how to set up duplicate sites on a plan Microsoft Project |
- how to set up duplicate sites on a plan
- File Size Reduction
- Can I run Project 2003 on 98SE?
- How do I show the baseline on all tasks in the Gantt Chart?
- Material Costs
- Can a parent cost field summarize only FILTERED cost data?
- Question: Problem publishing project to project2003server
- date field by default is "NA".
- Updating progress
- Status Indicator for Future Tasks
- Disable automatic calculation on % complete
- Why doesn't SF relation work ?
- Trying to get scheduled hours for a particular time period
- Installing Project on a Terminal Server
how to set up duplicate sites on a plan Posted: 04 May 2005 02:31 AM PDT Hi Sheila, A way of achieving this is to compress the Project tasks by clicking the little minus sign in front of its name, so that you have just the one summary. Now click in the ID cell for that summary to highlight the whole of the task. Now hold down the Ctrl key, then click in the ID cell again and drag downward until a grey indicator line appears immediately under the summary, and let go of the mouse (a bit fiddly but you'll soon get the hang of it!). That should give you a second copy of the file. Compress this second project as above. Now click and drag in the ID cells to select both files. Copy as before to give you 4 copies. This will build exponentially until you have the required number of copies ( about eight copy procedures). It's probably quicker to do than to explain! :) FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/ Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Sheila wrote: |
Posted: 03 May 2005 02:46 PM PDT Hi Kevin, Welcome to this Microsoft Project newsgroup :-) If you suspect a corrupt file, you could try the suggestions in FAQ Item: 43. File Bloat? - Might be Corruption. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/. Hope this helps - please let us know how you get on :-) Mike Glen Project MVP Kevin wrote: |
Can I run Project 2003 on 98SE? Posted: 03 May 2005 02:08 PM PDT Hi Slikroad, Welcome to this Microsoft Project newsgroup :) Alexander is correct. In this web site: http://www.microsoft.com/office/project/prodinfo/standreq.mspx , you'll find the Operating System has to be: Microsoft Windows® 2000 with Service Pack 3 (SP3) or later, or Windows XP or later. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/ Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Alexander Barvinsky wrote: |
How do I show the baseline on all tasks in the Gantt Chart? Posted: 03 May 2005 01:09 PM PDT That's why I usually don't teach them that! |
Posted: 03 May 2005 12:13 PM PDT Dale: Thank you so much. I was thinking it would use the cost per use field. -- John Cello John Cello Consulting Communications For Business www.johncelloconsulting.com "John Cello" wrote: |
Can a parent cost field summarize only FILTERED cost data? Posted: 03 May 2005 12:02 PM PDT Hello Danna, Instead of using filters, try the Grouping feature : Project / Group by / More Groups... Gérard Ducouret "danna" <microsoft.com> a écrit dans le message de news:com... visible) I |
Question: Problem publishing project to project2003server Posted: 03 May 2005 09:51 AM PDT Thanks Mike - I've already posted there, but received no reply. So I thought I'd try here also... "Mike Glen" wrote: |
date field by default is "NA". Posted: 03 May 2005 09:30 AM PDT Thank you all for the advice "Rod Gill" wrote: |
Posted: 03 May 2005 03:58 AM PDT Hi Paul, Well, you got me to wondering so I fired up an old computer with Project 98 on it. I created a project with a start date of 18 April 2005. When I check Project Information, the Current date is today (3 May 2005) at 8:00 am. When I set a status date (22 April 2005 ) it shows 5:00 pm. The only changes I noted quickly between Project 98 with SR-1 and Project 2003 with SP-1 is the Update Project command. In Project 98 even though I set a Status Date of 22 April 2005, the Update Project command wanted to update tasks as of the current date (today). This caused a problem when I used the Reschedule Uncompleted work button off the tracking toolbar. All incomplete tasks were rescheduled to start today, not 25 April 2005. The Reschedule uncompleted work to start after portion of the dialog box defaulted to 8:00 am today in Project 98 and defaulted to the Status Date and time (5:00 PM) in Project 2003. Personally I find having the manually change the Update through to the Status date to be much more of an irritation. My experience has been that frequently PMs are updating progress as of a date (Status) in the past. They get the information on progress from their resources on Monday or Tuesday and that progress (or lack of) is through the Friday night of the previous week. The only reference I can find to the similarities between the Current Date and the Status date is that if the Status Date is set to NA, project will use the current date. From help: "If you set the status date to NA, Project uses the current date as the status date." I don't think I have helped any, but I guess I would say this is not a bug - in my opinion it's more logical. ;-) Julie "Paul S" <microsoft.com> wrote in message news:com... |
Status Indicator for Future Tasks Posted: 03 May 2005 12:22 AM PDT Hi Ris, You are most welcome and thanks for the feedback. I think that's the first time I've ever been called an angel! Julie :-) "Ris" <microsoft.com> wrote in message news:com... |
Disable automatic calculation on % complete Posted: 02 May 2005 11:40 PM PDT Hi Ris, Welcome to this Microsoft Project newsgroup :) Project measures the %Complete based on the number of working periods completed against the total number of working periods planned. The Duration is just a measure of the working time between start and finish. Thus Doration and %Complete are inextricably tied and you can't change one without the other. (This, perhaps, is a good reason not to track staff tasks within a project.) However, If you look at the % Work completed, it could give you what want as it will remain correct irrespective of the end date, provided the task is of Fixed Work type and changing the end date does not introduce more or less work. That being said, it is not good practice ever to insert start and finish dates as that is what Project is for - to calculate the schedule for you. You enter the precedence link and the Duration and Project will calculate the dates for you. Another possibility is to create a hammock task that expands or contracts with the controlling milestones - please see FAQ Item: 19. Hammock Tasks. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/ Hope this helps - please let us know how you get on :-) Mike Glen Project MVP Ris wrote: |
Why doesn't SF relation work ? Posted: 02 May 2005 09:47 PM PDT Let me make sure I get this straight: SF (Start to Finish) I use it to link tasks to a predecessor like an Inspection. The WBS doesn't necessarily have to be the actual sequence (i.e. This comes before that, and that comes before the next thing) So I use SF to link the end of a task to the beiginning a an "Inspection" task that might actually be ten lines above the successor. Am I abusing the spirit and integrity of the SF? |
Trying to get scheduled hours for a particular time period Posted: 02 May 2005 08:57 PM PDT Hi John and Pratta, Thanks for your suggestion. I tried the option you gave me: changing the Major scale and Minor scale. Here I didn't really understand your guidelines that 'taking the difference between the two valuesâ. I was wondering whether is that I have to do manually or is there any kind of filter available to do this? I am quite interested in trying the simple VBA code which John mentioned. John, can you please let me know where I can find that code online, or is there any discussion group that discusses about that. Please suggest. Thanks again for you replies. "John" wrote: |
Installing Project on a Terminal Server Posted: 02 May 2005 02:56 PM PDT That's why it's the recommended solution: yes. Make sure you follow the white paper configuration recommendations though. If you expose Terminal Services to the Internet you need very careful security measures. -- Rod Gill Project MVP Visit www.msproject-systems.com for Project Companion Tools and more "MayWee" <microsoft.com> wrote in message news:com... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |