Pages

Search

Project Predecessors should have mouse over to ID the Task Name Microsoft Project

Project Predecessors should have mouse over to ID the Task Name Microsoft Project


Project Predecessors should have mouse over to ID the Task Name

Posted: 18 Aug 2005 01:57 PM PDT

In article <phx.gbl>,
"JackD" <momokuri@gmail> wrote:
 
Jack,
I wasn't aware of that, but now I am. Thanks

John

Link To-do lists to Tasks

Posted: 18 Aug 2005 01:21 PM PDT


Hi ATL,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP


ATL wrote: 



Non checked out project shows checked out

Posted: 18 Aug 2005 12:19 PM PDT


Hi la0d0g ,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP

la0d0g wrote: 



Can I create a project template?

Posted: 18 Aug 2005 11:58 AM PDT

Please let us know if there is anything else we can help with!
angie
--
This posting is provided "AS IS" with no warranties, and confers no rights.


"Sam" wrote:
 

Can I use multiple resouces for 1 task?

Posted: 18 Aug 2005 08:19 AM PDT

John,

Unfortunately I have not worked with Project for years and I have forgotten
a lot. Thank you for your time in responding to my question. I will look
into the link that you sent also.


"John" wrote:
 

Hierarchy structure in MS Project

Posted: 18 Aug 2005 05:12 AM PDT

schemr --

In the Enterprise Global file, create a new custom enterprise Project
outline code called Sales Manager. Make this a required field and list all
of our sales managers in the outline code structure. Save and close the
Enterprise Global and then exit and relaunch Microsoft Project Professional.
Ask each PM to open all of his/her projects and click Project - Project
Information, select the Sales Manager for each project, and then save and
publish each project using Collaborate - Publish - Project Plan. Add the
new Sales Manager field to each Project Center view in PWA. You might also
want to create a custom Project Center view called Sales Manager that has
grouping applied by default on this outline code. You might also want to
create a custom Portfolio Analyzer view that summarizes project data by the
Sales Manager outline code.

After you and the PM's complete the above series of steps, anyone who can
view the Project Center page will be able to apply grouping or sorting on
the Sales Manager outline code. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


"schemr" <microsoft.com> wrote in message
news:com... 


multiple baseline compare

Posted: 18 Aug 2005 01:33 AM PDT

Hi,

1. To compare two dates (for instance two baselinestartx)
Tools, Customize, Fields, select a number field
Activate Formula
[Baselinestartx]-[Baselinestarty] returns a value in days
projdatediff( [],[], Calendar name) returns a value in minutes
When you select a duration field projdatediff will be expressed in the
normal duration units

2. To show nonstandard bars in the Gantt Chart (such as haveing a hape to
indicate Baselinestart7 or a bar between baselinestart5 and Start)
see
http://www.mvps.org/project/faqs.htm

Faq 31. Customizing Task Bars

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"MAT" <microsoft.com> schreef in bericht
news:com... 
gantt? 


Printing reports with a date range

Posted: 17 Aug 2005 11:24 AM PDT

LadyBean01,
You are correct that Date Range filters out the tasks.
To get the timephased info you are looking for, try temporarily
changing your project start date to June 1. >Project, >Project
Information

Hope this helps!

Resource Usage View Project 2003 Server Master Project Plan

Posted: 17 Aug 2005 11:18 AM PDT

Hi,

All of this is perfectly possible without Project Server, even in Project
Standard, but not knowing Project Server very well I hesitate to gieve a
recipe in a Server environment.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Jerryinnc" <microsoft.com> schreef in bericht
news:com... 
the 
the 
to 
is 
the 
levels. 


how do I add a delay to the entire project

Posted: 17 Aug 2005 10:57 AM PDT

brandon erndt wrote:
 

You could set the status date to equal the date the work will resume for
this project and then hit the 'Reschedule' button on the Tracking Toolbar.
This will move the unfinished portions of all tasks so that they start
after the new status date.

--
Brian K - Project MVP
http://www.projectified.com
--
Senior Trainer - Electronic Arts
--
QuantumPM Associate
http://www.quantumpm.com

Save as MPP vs. Publish to Project Server

Posted: 17 Aug 2005 08:20 AM PDT

Okay, Mike.

All,
Please go to
microsoft.public.project.server
to follow this thread.

Thanks,
Jim


"Mike Glen" <glenATmvps.org> wrote in message
news:phx.gbl... 


how do i display week numbers in project?

Posted: 16 Aug 2005 12:55 PM PDT

In article <com>,
Rompie <microsoft.com> wrote:
 

Rompie,
I have probably heard of ISO week numbers but have never used them. I
also do not use Outlook. Because one MS application (or even several of
them) can do a particular thing doesn't mean all MS applications can do
it. A good example is that in Excel individual Worksheet cells can be
formatted. We get many posts in the Project newsgroup asking how that
can be done in Project, particularly in either of the Usage views.
Unfortunately individual field cell formatting is not an option in
Project.

The only formatting available for the timescale in Project is that
available in the selection lists for Units and labels found in the
Timescale edit window. That window can be accessed by either double
clicking on the timescale or by going to Format/Timescale.

Hope this helps.
John
Project MVP

Views with Gantt Chart Wizard.

Posted: 16 Aug 2005 09:23 AM PDT


Hi Dave,

You could create a new private project. Create your views there and then
transfer them via the Organizer to the working projects. Then, if one gets
changed significantly, you can recover it from your private project.

Mike Glen
MS Project MVP

Dave wrote: