Resource overallocation Microsoft Project |
- Resource overallocation
- How do I set up an annual GANT chart?
- outline tasks in Project
- Report export to Excel?
- Resetting the defaults?
- set up a project management task, that automatically extends
- Is there a good elearning/online learning provider tool for MS Pr.
- Earned Value re BCWP at Task and Resource Level
- Resource vs. Task Dependency
- Using Project for a Time & Materials contract
- Traffic light graphic indicators
- Resources as Crews
- Project Problems - BUGS!
- Running multiple projects with MS Project
Posted: 31 Jan 2005 12:21 AM PST Hi Fei, Your resource grapg probably sjhows Peak Units. Right-Click in the graphical part and show either work or %allocation, that will clarify. HTH -- Jan De Messemaeker Microsoft Project MVP +32 495 300 620 http://users.online.be/prom-ade "Fei" <microsoft.com> wrote in message news:com... |
How do I set up an annual GANT chart? Posted: 30 Jan 2005 06:43 PM PST Hi Liz did you post it to a general group - did you have any success with an answer. Personally, i would use Excel for this type of thing - but you are limited to 256 columns ... which means you can't quite do the whole year :( - 2 sheets each with 6 months? Cheers JulieD "Liz" <microsoft.com> wrote in message news:com... |
Posted: 30 Jan 2005 02:51 PM PST Hi if calculation is set to automatic (Tools/Options/Calculation) - could you give us an example of one summary and two tasks - and explain what you are seeing and what you expected to see. Cheers JulieD "ToArant" <microsoft.com> wrote in message news:com... |
Posted: 30 Jan 2005 09:51 AM PST In article <com>, Kamil Dursun <microsoft.com> wrote: Kamil, Cut and paste is the brute force approach but it will certainly work in a pinch. I wouldn't want to use it though on a regular basis - too error prone and very inefficient. John |
Posted: 30 Jan 2005 06:28 AM PST I'm not keen on fooling around with the unknowns, so I went into Tools - Options and adjusted as I needed, as it happens there was only a couple of changes I needed to make. Thx again Guys, Colin D. "John" <com> wrote in message news:microsoft.com... : In article <phx.gbl>, : "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> : wrote: : : > Colin D -- : > : > I am not aware of any automatic way to restore the defaults to their : > original conditition. Therefore, I would suggest you click Tools - Options, : > select the page you wish to reset and then click the Help button in the : > dialog. The Help for each page of the Options dialog tells you the default : > settings. Hope this helps. : : Dale/Colin, : One way to reset all defaults is to replace your existing Global file : with a backup Global. When older versions of Project were installed, a : backup Global was installed in the same folder as the active Global, : however I did a quick check and didn't find that to be the case with : current versions (maybe I just didn't dig deep enough). Nonetheless, : search for the location of you existing Global, change its name (e.g. : GlobalBU.mpp or similar) and then open Project. If I remember correctly, : Project will not find the Global and will therefore generate a new : default one. : : If you want to keep some of the custom settings, first use the Organizer : to transfer them from you existing Global to a dummy Project file. Then : use the Organizer to put them in your new default Global. : : Hope this helps. : John : Project MVP |
set up a project management task, that automatically extends Posted: 29 Jan 2005 06:17 AM PST You're welcome and thanks for the feedback "HarryPMP" <microsoft.com> wrote in message news:com... |
Is there a good elearning/online learning provider tool for MS Pr. Posted: 28 Jan 2005 02:29 PM PST I've heard good things regarding the courses from International Institute of Learning, www.iil.com. Several people that frequent this forum have been associated with them and might provide more feedback. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Marie" <microsoft.com> wrote in message news:com... |
Earned Value re BCWP at Task and Resource Level Posted: 28 Jan 2005 11:23 AM PST In the tools, Options menu, Calculation tab, make sure the first item "Updating task status updates resource status" is turned on. That option sets or severs the link between % Complete and % Work Complete. It's slightly misleading in its wording because it seems to imply it's a one-way connection when in fact it's two-way. With it turned on, entering % Complete also updates Actual Work and entering Actual Work updates % Complete. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "tdbcalif" <microsoft.com> wrote in message news:com... |
Posted: 28 Jan 2005 10:49 AM PST You can get much the same effect with resource calendars and the leveling engine although it doesn't give you any graphical indication of a "link." Task dependencies sequence tasks based on their logical relationships in the project's physical processes. Resource dependencies sequence tasks based on the availability of the resources required to do the work. How does that differ from Project's present method of leveling to sequence tasks to resolve overallocations, coupled with using task priorities to establish a preferred after-leveling order and the behavior of the resource calendar governing what time periods in which it is possible for the task to occur? As far as I know, "resource dependencies" allow the PM to say "I want Joe to do tasks A and B and since I already know he's not going to be able to do both of them at the same time, I sequence them with a link." But that's just doing manually what leveling does for you. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "JackD" <momokuri@gmail> wrote in message news:phx.gbl... |
Using Project for a Time & Materials contract Posted: 28 Jan 2005 08:34 AM PST Steve, Thanks for the info. Now to play with it some and see if I can molify my boss. Brown "Steve House [MVP]" <send.hotmail.com> wrote in message news:phx.gbl... |
Traffic light graphic indicators Posted: 28 Jan 2005 08:27 AM PST Hi Anton, I was hoping you'd try a formula of your own! In the Graphical Indicators dialog, for the first Test select "is less than or equal to" and in Value type in 25% and select the Red disk. Follow that pattern for the other tests. Mike Glen Project MVP Anton wrote: |
Posted: 28 Jan 2005 08:21 AM PST Hi Glenn, Welcome to this Microsoft Project newsgroup :-) I don't know if I read you correctly, but provided you don't want to assign them by name, you could call them, say, workers. Then in the Resource Sheet view, double-click workers to bring up the Resource Information dialog. In the General tab, you can create a profile of how many resources there are in this group by changing the Units % and the date when the change takes place. FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :-)) Mike Glen MS Project MVP Glenn wrote: |
Posted: 28 Jan 2005 08:05 AM PST Hi Steve i can't replicate it either in a new file - but the problem was on a big project file that was heading towards total corruption .... and it had heaps of sub-tasks that were successors to their summary tasks - i looked at the printout prior to these problems occuring and these tasks where not sub-tasks of the summary tasks at that stage .. they then got moved around ..... and this was the start of the problems with the file ... another problem with this file was the summary task's durations were not calculating correctly and every time you did anything in the file you got a circular error message which the users had been ignoring for about 2 weeks!!!! (luckily we resuced the file and all is well now) Cheers JulieD "Steve House [MVP]" <send.hotmail.com> wrote in message news:%phx.gbl... |
Running multiple projects with MS Project Posted: 27 Jan 2005 06:49 PM PST Hi Skip, Thanks for the feedback. Let us know if you have any other questions. Julie "Skip" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |