Custom field formulas and inserted projects Microsoft Project |
- Custom field formulas and inserted projects
- Project Professional licensing quetion
- custom field inforamtion to be limited to task row only
- Who does what when
- Elapsed Time tasks show as non-critical in a critical path display
- Auto Save as Web Page?
- Combining Linked Projects
- 1 Task, x Resources
- levelling & the status line
- Scheduling from fixed finish dates?
Custom field formulas and inserted projects Posted: 24 Feb 2005 09:59 AM PST Ah, so simple and obvious! :-) I hadn't set it to use the formula for summary tasks. Thanks! I'll also amend to use the "&". I appreciate the help! ...L "JackD" wrote: |
Project Professional licensing quetion Posted: 24 Feb 2005 09:33 AM PST That is the answer to a different question. Project Server does NOT come with a free copy of Project Pro. -- -Jack ... For project information and macro examples visit http://masamiki.com/project .. "Steve House [MVP]" <send.hotmail.com> wrote in message news:%phx.gbl... one it need part |
custom field inforamtion to be limited to task row only Posted: 24 Feb 2005 06:31 AM PST In article <com>, "Majid" <microsoft.com> wrote: Majid, I find it easier to help someone if they explain what they are trying to do rather than how they are trying to do it. So, instead of telling us you want to highlight Flag1, how about explaining what Flag1 represents. In other words, what determines if Flag1 is "yes" or "no"? Is there some kind of criteria (formula or VBA code)? Is it changed manually by the user? Whatever. When you say you want Flag1 highlighted, what do you mean? There are several text formatting options - color, italic, bold, etc. What is special about summary lines? What determines why and when they will be highlighted? More questions than answers I'm afraid. John Project MVP |
Posted: 24 Feb 2005 05:03 AM PST In article <com>, "jzis" <microsoft.com> wrote: jz, Boy wouldn't that be great - Shilling versus Johnson. Let me answer the two questions I saw in your multiple posts. First, the data on the right side of Usage reports is for numerical information only. It is possible to achieve what you want, but you will have to use VBA to export the information to another application (e.g. Excel). Second, Gantt bar text cannot be wrapped. The intent of being able to attach text to a Gantt bar is to provide simple reference information on the graphic, not to give details such that text wrapping would be required. Hope this helps. John Project MVP |
Elapsed Time tasks show as non-critical in a critical path display Posted: 24 Feb 2005 02:29 AM PST You're welcome, General - good luck :-) Mike Glen MS Project MVP General M wrote: |
Posted: 23 Feb 2005 05:37 PM PST "=?Utf-8?B?bWN1YmE=?=" <microsoft.com> wrote in message news:<com>... Go to Tools, Macro, Record new Macro, and then with the macro recorder running, complete the File-SaveAs function, with the required options. In the future, to re-run the macro, use Tools, Macro, Macros (Alt F8) to run the saved macro. You can also assign shortcut keys / toolbar items if this is something you do frequently. Here is what I got, but you may have different preferences: Sub Macro2() ' Macro Macro2 ' Macro Recorded Thu 24/02/05 by Michael Murray. FileSaveAs Name:="C:\My Documents\testproject.html", FormatID:="MSProject.HTML", map:="Default task information" End Sub Hope that helps, M. |
Posted: 23 Feb 2005 02:15 PM PST In article <com>, "Roland67" <microsoft.com> wrote: Roland, Did I misinterpret what is happening? I understood you to say that when your subprojects were inserted into a master, some of the tasks slammed over to the Project Start date of the master, however (and I had to confirm this with my own test), this will only occur if the subprojects are statically consolidated into the master (i.e. subprojects not linked to the master). In a dynamically consolidated master, the tasks in each subproject adhere to the Project Start date of their respective subprojects. Perhaps we need a re-statement of what is happening before we can offer other suggestions. By the way, I understand about customer wants. I just hope they are not looking for detail planning of any tasks beyond 12 months. Tasks beyond the rule-of-thumb 12 month window should be expressed as "planning packages". That is, they have a rough idea of Duration and perhaps even cost, but no details. As time marches on and those out-year planning packages get within 3 months of the present, then they should be detail planned. Just for reference, I am a firm believer that the constraint types "must-start-on" and "must-finish-on" should never be used. When you get down to it, they defy reality. It is said there are only two certainties in life. One of them has to do with "rendering unto Caesar" and the other has to do with the grim reaper. The "best laid plans" do not fit into either category. Oops, there I am on that soapbox again. Sorry. John Project MVP |
Posted: 23 Feb 2005 01:21 PM PST Jan De Messemaeker wrote: Hi thanks for your patience. OK, here is what I mean. I have 10 stones I have to bring from A to B. I can only carry one at a time. For each stone I take one hour So if I do it alone it is 10 hours of work for me. So is the "duration" I meant. Now my neighbor is popping by, as weak/strong as I am and offers me help. So we do it parallel. So we carry the stone in 5 hours. 2 people carry 5 stones. So the "elapsed time" is 5 hours although the actual working hours (man days usually called) are 10 hours as planned. So if I know how much effort a task is (in my case 10 hours) I want to see how much faster I am throwing in more ressources (people). Yeah Yeah, I know that in software dev it does not work this way, but I am not talking about software dev. So with four ressources I can finish the task in 2.5 hours I hope this is clearer now, because I doubt my MSP would add value to your understanding Kay |
Posted: 23 Feb 2005 11:24 AM PST Dale, Thanks so much – this feature does exactly what I wanted. Syd. nntp://news.microsoft.com/microsoft.public.project/<#phx.gbl> Syd -- Open the project in question and then do the following: 1. Click Tools - Tracking - Update Project 2. Select the task(s) for which no actuals were entered in the past reporting period 3. Click Tools - Tracking - Update Project 4. Select the "Reschedule remaining work to start after" option 5. Select the date one day BEFORE the next reporting period 6. Select the "Selected tasks" option 7. Click the OK button This will move uncompleted work to the next reporting period for the selected tasks only. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "Syd Millett" <send.infusiondev.com> wrote in message news:phx.gbl... [microsoft.public.project] |
Scheduling from fixed finish dates? Posted: 23 Feb 2005 09:32 AM PST Yup. Stick to FS dependencies. -- -Jack ... For project information and macro examples visit http://masamiki.com/project .. "Tom G." <net> wrote in message news:46.248.16... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |