Automatic calculating Microsoft Project |
- Automatic calculating
- How can I merge two files in Project?
- How do I track changes between interim project plans?
- Bad critical path
- Question on resource leveling
- How do i convert MS Project documents to a pdf format
- DateDiff function is not working for me
- Why does a resource name display as Joe[104%]
- Summary task bar and indent
- Printing across then down, rather than down then across
- Booking a room or equipment
Posted: 07 Dec 2004 02:13 AM PST Hi Steve The column [Duration2] contains calculated fields [Work]-[Duration1] Work = Actual work + Remaining work Duration 1 = project budget (days) We use a gantt chart view to change values in a Remaining work column and it used to automatically refresh the values in Duration 2. It's only since we upgraded to 2003 that this seems to have stopped? Hope I've explained this properly? Niki "Steve House [MVP]" wrote: |
How can I merge two files in Project? Posted: 06 Dec 2004 07:47 AM PST In article <com>, "Nikki" <microsoft.com> wrote: Mikki, I have to disagree with Joe's response. The correct answer is "yes". Depending on how the files are structured and the differences between the files, one or more methods can be used to "merge" the data. one method is to run a comparison between the two files to determine the differences using the Compare Project Versions which is utility in Project 2003 and an add-in for Project 2000. Once the differences are known, the file that has the greater difference from the baseline (i.e. before your updates or your manager's updates) can be updated manually or updates can be automated with a VBA macro. However a much better solution is to put the file on a shared server. That way changes can only be made by one person at a time and no conflicts occur. Hope this helps. John |
How do I track changes between interim project plans? Posted: 06 Dec 2004 07:27 AM PST In article <com>, Rob <microsoft.com> wrote: Rob, In addition to what Steve and Jan suggested, you can also run a comparison between plans using the Compare Project Versions utility on Project 2003 or as an add-in for Project 2000. John |
Posted: 04 Dec 2004 01:03 PM PST There is something strange going on here. But of even more concern is you have a notion of what the critical path "should" be. How did you arrive at the conclusion that certain tasks were critical so that you consider it an error if Project doesn't reflect the same? There is a very exact mathematical definition that determines whether a task is critical or not .... I wonder if you are using some other criterion? -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Solution" <microsoft.com> wrote in message news:com... |
Posted: 03 Dec 2004 01:28 PM PST A couple of points: When you have a task with an estimated duration of 10 days and you assign a resource to it at 50%, Project assumes you had that 50% assignment in mind when you came up with the 10-day number to begin with and so it doesn't change it. If you assign at 100% Project says this requires 10 days @ 100% or 80 man-hours. OTOH, if you assign at 50% Project says this task is worth 10 days at 50% or 40 man-hours. To get the duration to change and reflect the 20 days you'd hoped for, you need to do it in two steps, assigning him at 100% and then EDITING the assignment to reduce him to 50%. Otherwise set it to 20 days right from the get-go, based on the knowledge that that is how long it will take for a part-time resource to complete it. Second, resource leveling doesn't do what you seem to think it does. Leveling only has meaning when resources are OVERALLOCATED, that is, you have the *same* guy is assigned to both of those tasks at 100% and so he is expected to be in two places at once, working on two mutually exclusive tasks at the same time. In that case, leveling would delay one of the tasks so as to resolve the conflict. But that's all it does - shift the time frame of the work back and forth. It never adjusts the percentage of allocation nor does it change the duration the resource will work on the task. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Tom" <com> wrote in message news:phx.gbl... |
How do i convert MS Project documents to a pdf format Posted: 03 Dec 2004 11:07 AM PST Hi Bob! You could use PDFCreator anyway. It's free HTH Stefan |
DateDiff function is not working for me Posted: 03 Dec 2004 08:25 AM PST Hi Steve, Try this formula in one of the spare Number fields: IIf([Finish1]=ProjDateValue("NA"),0,DateDiff("d",[Finish],[Finish1])) Hope this helps. Let us know how you get along. Julie "Steve Scott" wrote: |
Why does a resource name display as Joe[104%] Posted: 03 Dec 2004 08:19 AM PST Hi Tom, The percentage is the resource assignment units. Joe is overallocated if his maximum units are 100% and his assignment units are 104%. You might find Project less confusing if you read through Mike Glen's series of articles on Project at http://tinyurl.com/2xbhc o http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 Hope this helps. Let us know how you get along. Julie "Tom" wrote: |
Posted: 03 Dec 2004 06:55 AM PST FYI - the duration of summary tasks is not necessarily the sum of the durations of the indented subtasks. It will be from when the earliest subtask begins until the latest subtask ends. If the subtasks star together, are not linked and run in parallel for example, the summary task duration will be simply the duration of the longest subtask, regardless of how many subtasks there are. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Pat W." <Pat microsoft.com> wrote in message news:com... |
Printing across then down, rather than down then across Posted: 03 Dec 2004 04:53 AM PST Cheers, Jack! At least I won't have to waste any more time on this. Regards Pete "JackD" wrote: |
Posted: 01 Dec 2004 01:23 PM PST Thanks, Julie. I do just want to restrict the scheduling based upon a set schedule, but it has to apply to every project (hundreds of projects), and I don't want to set a task calendar manually for each one. Currently we have the room in the resource pool and have blocked out the time on the resource calendar, but it means MSP expects us to enter time for the resource which isn't feasible. "JulieS" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |