Cost Roll Up in Project 2003 Microsoft Project |
- Cost Roll Up in Project 2003
- Baseline data not saved
- Disadvantages of assigning multiple resources to tasks in MSP?
- MS Project: Buffer time... How to?
- Identifying linked-to Ghost tasks
- team messaging in MS Project 2003
- How to I customise the legend (for the Gantt Chart) in Project 200
- MS Project COM Interop - Project is not an Object - C#
- Modeling task-based revenue instead of resource-based cost
- Replacement for MS Project: Projity is in beta testing
- how to change the font of all Task Notes in MS Project
- Automatic split of a task
- How to convert a Project 2003 task into an Outlook task
- calculation
- Actual Work mismatch
- Auto WBS numbering "skips" linked-to tasks
- task and subtask finish dates
- how do i filter to view only linked tasks?
- Creating Custom Fields
- MS Project 2000 Calendars
- Coloring Task
- Columns common to Gantt & resource usage view
- Is Project the App for my needs / template for my need
Posted: 28 Sep 2005 12:11 PM PDT GREAT Response. Very clear & easy. THANKS "Dale Howard [MVP]" wrote: |
Posted: 28 Sep 2005 09:01 AM PDT Hi Dan, You're welcome and thanks for the feedback. Sorry the fix didn't work :-( I'm afraid I don't have any other suggestions for you but perhaps some other reader has a trick or two up his or her sleeve. Julie "DanG" <microsoft.com> wrote in message news:com... |
Disadvantages of assigning multiple resources to tasks in MSP? Posted: 28 Sep 2005 06:31 AM PDT Hi Emma, There is no (major) problem with aving multiple resopurces on a task as long as all users remember that Project nearly always handles those multiple assignments (a resource on a task = an assignment) as if they were independent tasks: for instance, one resouce has a day off, the other one happily continues to work; Change the work of one assignment it will not affect the other opne (and then indeed both assignments will have different durations... Everything quite logical, but sometimes so surprising that I keep on recommending to use one assignment per task as long as utterly possible. Hope this helps, -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "EmmaG25" <microsoft.com> schreef in bericht news:com... It and |
MS Project: Buffer time... How to? Posted: 28 Sep 2005 03:43 AM PDT Hi Woman in white, Well, the only way to add buffer time (in the TOC sense of the word) is to CHANGE THE END DATE of the project (f.i. by adding a Must Finish on Milestone) You can then see the buffer by task by inserting the Total Slack column. -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "WomanInWhite" <com> schreef in bericht news:googlegroups.com... |
Identifying linked-to Ghost tasks Posted: 28 Sep 2005 02:33 AM PDT Hi DonL, Yes, I thought of that. However, I assumed Martin was looking for a method of identifying tasks in the current project with external predecessors and/or external successors, from his comment "linked-to"ghost" tasks". The [External] field will show "yes" if a specific task is external but will not flag if the predecessor or successor is external. Of course, it is possible that my mind is just on a holiday :-) Julie "DonL" <microsoft.com> wrote in message news:com... |
team messaging in MS Project 2003 Posted: 27 Sep 2005 09:48 PM PDT Hi T Sharrock, See: http://support.microsoft.com/default.aspx?scid=kb;en-us;818337 Hope this helps. Let us know how you get along. Julie "T Sharrock" <microsoft.com> wrote in message news:com... |
How to I customise the legend (for the Gantt Chart) in Project 200 Posted: 27 Sep 2005 04:31 PM PDT I don't think you can include those in the legend, but I've never tried either. -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. "Vikkus" <microsoft.com> wrote in message news:com... ?? task Late from up. remove remove I the |
MS Project COM Interop - Project is not an Object - C# Posted: 27 Sep 2005 02:56 PM PDT On Wed, 28 Sep 2005 05:09:13 -0400, "Gary L. Chefetz [MVP]" <gary AT chefetz DOT org> wrote: Thank you. I will do that. I will have to use Google as my ISP doesn't carry that newsgroup. Ken Wilson Seeking viable employment in Victoria, BC |
Modeling task-based revenue instead of resource-based cost Posted: 27 Sep 2005 12:39 PM PDT Hello I should have prefaced this with more about our business, but in a service business revenue is definitely based on completing tasks. When we sign a new client, we craft a project plan to match the scope and estimate the hours necessary to achieve that scope. We can then bill and/or recognize revenue based on hours completed and/or percent complete on a monthly basis. So our revenue is directly and solely connected to a task's hours. Each client could have a different rate, depending on the value of their contract and the hours in the plan, so I can't say that Sally's rate is a flate $150 (like in a lawyer example) because in one project it may be $150 but in another it could be $300. And that rate is based on the project, regardless of who completes an hour of work. No worries on the overlay of cost info - we're not calculating cost in any other manner or use, so it's fine. I realize it's a bit heretical but it works! Thanks for the help and insight. "John" wrote: |
Replacement for MS Project: Projity is in beta testing Posted: 27 Sep 2005 12:14 PM PDT Hi, I think this sucks, yes. I wouldn't use the space paid for by Microsoft to attack their products and make publicity for mine. In my feeling, this is theft and it should be considered a criminal act. Have the honesty to pay for your own publicity, please. -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 <com> schreef in bericht news:googlegroups.com... |
how to change the font of all Task Notes in MS Project Posted: 27 Sep 2005 03:31 AM PDT Hi Ian, So sorry. In further testing (with some much more obvious changes to font formatting) you are correct. The only way I seem to be able to carry the formatting to the printed notes page seems by changing the font in the Task Information dialog box. I am sorry to lead you on a wild chase :-( Julie "Ian" <microsoft.com> wrote in message news:com... |
Posted: 27 Sep 2005 02:53 AM PDT THX Jan, but... it's not working as I want to (I tried it before my first post). What I want to do in fact is the following, eg.: - you have 1 task - T1 - for the entire day (meaning 8 hrs); - another task - T2 (2hrs) - shows up as very urgent and now I have to add this task in my .mpp; - first I had my task for 8hrs during the day and now I have T1 for 4hrs, then T2 for 2hrs, again T1 for 4hrs. What I want to be shown automatically when I enter T2 in my plan is something like that (sorry for my pathetic try of replacing graphics with letters :) ): T1 xxxx...xxxx T2 xx It's easy for me as a guy that plays a lot with project plans to do it, but I don't want to put another task on my programmers to learn to work with MPP. THX a lot |
How to convert a Project 2003 task into an Outlook task Posted: 27 Sep 2005 12:53 AM PDT Project 2000 used to have a workgroup feature which allowed you to do exactly what you are looking for. Unfortunately MS has decided to discontinue to support for that feature so you go out and buy Project Server. You can still download and install the Workgroup feature here http://www.microsoft.com/downloads/details.aspx?familyid=6382c615-1090-452c-8eba-4025b8976c18&displaylang=en "Penelope" wrote: |
Posted: 26 Sep 2005 09:59 PM PDT "karthick" wrote: Earned Value (EV) or the Budgeted Costs of Work Performed (BCWP): The physical work accomplished to the As-of Date or the Status Date. Planned Value (PV) or the Budgeted Costs of Work Schedule (BCWS): The baseline, or the physical work scheduled (planned) to the As-of Date or the Status Date. Actual Cost (AC) or the Actual Cost of Work Performed (ACWP): Total costs incurred as a result of accomplishing the work to the Status Date. |
Posted: 26 Sep 2005 12:31 PM PDT Where exactly do you see a big total (meaning for the whole project?) in the resource usage view? -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Andrea" <microsoft.com> schreef in bericht news:com... for What I the work |
Auto WBS numbering "skips" linked-to tasks Posted: 26 Sep 2005 09:04 AM PDT That seems to work. As you say, bit of a pain to do, as I have quite a few links in my schedule. I guess it's something I'm going to have to live with, but at least I have your suggestion as a fallback position! Cheers Martin "DonL" wrote: |
Posted: 26 Sep 2005 08:59 AM PDT Thanks so much - that was it! Don't know how that option got miss-set... "Gérard Ducouret" wrote: |
how do i filter to view only linked tasks? Posted: 26 Sep 2005 08:25 AM PDT In article <com>, Ron <microsoft.com> wrote: Ron, The method I used (several years ago) was the following: Predecessors is greater than 0 Or Successors is greater than 0 You probably want to turn off the option for Summary Lines. Hope this helps. John Project MVP |
Posted: 26 Sep 2005 07:27 AM PDT In article <com>, "Menji" <microsoft.com> wrote: Menji, Perhaps Gerard's response is the answer you were seeking but on the off chance that you did NOT want to simply change the format of the existing Start and Finish fields, two custom fields could be set up to show only the Start and Finish times even though the standard Start and Finish fields still show just the date. In two custom text fields, use the following formulas: Text1 = cstr(timevalue([start])) and Text2 = cstr(timevalue([finish]) Hope this helps. John Project MVP |
Posted: 26 Sep 2005 07:27 AM PDT Hi Marcos Mello, Glad to have helped and thanks for the feedback. Sorry to hear that you had already applied my suggestion and that didn't work. I came across the following Knowledge Base article. I don't know if it applies to your situation, but I thought I'd post it just in case it does apply: http://support.microsoft.com/default.aspx?scid=kb;en-us;258273 Julie "Marcos Mello" <microsoft.com> wrote in message news:com... |
Posted: 26 Sep 2005 06:56 AM PDT In article <com>, "Scotty g" <Scotty microsoft.com> wrote: Scotty, Unfortunately, no. In Project the font characteristics can be customized (e.g. font color, bold, italic, etc.) but the background color cannot be changed. Hope this helps. John Project MVP |
Columns common to Gantt & resource usage view Posted: 25 Sep 2005 10:28 PM PDT You should also try the task usage view. It displays tasks with resources and the priority field is available in the view. "Jan De Messemaeker" wrote: |
Is Project the App for my needs / template for my need Posted: 24 Sep 2005 03:05 AM PDT Hi Lars, Welcome to this Microsoft Project newsgroup :) I don't think Project is for you. It is a project management scheduling package. By definition, a project has a clearly defined start and finish, and you have to enter tasks and assign resources before yu can see a resouce schedule. I don't know of any other project management packa ge that will do what you're afer. Maybe someone else knows. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Lars Andersen wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |