Newbie Question - How to delay a project Microsoft Project |
- Newbie Question - How to delay a project
- Version Confusion
- is there a way to view a gantt of one resource in project 2003?
- Holiday Days
- can i level one resource in project 2003?
- Dependencies
- compress timescale
- Baseline & Leveling
- how to refer to a task by it's ID number
- Critical path when summary tasks are linked?
- Comparing baseline and projected finish dates
- Is there a way to get text to autowrap in Project, without having.
- how do I schedule a task for one hour per day?
- Publishing to web
Newbie Question - How to delay a project Posted: 29 Mar 2005 02:35 PM PST If work has not yet begun, you can simply change the project start date: (Project, Project Information). If work has been done, nad the remainder needs to be delayed, you can go to Tools, Tracking, Update Project, Reschedule Uncompleted Work to Begin After: [set date]. -Reid "Damien Sawyer" wrote: |
Posted: 29 Mar 2005 09:28 AM PST In article <0d4a01c5348c$8afd77a0$gbl>, "Karen" <microsoft.com> wrote: Karen, Although I tend to agree with Jan there may be a couple of other possibilities. Is you co-worker using Project 2000 with the SR-1 update? For that matter, does your version of Project 2003 have the latest updates? I don't know if that would have any effect but it might be worth looking into. Another thing to try is saving your Project 2003 file as a Project database. Then see if your co-worker can open it. Maybe there is some corruption and saving as a database may just clear it. You might also want to go to the MVP website at: http://www.mvps.org/project/faqs.htm and look at FAQ 43. Hope this helps. John Project MVP |
is there a way to view a gantt of one resource in project 2003? Posted: 29 Mar 2005 08:12 AM PST John wrote: sure did, thanks again! (and thanks to everyone else as well for their suggestions) |
Posted: 29 Mar 2005 07:41 AM PST Hi this is only possible in the gantt chart if you change it to show the specific resource's calendar (format / timescale / non-working time, calendar drop down) and this "works" if you then filter only for the resource and then print it out ..as you can see it "messes" up the gantt chart for everyone else. however, you might like to check out Jan de Messemaeker's site - as he has an alternative approach which i think works well ... http://users.online.be/prom-ade/ check out the article under the ENGLISH section - Microsoft Project - An Abstract (and needless to say, always try something new on a copy of the project file!) Cheers JulieD "C Kennerdale" <microsoft.com> wrote in message news:com... |
can i level one resource in project 2003? Posted: 29 Mar 2005 07:12 AM PST thanks, worked great. Dale Howard [MVP] wrote: |
Posted: 29 Mar 2005 06:55 AM PST Your boss also needs to understand that with certain exceptions you do not input the task start and end dates into Project. It's primary job is to be a schedule calculator - you tell it when the project can start and then it tells you all the task start and end dates, not the other way around. If you are inputting tasks with their start and finish dates that he's somehow come on his own, you're essentially hunting flies with an elephant gun, using the software simply to illustrate a schedule, something much more easily done with a paper calendar and box of magic markers. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Karen" <microsoft.com> wrote in message news:0c4701c5346f$6050f620$gbl... |
Posted: 29 Mar 2005 05:41 AM PST Hi Kim, Format, Timescale allows to compres sthe timescale. This setting, however, is constant through time so you can't selectively compress, sorry. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Kim" <microsoft.com> schreef in bericht news:com... am in |
Posted: 29 Mar 2005 05:37 AM PST glad its solved and thanks for letting us know! "mic994" <microsoft.com> wrote in message news:com... |
how to refer to a task by it's ID number Posted: 29 Mar 2005 01:23 AM PST Hi Elena, That is unfortunately not possible in a formula. You can only address fields of the task itself, and Project fields. It is possible in VBA. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Elena Osipova" <Elena microsoft.com> schreef in bericht news:com... the other |
Critical path when summary tasks are linked? Posted: 28 Mar 2005 06:05 PM PST You're welcome, Dave :-) Mike Glen MS Project MVP davekmd wrote: |
Comparing baseline and projected finish dates Posted: 28 Mar 2005 04:07 PM PST hi Alan, on the MS Project menu bar click VIEW > TABLES > MORE TABLES > VARIANCE. This will give you the schedule variance. The Variance field shows the calculated difference between planned and scheduled information. Regards, Haris "Alan" wrote: |
Is there a way to get text to autowrap in Project, without having. Posted: 28 Mar 2005 03:51 PM PST In article <com>, chuszo <microsoft.com> wrote: chuszo, Which "text" are you trying to autowrap? Basically Project can only wrap text if there are spaces in the text string. If you are simply trying to have the Task Name wrap, depending on which version of Project you are using, row height can either be set for all task rows only (Project 98 and earlier) or individual task rows (Project 2000 and later). There are two ways to set the row height of all rows. Either select the whole view and drag one of the row separator bars or go to View/Table/More Tables and hit the "edit" button for the selected view. In the lower right corner of the Table Definition window there is a row height adjustment. This is Project's version of "word wrap". Set the value to whatever row height is necessary to allow all wrapped text to show. Hope this helps. John Project MVP |
how do I schedule a task for one hour per day? Posted: 28 Mar 2005 12:45 PM PST Hi Norm, Welcome to this Microsoft Project newsgroup :) You might like to have a look at my series on Microsoft Project in the TechTrax ezine, particularly #5 - Working With Resources, at this site: http://tinyurl.com/2xbhc or this: http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 (Perhaps you'd care to rate the article before leaving the site, :) Thanks.) FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP NormBowler wrote: |
Posted: 26 Mar 2005 07:47 PM PST For a Gantt, output it to a gif using EditCopyPicture and stick it on a web page. Dave Steph. wrote: that I can to webpage server and university the could |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |