Production Manufacturing Microsoft Project |
- Production Manufacturing
- Organizational Help
- New Project
- Can I change the Duration field format?
- Filtering a Resource Graph
- Putting tasks on hold indefinitely
- Project98
- Interim Plans
- Fixed Work Task
- Baseline Work does not equal Work after baseline has been performe
- raise WBS level of task
- Interactive filter to show a task and all it's predecessors
- Project 98 and Value Lists?
- need help
- Special Snapshot View
- Can I print with gridlines accross the columns (Gantt View)
Posted: 29 Apr 2005 07:02 PM PDT Hi Bob, As you know, Duration is always measured in working time, so if Saturday and Sunday are non-working days, the default Duration field does not count them. There is a work around using a custom duration field and a custom calendar. Create a new calendar (Tools>Change Working Time). Copy the Standard calendar, name it (I used 7Day) and make Saturdays & Sundays working days. Then insert a custom duration field ([Duration1] for example) in the task table. Choose Tools>Customize Fields and select the [Duration1] field. Click the Formula... button and use the following formula: ProjDateDiff([Start],[Finish],"7Day") In the Customize fields dialog box, click the Use Formula option for the task and group summary rows. This will calculate the number of calendar days between the start of the task and the finish of the task using the 7Day calendar. . Hope this helps. Let us know how you get along. Julie "bob" <com> wrote in message news:com... |
Posted: 29 Apr 2005 01:36 PM PDT jhalterm -- You cannot create folders in the Project Server database. To categorize your projects, you should consider using either custom enterprise Project fields or outline codes. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant Denver, Colorado http://www.msprojectexperts.com "We wrote the books on Project Server" "jhalterm" <microsoft.com> wrote in message news:com... |
Posted: 29 Apr 2005 11:06 AM PDT There are about 15 subtasks for each of these 5 tasks. It looks like a huge ball of string with 300 trucks and numerous lags. I need to allocate all resources for the tasks, material and labor. A little different from others I have done.. Looking for ideas... Thanks.. "Doug" wrote: |
Can I change the Duration field format? Posted: 29 Apr 2005 09:20 AM PDT Note that there's also a checkbox to remove the space between the number and the letter. -- Reid McTaggart Alegient, Inc., Houston Project Server Experts Microsoft Certified Partner "Madoc Pope" wrote: |
Posted: 29 Apr 2005 08:28 AM PDT Use the FILTER buttom and the given filters. If none of the built-in Microsoft Office Project 2003 filters meet your needs, you can create a new filter or modify an existing filter. On the Project menu, point to Filtered for, and then click More Filters. To create or modify a task filter, click Task. To create or modify a resource filter, click Resource. To create a new filter, click New, and then type a new name for the filter in the Name box. To modify an existing filter, click a filter name in the Filters list, and then click Edit. Under Filter, click a field name and a test. In the Value(s) column, type or select a value to test for or set a range of values by typing two values separated by a comma(,). If the filter will contain more than one criterion row, select new conditions on the row immediately underneath the first row, and then click an operator in the And/Or column of the same row. Click OK, and then click Apply. Regards, --------- Haris Rashid http://www.manage-systems.com ---------------------------------------- "Angela" wrote: |
Putting tasks on hold indefinitely Posted: 29 Apr 2005 07:56 AM PDT Hi, This is how the maintenance shop for Mainframe applications at my biggest customer works. -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Joe" <microsoft.com> schreef in bericht news:com... the task that other. the is on, The |
Posted: 29 Apr 2005 06:58 AM PDT I used 2003 before under my employers group license. Since then I have retired and Windows died. I rebuilt the system and installed my personal copy of project 98. When i double click, nothing happens. No error or message of any kind. I have tried repair and uninstall/reinstall many times and it is the same. Before i spend anymore time on this, i wnated assurance from someone that it works. MediaCenter should be the same as XP Professional. "JackD" wrote: |
Posted: 29 Apr 2005 12:00 AM PDT Interim Plans can be saved in MS Project 2003. You can compare an interim plan with the baseline plan or current plan to monitor project progress or slippage. You can save up to 10 interim plans. By comparing baseline or current information with an interim plan, you can track task start and finish dates only, not work or costs. You can save up to 10 interim plans for each project plan. On the Tools menu, point to Tracking, and then click Save Baseline. Click Save interim plan. In the Copy box, click the name of the baseline or interim plan with the start and finish or baseline start and finish values you want to save. In the Into box, click the name of the interim plan into which you want to copy the values. Click Entire project or Selected tasks to save the portion of the schedule you want. After saving an interim plan, you can view the plan's start and finish dates by inserting its fields into the Task Sheet view; for example, if you've saved three interim plans, you can view the dates saved in the third plan by inserting the Start3 and Finish3 fields Using the Gantt Chart Wizard, you can instantly change the formatting of items such as the critical path, display link lines between dependent tasks, or select color options and patterns for Gantt bars representing summary tasks, subtasks, or milestones. Follow the instructions on the gantt chart wizard and select custom fields in the gantt chart wizard to display the fields related to the interim plan. ----------- Haris Rashid http://www.manage-systems.com "nholt" wrote: |
Posted: 28 Apr 2005 02:13 PM PDT JodyJ, I agree with and am not sure why both resrouces are not updating. That really is something I dont' get either. The reason your units are changing when you change the duration of a task is because you have fixed work selected. Change your type from fixed work to fixed units before you change the duration and then the units will stay the same. Then you will see the hours of work increase or decrease depending on the direction you change the duration. "JodyJ" wrote: |
Baseline Work does not equal Work after baseline has been performe Posted: 28 Apr 2005 11:58 AM PDT Hi Chaz Are you sure you haven't allocated work to a summary task inadvertently? Easy to do. Insert a resource column to check. Regards...............Pratta "chazman" wrote: |
Posted: 28 Apr 2005 10:06 AM PDT you're welcome and thanks for the feedback -- Cheers JulieD "Gayle Ann" <Gayle microsoft.com> wrote in message news:com... |
Interactive filter to show a task and all it's predecessors Posted: 28 Apr 2005 08:30 AM PDT Thanks Jan. That worked just great. Jim "Jan De Messemaeker" wrote: |
Posted: 28 Apr 2005 06:54 AM PDT Hi Steve, It's simple: P98 did not know field customizing at all. So no formula, no graphical indicator, no value list, no specific treatment of summary tasks. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Steve Scott" <microsoft.com> schreef in bericht news:com... correct?? it |
Posted: 27 Apr 2005 10:06 PM PDT you'll need to be more specific -- Cheers JulieD check out www.hcts.net.au/tipsandtricks.htm ....well i'm working on it anyway "catchyogi" <com> wrote in message news:com... |
Posted: 27 Apr 2005 03:09 PM PDT Hi Ryan Have you tried using the Resource Usage view with the master project open. Just insert a column for the project on the LHS. If the fies are open then the filename will show, if not it will show the path. As you have a resource pool then all resources are listed with all the tasks, in all the projects, with the flexibility of roll-up to resource summary level. You can drill down to find the cause of overallocation.. You don't need to do any VBA to get these views. Regards...............Pratta "Ryan P" wrote: |
Can I print with gridlines accross the columns (Gantt View) Posted: 27 Apr 2005 01:00 PM PDT Or ... are you asking if you can have horizontal rows across your Gantt chart? If that's the case: Right click in a blank part of your Gantt chart, choose Gridlines. On the left you'll see "Line to change" and Gantt Rows is an option. Choose a type of line, and even choose what interval you want. Check Print Preview. Again, I may have answered a question that isn't exactly what you were asking. |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |