Project Predecessors should have mouse over to ID the Task Name Microsoft Project |
- Project Predecessors should have mouse over to ID the Task Name
- Link To-do lists to Tasks
- Non checked out project shows checked out
- Can I create a project template?
- Can I use multiple resouces for 1 task?
- Hierarchy structure in MS Project
- multiple baseline compare
- Printing reports with a date range
- Resource Usage View Project 2003 Server Master Project Plan
- how do I add a delay to the entire project
- Save as MPP vs. Publish to Project Server
- how do i display week numbers in project?
- Views with Gantt Chart Wizard.
Project Predecessors should have mouse over to ID the Task Name Posted: 18 Aug 2005 01:57 PM PDT In article <phx.gbl>, "JackD" <momokuri@gmail> wrote: Jack, I wasn't aware of that, but now I am. Thanks John |
Posted: 18 Aug 2005 01:21 PM PDT Hi ATL, Try posting on the server newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/. Mike Glen Project MVP ATL wrote: |
Non checked out project shows checked out Posted: 18 Aug 2005 12:19 PM PDT Hi la0d0g , Try posting on the server newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/. Mike Glen Project MVP la0d0g wrote: |
Can I create a project template? Posted: 18 Aug 2005 11:58 AM PDT Please let us know if there is anything else we can help with! angie -- This posting is provided "AS IS" with no warranties, and confers no rights. "Sam" wrote: |
Can I use multiple resouces for 1 task? Posted: 18 Aug 2005 08:19 AM PDT John, Unfortunately I have not worked with Project for years and I have forgotten a lot. Thank you for your time in responding to my question. I will look into the link that you sent also. "John" wrote: |
Hierarchy structure in MS Project Posted: 18 Aug 2005 05:12 AM PDT schemr -- In the Enterprise Global file, create a new custom enterprise Project outline code called Sales Manager. Make this a required field and list all of our sales managers in the outline code structure. Save and close the Enterprise Global and then exit and relaunch Microsoft Project Professional. Ask each PM to open all of his/her projects and click Project - Project Information, select the Sales Manager for each project, and then save and publish each project using Collaborate - Publish - Project Plan. Add the new Sales Manager field to each Project Center view in PWA. You might also want to create a custom Project Center view called Sales Manager that has grouping applied by default on this outline code. You might also want to create a custom Portfolio Analyzer view that summarizes project data by the Sales Manager outline code. After you and the PM's complete the above series of steps, anyone who can view the Project Center page will be able to apply grouping or sorting on the Sales Manager outline code. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com http://www.projectserverexperts.com "We wrote the book on Project Server" "schemr" <microsoft.com> wrote in message news:com... |
Posted: 18 Aug 2005 01:33 AM PDT Hi, 1. To compare two dates (for instance two baselinestartx) Tools, Customize, Fields, select a number field Activate Formula [Baselinestartx]-[Baselinestarty] returns a value in days projdatediff( [],[], Calendar name) returns a value in minutes When you select a duration field projdatediff will be expressed in the normal duration units 2. To show nonstandard bars in the Gantt Chart (such as haveing a hape to indicate Baselinestart7 or a bar between baselinestart5 and Start) see http://www.mvps.org/project/faqs.htm Faq 31. Customizing Task Bars HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "MAT" <microsoft.com> schreef in bericht news:com... gantt? |
Printing reports with a date range Posted: 17 Aug 2005 11:24 AM PDT LadyBean01, You are correct that Date Range filters out the tasks. To get the timephased info you are looking for, try temporarily changing your project start date to June 1. >Project, >Project Information Hope this helps! |
Resource Usage View Project 2003 Server Master Project Plan Posted: 17 Aug 2005 11:18 AM PDT Hi, All of this is perfectly possible without Project Server, even in Project Standard, but not knowing Project Server very well I hesitate to gieve a recipe in a Server environment. -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Jerryinnc" <microsoft.com> schreef in bericht news:com... the the to is the levels. |
how do I add a delay to the entire project Posted: 17 Aug 2005 10:57 AM PDT brandon erndt wrote: You could set the status date to equal the date the work will resume for this project and then hit the 'Reschedule' button on the Tracking Toolbar. This will move the unfinished portions of all tasks so that they start after the new status date. -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com |
Save as MPP vs. Publish to Project Server Posted: 17 Aug 2005 08:20 AM PDT Okay, Mike. All, Please go to microsoft.public.project.server to follow this thread. Thanks, Jim "Mike Glen" <glenATmvps.org> wrote in message news:phx.gbl... |
how do i display week numbers in project? Posted: 16 Aug 2005 12:55 PM PDT In article <com>, Rompie <microsoft.com> wrote: Rompie, I have probably heard of ISO week numbers but have never used them. I also do not use Outlook. Because one MS application (or even several of them) can do a particular thing doesn't mean all MS applications can do it. A good example is that in Excel individual Worksheet cells can be formatted. We get many posts in the Project newsgroup asking how that can be done in Project, particularly in either of the Usage views. Unfortunately individual field cell formatting is not an option in Project. The only formatting available for the timescale in Project is that available in the selection lists for Units and labels found in the Timescale edit window. That window can be accessed by either double clicking on the timescale or by going to Format/Timescale. Hope this helps. John Project MVP |
Views with Gantt Chart Wizard. Posted: 16 Aug 2005 09:23 AM PDT Hi Dave, You could create a new private project. Create your views there and then transfer them via the Organizer to the working projects. Then, if one gets changed significantly, you can recover it from your private project. Mike Glen MS Project MVP Dave wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |