Changing Work day from 8h Microsoft Project |
- Changing Work day from 8h
- Save history
- Filtering for anything from "Today"
- Creating non-standard reports in Project2003
- Is there a way to insert a marker to represent todays date?
- How to change font color based on a condition
- Cost accruel
- Duration of task calculated wrongly - not round up
- View My Tasks (PWA) table in the Database
- How do I clear the "Browsed Pages" when inserting a Hyperlink in .
- Setting variable allocations for resources
- Gantt Chart
- Best way to handle multiple projects
- How to create a variance between scheduled date and 2nd baseline?
- Assignment Units change
Posted: 03 Oct 2005 12:16 PM PDT You're welcome, Bob :-) But a word of caution. You should seldem, if ever, enter Start and Finish dates in Project. If you do, Project will create constraints which could severely limit the flexibility that you could have. Always enter Durations and use the Precedence links to drive the Start/Finish dates. Mike Glen MS Project MVP Bob wrote: |
Posted: 03 Oct 2005 11:22 AM PDT Hi David, Sorry, I know nothing of SQL. You could try posting on the developer newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Mike Glen Project MVP David wrote: |
Filtering for anything from "Today" Posted: 03 Oct 2005 11:16 AM PDT D Pingger wrote: You can make Date1 be equal to Now() using a formula and then filter for tasks whose start is greater than Date1. -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com |
Creating non-standard reports in Project2003 Posted: 03 Oct 2005 09:16 AM PDT Hi Jude, Welcome to this Microsoft Project newsgroup :) You might like to have a look at my series on Microsoft Project in the TechTrax ezine, particularly #24 - Customizing Reports, at this site: http://tinyurl.com/2xbhc or this: http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 (Perhaps you'd care to rate the article before leaving the site, :) Thanks.) FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP JulieS wrote: |
Is there a way to insert a marker to represent todays date? Posted: 03 Oct 2005 09:06 AM PDT Quidam, Not sure what type of marker you want, but there is a line showing the current date in the Project Center (PWA) and the View a Project page for a selected project. For a timescale line for today's date, you have more options in Microsoft Project. Go to Format/Gridlines. See automated guides if interested: http://www.pssi.biz/guides/current_date.htm "Quidam" wrote: |
How to change font color based on a condition Posted: 03 Oct 2005 08:48 AM PDT Hi Aman, Welcome to this Microsoft Project newsgroup :) I would have thought that you could do this within Project uasiong a Customized field. You might like to have a look at my series on Microsoft Project in the TechTrax ezine, particularly #14 & 15, at this site: http://tinyurl.com/2xbhc or this: http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 (Perhaps you'd care to rate the articles before leaving the site, :) Thanks.) FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Aman wrote: |
Posted: 03 Oct 2005 01:35 AM PDT Project is not a cost accounting product. I advise not doing this in Project at all, rather output the relevant tasks and dates to Excel then track partial payments etc there or in your accounting system. -- Rod Gill Project MVP Visit www.msproject-systems.com for Project Companion Tools and more "Eva" <microsoft.com> wrote in message news:com... |
Duration of task calculated wrongly - not round up Posted: 02 Oct 2005 11:53 PM PDT Hi Peter, Welcome to this Microsoft Project newsgroup :) If you don't align working hours as directed in the FAQ, then, say, you have entered a 1 day task, it will start at the 8:00 original time and not the 8.30 that you've now set up. This is because, generally, changing the default only affects the future and not the past. Thus you will have a half hour discrepancy which is the likely source of your decimals. You need to re-enter the Durations to correct this. Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Peter Bons wrote: |
View My Tasks (PWA) table in the Database Posted: 02 Oct 2005 05:09 AM PDT No, Taleq - I don't have a project server - that's why I directed you to ask the question in the correct newsgroup where the experts in PWA etc hang out. Mike Glen Project MVP Talaq wrote: |
How do I clear the "Browsed Pages" when inserting a Hyperlink in . Posted: 01 Oct 2005 08:59 AM PDT That was the first thing that I tried but no go. It seems to have a very old list of web pages. "Brian K - Project MVP" wrote: |
Setting variable allocations for resources Posted: 30 Sep 2005 01:59 PM PDT Hi Larry, I'm sorry. I guess I misunderstood your initial question. The resource calendars will "shuffle the assignments to the day shift or the night shift" for you. The project calendar can still be the 24 Hours calendar but using different base calendars for the 7 resources on days and the 3 resources on night will schedule the tasks correctly. Hope the clarification helps. Julie "snetzky" wrote: |
Posted: 30 Sep 2005 12:33 PM PDT In article <com>, baz <microsoft.com> wrote: baz, Sorry, to actually see the non-working days on the Gantt a minor timescale showing "days" must be displayed. Your question is interesting because most people want to eliminate the non-working days so they can see more of the Gantt's full span. John Project MVP |
Best way to handle multiple projects Posted: 30 Sep 2005 11:22 AM PDT One option is to use the Text fields and give a unique identifier/part no. to the set of 50. However, a project with 5000 activities become hard to use. I find it is easier to use the summary project, and insert (and remove) one or more of the 50 when they are completed. Ron "David" <microsoft.com> wrote in message news:com... |
How to create a variance between scheduled date and 2nd baseline? Posted: 30 Sep 2005 09:23 AM PDT Hi Zooms, Welcome to this Microsoft Project newsgroup :) You might like to have a look at my series on Microsoft Project in the TechTrax ezine, particularly #14 - Customizing Fields, at this site: http://tinyurl.com/2xbhc or this: http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 (Perhaps you'd care to rate the article before leaving the site, :) Thanks.) FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP jloh wrote: |
Posted: 30 Sep 2005 03:31 AM PDT Hi Jan, Are you using Project 2000? I am getting this problem in 2000 version. Can you please try doing this from Gantt view in Project 2000? Thanks, Amit |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |