Gnatt Chart and Non Working Days Microsoft Project |
- Gnatt Chart and Non Working Days
- delete certain tasks macro
- Is project 2k3 server overkill for a medium sized company?
- Set non-working days for every other Monday
- How to make Project to adjust task according to resource availabil
- using relative constraint dates
- Removing resource with unfinished tasks
- best task type to use in Project 2002 - fixed duration or units
- Using formula to calc date as part of filter
- slack time looks incorrect goes pass last task
- Resource calendar / scheduling
- Resource group
Gnatt Chart and Non Working Days Posted: 20 May 2005 02:16 PM PDT Deb, You can do that by setting your timescale to weeks instead of days. Regards, Murali "JulieS" wrote: |
Posted: 20 May 2005 02:16 PM PDT In article <com>, Tomcat <microsoft.com> wrote: Tomcat, Rod's suggestion will certainly do what you requested but I offer a caution. It would be nice to know the reason you want to delete tasks with a 1 day Duration. I can think of a few scenarios where 1 day tasks are significant and relevant to a project plan. Deleting them outright may not be the best approach. John Project MVP |
Is project 2k3 server overkill for a medium sized company? Posted: 20 May 2005 11:23 AM PDT Understood Rod, and thanks. Issues associated with publishing can likely be covered through training. As a second step, it might be wise to push the project to MIS/OPs folks first, and let them guarantee security and rights before posting. Now for installation and configuration: on a scale of 1 to 10, where 10 is expert, our companies MIS/OPs group would rate a 4.5. Given the scalability and complexity of the Project server, SharePoint and SQL combo, my guess is that we should hook up with a consultant type post purchase. Many thanks to you Steven "Rod Gill" wrote: |
Set non-working days for every other Monday Posted: 20 May 2005 10:55 AM PDT tx, I tried recording a macro for some hints and it wasn't particularly helpful "JulieS" <passport6847 at maine dot rr dot com> wrote in message news:uaoM$phx.gbl... month |
How to make Project to adjust task according to resource availabil Posted: 20 May 2005 08:34 AM PDT Excellent hint, at least some flexibility! And I would say, âyou can select specific RESOURCE (not task) to levelâ. Project allows to clear leveling for specific tasks, so Iâll try to use combination of both. Appreciate everyoneâs help. IK "Joe" wrote: |
using relative constraint dates Posted: 20 May 2005 07:51 AM PDT This is what I was looking for.... thanks to both of you! Geoff "Reid McTaggart" wrote: |
Removing resource with unfinished tasks Posted: 20 May 2005 07:40 AM PDT Hi Dan, These results may be correct if you changed, for example, the task duration while the task type was set to "fixed work" (while the %Complete was already 50% for ex). The resource Jim L is assigned full time during some days and part time the other days. When you *replace* Jim L by Dan, Ms Project replace Jim L only on the remaining work, may be at part time. So after the replacement, the assignments are : Jim L [100%];Dan [50%] Hope this helps, Gérard Ducouret "Dan McCarty" <com> a écrit dans le message de news:googlegroups.com... Gérard Ducouret wrote: the I *did* try to replace it. When I click the Replace button the resource list goes from Jim L [100%] to Dan [50%] Jim L [100%] If I try to click his name and Replace him *again* (with myself again), I get a message about not being able to assign a resource to a task twice. That makes sence. But when I click OK to dismiss the message another message pops up about deleting an item with "actual values" (as opposed to just "values," apparently). I don't want to delete any work done on the project. How can I just replace the remaining work with another resource? This is Project 2003, BTW. to message delete that many unstarted finished. tasks to |
best task type to use in Project 2002 - fixed duration or units Posted: 20 May 2005 03:31 AM PDT There is no such thing as a "best setting" for task type. The task type is a switch you use when editing work assignments so when you change one of the Work, Duration, or Units variables, Project will recalculate the proper other variable in the triad. As such, the task type setting for a given task might change many times as you refine your plan dependong just what term you're changing and why you're changing it in this particular edit. Example: I have Joe Painter assigned to paint a room. He works an 8 hour day, is assigned 100% to the task, and we estimate it will take 5 days to do the painting. Work = Duration * Units - always, it's Project's Prime Directive and you can never, ever, have a task that violates it. So his 100% committment to 40 hours (5 days) of painting means that task requires 40 man-hours of effort. Now we're about to edit his work assignment to 50%. When we do, we have to ask ourselves just why we're doing that. Is it because we need him free'ed up some of each day to do some other work elsewhere at the same time the room is being painted? If that's the case, the painting will still require the same number of man-hours of effort but the duration it takes to do that will be twice as long. Make the task Fixed Work, change the Units and Project recalculates the duration and sets it to 10 days. Or the other alternative is we have realized it's actually only a 20 man-hour task but we don't need it done any sooner than 5 days none-the-less. While usually you'd want to get it done ASAP, let's say for some reason this time we want to leave it at 5 days. So set the task type to Fixed Duration, edit the Units, and this time Project will recalculate Work and set it to 20 man-hours, or even more logical, set the work to the required 20 man-hours and Project tells us we only need the painter at 50% committment so he can do other stuff part of the time. The identity Work = Duration * Units is just like any other linear equation Y=mX+b. Its terms include a constant, an independent variable, and a dependent variable. You can pick any of the 3 terms and make it the constant by way of choosing the task type, take your pick one of the remaining two terms and edit it, making it the independent variable, and Project will recalculate the third, dependent variable, term for you. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "POP" <microsoft.com> wrote in message news:com... |
Using formula to calc date as part of filter Posted: 19 May 2005 07:56 PM PDT wendyB wrote: Not in the "Value(s)" field, not that I am aware of... -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com |
slack time looks incorrect goes pass last task Posted: 19 May 2005 05:20 PM PDT I think Brian's explanation is most likely. Three other possibilities I can think of: 1 - corrupted file 2 - virtual memory shortage 3 - bar style definitions Regarding #3, is it possible that your bar style definitions are causing you to see the baseline instead of the current plan? In that case, if the schedule has slipped, the lag bars would run past the apparent finish date. -- Reid McTaggart Alegient, Inc., Houston Project Server Experts Microsoft Certified Partner "Brian K - Project MVP" wrote: |
Resource calendar / scheduling Posted: 19 May 2005 03:46 PM PDT Cheers Julie, That's useful info. Just a thought: Would it be possible for MSP to link into people's Outlook calendars, extract the information and then display it in various forms. A simple display of availability would be desirable obviously! Or is this just asking for too much?!!! Thanks, Mark O "JulieD" wrote: |
Posted: 18 May 2005 10:32 PM PDT Hi Sheila, Yes, you can put Max. Units to 500, which means five people are allocated to the project. But this is not a reply to your original question, I quote: "that "group" should include the usual resources." Well, it doesn't include other resources. It's just 5 units of a resource, that's all. Hence my reply that a resource including other resources is not possible. Resource pools help put resoruces in common between multiple projects. Look for help on Resource Sharing. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Sheila" <co.uk> schreef in bericht news:googlegroups.com... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |