label split task bar Microsoft Project |
- label split task bar
- BCWP Calculation Aberration
- label a split task bar
- Print list of linked projects to resource pool?
- Let Project pick a resource from an able grup
- Exporting reports to excel
- Mailing list labels from outlook
- Mailing labels from outlook
- Resource Graph over-allocation
- Repeating Tasks
- How do you make the entire week workdays?
- RBS changes needed
- MS Project - Overallocated Resources - Different Cost
- Recurring tasks with oddset schedules... HELP
- Status Date and Current Date
- Can Project send emails using Novell Groupwise?
- Compatibility problem with MS Project 2003
- MSProject - how to place user defined "Custom File Properties" on.
- stacking pictures in microsoft word
Posted: 14 Feb 2005 11:27 AM PST I'd give the same answer as the others gave you, but I'll also add that you might want to reconsider the approach you've taken. If at the end of all those fits and spurts of activity, the end of the sequence you've created, there's one deliverable completed then what you're doing is ok, if somewhat akward. But if each of those occurences produces its own deliverable (and just guessing I'll bet that's the case, it is 99% of the time you have a series of tasks like that), then it's another story and they really should be listed in the plan as independent tasks. If you were painting the offices on a certain floor, each office takes 1 day and you figured you could do one of them every month, in between other work taking place, it would not be one task "painting" interrupted a number of times. Instead it should be a series of separate tasks "paint room 201" "paint room 202" "paint room 203" ... each of them at whatever point in the work that particular room gets done. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "pocketbattle1" <microsoft.com> wrote in message news:com... |
Posted: 14 Feb 2005 09:47 AM PST Yes, I have tried this. No help. But thanks for the response. - Will "Gérard Ducouret" wrote: |
Posted: 14 Feb 2005 07:51 AM PST That is the way it is. You only get text left, right, center above and below. I suppose if you really wanted, you could write some visual basic which would look at the task, determine the number of splits, use a spare text field to write out the task name that many times, determine the approximate length of the text string and the total length of the task and set the timescale accordingly, but it would probably not work for all tasks at the same time. Why not just create multiple tasks and roll them up to a summary task? Working with split tasks is usually not a good thing. -- -Jack ... For project information and macro examples visit http://masamiki.com/project .. "pocketbattle1" <microsoft.com> wrote in message news:com... need the occured. inside ive clarified |
Print list of linked projects to resource pool? Posted: 14 Feb 2005 04:19 AM PST Hello DTScheduler Sorry, my keyboard made a mistake ;-) AFAIK : As Far As I Know Gérard "DTScheduler" <microsoft.com> a écrit dans le message de news:com... any go to write |
Let Project pick a resource from an able grup Posted: 13 Feb 2005 08:23 PM PST Oh well, I guess I will just keep manually shuffling. Thanks for the replies. Although the functionality is not available to me, at least I can stop looking for it. Cheers "Marky C" wrote: |
Posted: 13 Feb 2005 07:03 AM PST In article <com>, "Gilad" <microsoft.com> wrote: Gilad, Another option is to use VBA to export whatever data is needed and then format as required. John Project MVP |
Mailing list labels from outlook Posted: 12 Feb 2005 07:33 AM PST Hi Casie if you go to the following page - you'll see details about MS communities - the outlook link or the office link would probably be what you're after. http://www.microsoft.com/communities/newsgroups/default.mspx Cheers JulieD "Casie" <microsoft.com> wrote in message news:com... |
Posted: 12 Feb 2005 07:27 AM PST Hi Cassie, Thanks for your input. :) From Outlook, I went to Help/Microsoft Office Online and I don't see a link to Office Discussion Groups. To help us get this sorted, could you retrace your steps again to confirm the selections you made? Perhaps you could copy/paste the URL? Thans. Mike Glen Project MVP Casie wrote: |
Resource Graph over-allocation Posted: 11 Feb 2005 07:11 PM PST To the curious: Problem solved. Two problems: 1. Resource graph did not show work but peak units, 2. And in the assignment of the resource units had received the work value. -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "pominoz" <microsoft.com> schreef in bericht news:com... (not resource my graph day. and |
Posted: 11 Feb 2005 12:05 PM PST Rod - thanks for the thoughts. I played with it last eve. and here's what I came up with that works. I set up 3 recurirng tasks as follows. One called Nights, runs for 3 days, then repeats every 12th day. One called Off, runs for 3 days and repeats every 6th day. Lastly, one dalled Days, runs for 3 days, repeats every 12th. I made all the days in the year working days, as his schedule runs across all 7 days of the week. Thanks again John "Rod Gill" wrote: |
How do you make the entire week workdays? Posted: 11 Feb 2005 11:43 AM PST There are several reply already telling you how to do this, but I should add - Are you sure you really want to? Since the calendar controls the scheduling of tasks and tasks usually are proken down to the level of the work done by one person or a team of individuals, showing all 7 days as workingg days implies that once a task starts, people will work on it every day, no days off at all, until it' done. Before setting up your calendar as 7 days you should make sure that really describes what's going to happen with your tasks. If there's a task that takes 2 weeks to do, will it be worked on every day for 2 weeks without the people working on it taking any days off? -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Lucy2000" <microsoft.com> wrote in message news:com... |
Posted: 11 Feb 2005 10:59 AM PST Dave N -- Depending on what changes you make to the RBS, you will probably need to manually edit the RBS field for some resources, and perhaps for all. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "Dave N." <microsoft.com> wrote in message news:com... |
MS Project - Overallocated Resources - Different Cost Posted: 11 Feb 2005 09:22 AM PST There's no provision to automatically do what you ask. A couple of things for explanation and a possible solution. "Overallocation" doesn't quite mean what you're using it to be in that "allocation" not a direct indication of number man-hours scheduled and an overallocation is not necessarily a manpower shortfall. Allocations and overallocations refer to a rate variable, namely the rate at which duration time is converted into useful work output, not a scalar. Saying a resource is available 300% and at some point he is allocated 400% doesn't really tell you anything that a cost could be derived from because there's no indication of how much time the overallocation exists for. It means that an existing resource is being required to produce more work during some undefined time period than it is physically capable of. One way to resolve it is to hire an external resource, true. But another (and more common) way of resolving is to extend the duration of the task, in the case of reducing a 400% allocation to a 300% and depending on the nature of the work itself one might extend the duration by 33%, a 40 hour task becoming a 53 hour task for example thus eliminating the need to hire more help. Or one might shift part of the work. The classic case would be where Joe is booked for two full day tasks on Monday, each required to produce 8 man-hours of work, when he only works an 8 hour shift. One of those tasks must be shifted to Tuesday because Joe can't be in two places at once on Monday. For a plan to be valid, all overallocations other than trivial ones absolutely have to be resolved before the schedule is finalized, otherwise you're virtually guaranteeing tasks will run late. Hence, by the time you get to the point you're looking at costs, overallocations should no longer exist in the plan and so there's no provision to assign them a unique cost rate, in addition to the fact that a resource having a peak greater than his allowed maximum still doesn't tell you how many hours that level is required. What I would do in your case is create a new resource in the resource list, named "Temp Fid Maker" or some such, and give them a rate of $100. On the task in question, you would have two resources assigned - "Existing Resource Team, 300%" and "Temp Fid Maker, 100%." -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Pete Ploszay" <microsoft.com> wrote in message news:06e401c5105e$40385110$gbl... |
Recurring tasks with oddset schedules... HELP Posted: 11 Feb 2005 08:51 AM PST Double click on the subtasks. On the general tab, make sure that the rollup to summary task box is checked. Next go to format menu, barstyles. Create a bar style (or use a pre-existing one) which has "Show for" set to "rolled up" Set the text for that bar to show in the middle of the bar. Click OK -- -Jack ... For project information and macro examples visit http://masamiki.com/project .. "Lucy2000" <microsoft.com> wrote in message news:com... on up Write |
Posted: 11 Feb 2005 08:14 AM PST Hello Dale, Thanks for the information ! Newbie "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> a écrit dans le message de news:phx.gbl... you added |
Can Project send emails using Novell Groupwise? Posted: 11 Feb 2005 07:37 AM PST Rick, If you're talking about Project Server, it will use any SMTP gateway (including Groupwise - we use it right now) that you point it to, as long as that gateway is setup to accept and forward mail from outside sources. This is commonly known as a mail relay and mail administrators typically lock down mail relay so they don't become victims to spammers that hijack their gateway. However, if you talk to your mail admins and tell them what you need to accomplish the can "white list" your project server so mail relay will be allowed. Earl I am researching my MSc Dissertation and need to know if MS Project 2003 can send reminder emails to designated respondants via Novell Groupwise 6 instead of MS Outlook. |
Compatibility problem with MS Project 2003 Posted: 11 Feb 2005 07:35 AM PST Hi Paola, Try posting on the developer newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/. Mike Glen Project MVP Paola (ORCL) wrote: |
MSProject - how to place user defined "Custom File Properties" on. Posted: 10 Feb 2005 01:25 PM PST Hi G, You are right, this cannot be done as uch. The workaround is either not to use customproperties, but instead the textn fields of the project summary tasks (which are accessible by page setup) or to copy (possibly by VBA) the value of the custom property into a projectsummarytask.textn field or also to copy them directly into the setup header or footer. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "GWoody" <microsoft.com> schreef in bericht news:com... Can the |
stacking pictures in microsoft word Posted: 10 Feb 2005 01:07 PM PST recommend the microsoft.public.word.newusers group - however, displaying the drawing toolbar in word (view / toolbars / drawing) and playing with the option under the "DRAW" icon would probably give you what you were after. Note, however, first double click on the pictures and choose the layout tab and then "tight" as this is the easiest option when manipulating pictures in word. Cheers JulieD "Mike Glen" <glenATmvps.org> wrote in message news:phx.gbl... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |