank You!

"Jan De Messemaeker" wrote:
 

HTML Task Views

Posted: 31 Oct 2005 12:32 PM PST

Hi Jennie ,

Welcome to this Microsoft Project newsgroup :-)

Please see FAQ Item: 16. Project Viewer.

FAQs, companion products and other useful Project information can be seen at
this web address:http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP

Jennie B wrote: 



How to create a link between a task and a recurring meeting?

Posted: 31 Oct 2005 12:04 PM PST

Tiras,

Generally, the dates get pushed because a task cannot be completed (fully)
within the given time frame of the calendar you set the task to. If you drill
down in the Task Usage view the the "hour" level, you can see whether this is
the case.

You might also want to check your calendars for each meeting type to be sure
the meeting times were set up correctly for the time period in question (you
only mentioned that you verified that the correct calendar was assigned to
the task :)).

Hope this helps! :)
--
Don L.


"Triasp" wrote:
 

Find overallocated tasks when resource availability > 100%

Posted: 31 Oct 2005 11:59 AM PST

Chris,

Thanks for your help. I tried it again on a fresh project and it works fine
now. It still doesn't work on the "old" project, so something bizarre must
have happened there.

Tracy

"Chris Marriott" wrote: