Can any recommend a pre-assessment test for MS Project users Microsoft Project |
- Can any recommend a pre-assessment test for MS Project users
- MS Project -> Lotus Notes
- how do I stop project from calculating actuals
- What percent of projects are late and overbudget?
- How can I input a deadline with an option of 5 days delay is ok?
- How do I prioritize tasks in Project 2003?
- % Incomplete Tasks
- Cross-project dependencies
- PERT on 'Work' - not 'Duration'
- Best Practice
Can any recommend a pre-assessment test for MS Project users Posted: 12 Nov 2005 06:27 AM PST Steve, Thank you. I agree with you 100 percent and have had formal training in PM and teach those skills along with the software. However, this training was done as a requirement of a state workforce grant and apparently, they need to see a pre and post assessment on software skills as well as for the PM training the group received. Kay "Steve House [Project MVP]" wrote: |
Posted: 11 Nov 2005 01:14 PM PST Hi, thanks for your response. I found in between by google research a the tool Allocatus, which does what I want. Thanks again Graham -- Graham Smith "JulieS" <passport6847 at maine dot rr dot com> wrote in message news:phx.gbl... |
how do I stop project from calculating actuals Posted: 11 Nov 2005 12:28 PM PST Hi, You could also use Physical %complete which does not feed back to actuals and seems to be what you have in mind. -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "capo3playd" <microsoft.com> schreef in bericht news:com... enter |
What percent of projects are late and overbudget? Posted: 11 Nov 2005 06:23 AM PST Hi Dan, I can't give you figures, but I can suggest you define what is meant by "success". On time and within budget is not a valid measure. I would be so bold as to suggest that some 90% of properly planned projects would be on time and within budget if they were allowed to progress from start to completion without any interference. The prime reason why projects appear go astray is because the parameters on which the project was planned, are changed frequently as the project progresses, without due acceptance of the subsequent changes to completion date and extra costs. Indeed, in spite of all the changes to specifications, projects are more often than not unfairly measured against the originally stated completion date and budget. If only the PMs could be left alone to get on with the job without change! Mike Glen MS Project MVP nospam wrote: |
How can I input a deadline with an option of 5 days delay is ok? Posted: 11 Nov 2005 02:40 AM PST First of all, you shouldn't try to set start and finish dates for tasks at all - these are normally calculated values. In fact the whole reason scheduling software such as Project exists is to calculate those dates for you. The start date is calculated as the earliest possible start based on project kick-off date and the durations, links, etc of all the tasks leading up to the task in question. The finish date is the calculated from start date plus the estimated duration it will take to complete the work. To show that it needs to be completed by a certain date, set the deadline entry on the task's advanced tab to that date. I notice your example is a task that lasts an entire year. A task is a discrete block of work done by a single set of skills that results in a single deliverable and very, very rarely would such a thing last a full year. In fact, the general rule of thumb is called the "8/80 Rule" which says if the task is less than 8 hours in duration you're micro-managing to excess but if it is more than 80 hours you haven't broken things down far enough to actually be able to manage it at all. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Yon Han CHONG" <Yon Han microsoft.com> wrote in message news:com... |
How do I prioritize tasks in Project 2003? Posted: 10 Nov 2005 02:16 PM PST One of the primary uses of Critical Path Scheduling is to prioritze tasks. Tasks with less slack have a higher priority than tasks with more slack. Of course, you have to take in other factors as well, like risk, complexity, etc. But certainly slack should be a factor. |
Posted: 10 Nov 2005 10:46 AM PST Hi Qaspec, Welcome to this Microsoft Project newsgroup :) You might like to have a look at my series on Microsoft Project in the TechTrax ezine, particularly #14 - Customizing Fields, at this site: http://tinyurl.com/2xbhc or this: http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 (Perhaps you'd care to rate the article before leaving the site, :) Thanks.) FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP JulieS wrote: |
Posted: 10 Nov 2005 10:41 AM PST Thanks, Jan. I spoke too soon -- the master does in fact show the links in grey. We can close this thread. "Jan De Messemaeker" wrote: |
PERT on 'Work' - not 'Duration' Posted: 10 Nov 2005 02:47 AM PST Hi Johannes, You are welcome for the answer and glad to know it helped solve your dilemma. As far as the why question -- sorry, I gave up long ago trying to fathom the reasoning why for all software -- including Project ;-). Thanks for the feedback. Julie "Johannes Nyholm Jørgensen" <microsoft.com> wrote in message news:com... |
Posted: 09 Nov 2005 07:08 AM PST Create a hammock task that is whose duraton is driven by the project start and end dates for the managment task(s) an assign the PM to it as tjhe resource. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Matium" <net> wrote in message news:googlegroups.com... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |