Pages

Search

Schedule from (date) in master project Microsoft Project

Schedule from (date) in master project Microsoft Project


Schedule from (date) in master project

Posted: 23 Mar 2005 04:53 PM PST

Hi Leslie,

I cannot give a definitive answer, but I suspect the scheduelling from start
of the Master is trying to overrule the individual schedule from finish
projects. It can only truly reflect the state of the Master when all the
sub-projects are open as, until you open the subprojects, it hasn't the data
to complete any calculatons. I always recommend that all sub-projects are
opened when you're working on a Master file as this will ensure all work
will be propagated downwards.


Mike Glen
Project MVP




LeslieF wrote: 



24 Hour/Day Schedule

Posted: 23 Mar 2005 03:17 PM PST

and for the start of the project, ensure that your date format displays time
as well -tools / options / view -date format
and then set it under project / project information - start date
you might also like to ensure that you've selected the 24hr calendar in the
calendar drop down box in this screen as well.

Cheers
JulieD


"ss" <microsoft.com> wrote in message
news:com... 


Master project error

Posted: 23 Mar 2005 02:21 PM PST

30 projects is a lot. Maybe your computer memory is overtaxed. Have you
tried with fewer subprojects? Project does weird things when memory gets
short.

-Reid

"LeslieF" wrote:
 

What software application did Microsoft Office Project originate f

Posted: 23 Mar 2005 01:15 PM PST

I remember a Project for DOS which I think was from Microsoft. This evolved
into Microsoft Project for Windows in '90

--

Rod Gill
Project MVP


"JackD" <momokuri@gmail> wrote in message
news:phx.gbl... 


Relationship lines color

Posted: 23 Mar 2005 01:05 PM PST

Thanks JackD, that did the trick!

"JackD" wrote:
 

2002 vs. 2003

Posted: 23 Mar 2005 11:53 AM PST

Was calculation set to automatic in Project 2002? If not, then editing
something in Project 2003 (automatic calculations is on by default) will
force a recalc which would of course change dates.

--

Rod Gill
Project MVP


"Jodi" <com> wrote in message
news:com... 


collaboration with Web Access

Posted: 23 Mar 2005 10:57 AM PST

Dima --

You should NEVER purchase Microsoft Project for team members, unless you
want total chaos. Team members and executives should use PWA for their
project work, while project managers should use both Microsoft Project
Professional and PWA for their work. I don't have the time to answer your
question in detail, therefore, for a list of features in PWA you should
refer to the following link:

http://office.microsoft.com/en-us/FX010857951033.aspx

Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"


"Dima" <microsoft.com> wrote in message
news:com... 


Manual Box Positioning on network diagram

Posted: 23 Mar 2005 10:17 AM PST

Thanks Mike.

It only happens in this particular project. I have other projects (separate
files actually) and it works fine. I just updated from project 2002 to 2003
one week ago and it is the first time I open up this project, so I wonder if
something on the file is not liked by 2003... I'm going to try to open the
file in another PC with Project 2002 to see what it does.

Ivan

"Mike Glen" wrote:
 

Enterprise global

Posted: 23 Mar 2005 09:41 AM PST

Kim --

Refer to the following link:

http://www.projectserverexperts.com/Shared%20Documents/checkinprojectsandresources.htm

Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"


"Kim" <microsoft.com> wrote in message
news:com... 


How do I change the color of text in a Gantt?

Posted: 23 Mar 2005 08:27 AM PST

In article <com>,
Dave S <microsoft.com> wrote:
 

Dave,
No you're not missing anything other than perhaps an "outside of the
box" approach. If the text on the right is red, all the text on the
right is red. However what I was suggesting is a little different. I
suggested that the tasks bum17 wanted to highlight could have an entry
in a spare text field. I suggested a spare text field so he/she could
enter special text that was not dependent on other text for the task
(e.g. Task Name). Then set the color of text on one side of the Gantt
bar to whatever highlight color is desired and display the contents of
the spare text field on that side. Only those tasks that have an entry
in the spare text field will show the highlighted color.

The bottom line is it can be done, but . . . the method I suggest may
not be convenient.

John

How do I manage multiple Jobs in a single project worksheet?

Posted: 23 Mar 2005 08:19 AM PST

Hi,

The most simple advice I generally give on this matter is:
If your projects have to be managed by more than one person, you need
multiple files.
If not, use a single file. It is 100 times simpler.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Hank Lambert" <microsoft.com> schreef in bericht
news:com... 
mounts, 
we 


Sub task dependencies

Posted: 23 Mar 2005 07:35 AM PST

In article <com>,
"SL" <microsoft.com> wrote:
 

SL,
First your post doesn't mention anything about linkages between the
subtasks. Since you are expecting dates to move I will assume the 3
subtasks are linked in the default (i.e. finish-to-start).

Given the above assumption there are a couple of ways to get what you
want. Probably the easiest is to use "reverse scheduling". Go to
Project/Project Information. Set the "Schedule from" option to the
Project Finish Date. Then enter the desired Start Date of subtask 3.

Reverse scheduling will ensure that all tasks start as late as possible
even though the Constraint Type field shows "as-soon-as-possible".
Therefore, when you constrain the third subtask to start on a particular
date, all the other tasks will move to accommodate that date.

Hope this helps.
John
Project MVP

Resource Pools and templates

Posted: 23 Mar 2005 05:47 AM PST

I don't see why not - I haven't tried - why don't you?

Mike Glen
Project MVP




com wrote: 



Remove actual work entries

Posted: 23 Mar 2005 05:37 AM PST

You're welcome. Life is easy when the questions are so clear.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Tom Friske" <microsoft.com> schreef in bericht
news:com... 
entered 
happened 
do 

with 
Is 


Adminstrative Time template

Posted: 23 Mar 2005 02:27 AM PST

You're welcome, Paul :-)

Mike Glen
MS Project MVP





Paul Linscott wrote: 



Is there a Project Viewer?

Posted: 21 Mar 2005 07:05 PM PST

Hi Mike

Many thanks for your reply. This has helped, thank you! I have saved the
mvp site as a fav.

Thank you!


"Mike Glen" wrote: