Update Project Dialog Box Microsoft Project |
- Update Project Dialog Box
- to show actual % of work completed
- How do you remove a subproject from a master project?
- Project capabilities
- Project 2003 - reformatting summary tasks, tasks, & subtasks
- Can I set repeating subtasks for each task entered in Project?
- I need to specify time as well as date in Constraint Date
- can't find Microsoft Project 9.0 OLE DB on my list of OLE DB Providers
- Auto Filter
- How do I set up a Mail client server in Outlook
- Screens
- Custom Fields in Project
- is scheduling from a finish date the best way to approach this scenario
Posted: 10 Mar 2005 11:53 AM PST Hi Anita, Those settings control how Project updates % Complete on tasks that should have been in progess (but not finished) as of the status date (date appearing in the Update Project dialog box). The choice set 0-100% complete would mark a task that should have been started by not completed as of the date the appropriate % complete. For example, a 10 day task that that started on 28 April 2005 should have been 50% complete as of 4 March 2005. If I choose "set 0-100% complete it is marked as 50% complete. If I choose 0 or 100% complete only the same task with the same update date (4 March) the % complete is not touched by Project because it is not scheduled to be completed until 11 March 2005. Hope this helps. Let us know how you get along. Julie "Anita" wrote: |
to show actual % of work completed Posted: 10 Mar 2005 11:23 AM PST Hi ML, I'm not sure from your post if you want to show the % work complete in the task sheet (in which case follow "Project Slaves" direction) or as text next to the bar in the Gantt chart. To show % Work Complete next to the bar, choose Format> Bar Styles. Find the bar for the task type (Normal, Critical etc.). At the bottom of the Format Bar Styles dialog box, click the Text tab, select where you want the text to appear (Left, Right etc.) and select % Work Complete from the field list. Hope this helps. Let us know how you get along. Julie "ML" wrote: |
How do you remove a subproject from a master project? Posted: 10 Mar 2005 11:13 AM PST Hi Todd, Have you installed SP-1 for Project 2003? The ability to remove a subtask was a bug that was fixed. See the KB article: http://support.microsoft.com/default.aspx?scid=kb;en-us;834684 The hot fix referenced was included in SP-1. See KB article: http://support.microsoft.com/default.aspx?scid=kb;en-us;837240 for details and download instructions. Hope this helps. Let us know how you get along. Julie "Todd Olson" wrote: |
Posted: 10 Mar 2005 10:25 AM PST In article <phx.gbl>, "JackD" <momokuri@gmail> wrote: Jack, I respect your opinion. Thanks for weighing in. Actually with regard to the accounting month issue, the method I use does not try to do it all in Project. Like you said, the Project timescale can NOT be changed to accommodate a non-standard calendar. However, the data CAN be converted and exported to an application where it can be readily integrated with other company financial systems. With regard to cost. If a macro or add-in is developed to provide needed functionality, why can't it be made available to all users in a company, whether there are 10 employees or 10's of thousands? It is no different than existing add-ins and utilities. And I do agree, some of the requests for added "functionality" are NOT worth the effort to write up in code. I think we have both seen that on this newsgroup. However, I think it is always wise to think outside of the box, but it isn't always worth the effort to implement the resulting solution. John |
Project 2003 - reformatting summary tasks, tasks, & subtasks Posted: 10 Mar 2005 10:01 AM PST Yay! Worked like a charm! Thank you so much! "JulieS" wrote: |
Can I set repeating subtasks for each task entered in Project? Posted: 10 Mar 2005 09:43 AM PST Hi Laura, The macro not recording the indent is odd. If you look at the VBA code in the VB Editor does the code include the text "Outline Indent" (without the quotes.) As far as the linking to previous tasks, that is controlled Project wide through Tools>Options the Schedule tab and the choice "AutoLink Inserted or Moved Tasks". If that option is on, you should see the linking occurring even without the macro. What version of Project are you using? Julie "Laura" wrote: |
I need to specify time as well as date in Constraint Date Posted: 10 Mar 2005 07:26 AM PST Hi Mike absolutely, firstly ensure that you're seeing your times in the start & finish columns (tools / options / view - change the date format to one that includes the time as well) .. now when you set your constraints (an remember, try to minimise the number of constraints in a project - use links instead where possible) ... choose the date as per normal then at the end of the year bit click in the cell, press the space bar and type the time (e.g. 7:00 am) Hope this helps Cheers JulieD "Mike" <net> wrote in message news:googlegroups.com... |
can't find Microsoft Project 9.0 OLE DB on my list of OLE DB Providers Posted: 10 Mar 2005 06:50 AM PST Hi Julie, Yes the Project 10 OLE DB provider did appear once I went to the "Other/Advanced" choice in the Data Connection Wizard. According to the Prjoledb.htm file "To view data access pages on a local provider, you need to use Microsoft Access 2000 or 2002 along with Microsoft Project installed on the computer viewing the provider. Microsoft Project automatically installs the OLE DB Provider, any international .dll, the appropriate registry keys, and any needed ActiveX controls." So I don't know if modification of your installation of Project is in order. Sorry, I installed project so long ago I don't recall the installation settings I selected. I do know I installed Project *after* installing Access. Hope this helps. Cheers! The Other(2) Julie "JulieD" wrote: |
Posted: 10 Mar 2005 02:34 AM PST Hi Empowerment Group, Are you typing in the test or selecting it from the list of durations in the Custom AutoFilter? If you are typing, are you adding the quotes around the duration or just entering the number and measurement unit? If I type in "3d" with the quotes, I get a message "The entry is not valid." However, typing in the quotes shouldn't work for any filter in the duration field. Hope this helps. Let us know how you get along. Julie "The Empowerment Group" wrote: |
How do I set up a Mail client server in Outlook Posted: 09 Mar 2005 05:19 PM PST Joe, This NG is dedicated to the Microsoft Project software. You would have better luck posting in an NG dedicated to Outlook. SarahK |
Posted: 09 Mar 2005 01:39 PM PST Tools>Customize>Toolbars... Select Commands tab, then click "View" in "Categories",then try to find "View" dropdown list in "Commands" window, then drag and drop it to the toolbar "Harry" wrote: |
Posted: 09 Mar 2005 12:17 PM PST Try to make a template for this kind of project with your custom fields even value lists for these fields if you want "Harry" wrote: |
is scheduling from a finish date the best way to approach this scenario Posted: 09 Mar 2005 08:17 AM PST Hi Jan thanks for this ... Cheers JulieD "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message news:phx.gbl... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |