Will not let me save formula in customized fields Microsoft Project |
- Will not let me save formula in customized fields
- Adding conditional format to fields in Project 2000??
- Running a macro on a set of collapsed tasks
- Semi-urgent help! - Event 'calculation' problem
- convert Gantt chart to PDF file
- % Completion question
- Automatic updating of external links
- can't indent/outdent or show/hide subtasks
- Work vs Duration
- project xml schema advice
Will not let me save formula in customized fields Posted: 24 Aug 2004 11:04 AM PDT Hi, Sorry to pop in but it occurred to me that it sounds as if you are trying to type a formula directly into a field in a view. Forgive me if that is not the case. If it is...formulas are entered in Tools, Customize, fields HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 <microsoft.com> schreef in bericht news:c81f01c48a13$9bfbd200$gbl... |
Adding conditional format to fields in Project 2000?? Posted: 24 Aug 2004 09:54 AM PDT Hi Ron, You were on the right track. Did you take a baseline and compare current schedule to baseline? HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Ron" <microsoft.com> schreef in bericht news:c65101c489fa$fc7f5890$gbl... |
Running a macro on a set of collapsed tasks Posted: 24 Aug 2004 09:33 AM PDT Thanks to both Jan and Mark! (Or should I say "hartelijk bedankt" to Jan??) My code does go through each task in activeproject.tasks (as well as checking for blank tasks so that they're skipped), so I'll have to see what else could possibly prevent the macro from "reading" the info in the collapsed tasks. One theory down, thousands to go! Thanks very much, Phyl "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message news:<#UF#phx.gbl>... |
Semi-urgent help! - Event 'calculation' problem Posted: 24 Aug 2004 06:35 AM PDT You're welcome, Brian - you got it! :-) Mike Glen MS Project MVP A Nony Mouse wrote: |
convert Gantt chart to PDF file Posted: 24 Aug 2004 04:57 AM PDT Hello, Try PDF 995. It is freeware. to save as a PDF unfortunately the other person |
Posted: 23 Aug 2004 07:16 PM PDT You'll need use a text field to hold your results with a function to convert your calculated percentage from numeric to text and append the "%" character to the result. FYI, if you have 100 sites to convert and have done 37, you can use the "% Physical Complete" field to record progress at 37% if you don't mind figuring the percentage by hand. I would suggest you think a bit more about your plan's structure and your method of recording progress. In terms of monitoring whether you are on time and within budget the breakdown you've outlined and your method of recording progress won't help you actually manage the work very much. Saying that 17% of the sites in Subregion 1 and 42 % of the sites in Subregion 2 has been converted doesn't tell you WHEN Region 1 will finish, whether you're ahead of or behind schedule, or how much it will cost. Consider ... what if the circumstances of the installations are such that the conversion of each site in Group1 only takes 1 day but Group 2's sites are much more complex and take 10 days each? The 33% of the sites in Group 1 represent only 3 days of work while the 11% of Group 2's represents 30 days and it has cost you 10 times as much for the resources to do Group 2's 11% than it did to do Group 1's. Thus Subregion 1 is really NOT at 17% complete in terms of the total time and cost required to do all the work. Rather it actually is only 12% complete using my example numbers because you have worked a total of 33 days out of a required total of 279 days. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Chris" <co.nz> wrote in message news:55f101c48a23$c32225e0$gbl... |
Automatic updating of external links Posted: 23 Aug 2004 10:05 AM PDT Hi Michelle, Yes it definitely makes sense except that I still can't see how a milestone can be "tracking a % complete status"; the milestone will only show 100% complete when you set it to 100% complete explicitly, its % completion is by no means calculated from other tasks HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "meesh1224" <microsoft.com> schreef in bericht news:com... predecessor it the Depending date. is dependent (in show PMO The How |
can't indent/outdent or show/hide subtasks Posted: 23 Aug 2004 07:03 AM PDT Sort by ID again (being careful not to select Permenantly Renumber). "4lane" <microsoft.com> wrote in message news:com... 'reacitvate' indent/outdent |
Posted: 23 Aug 2004 06:23 AM PDT Yes and no I agree that working with duration and deadlines makes sense. I do not endorse the concept of % complete unless there are discrete countable events - in another post, I indicated that if you were digging a 100 foot trench and had dug 50 feet I would gladly give you 50% complete. However most "white collar" work does not have discrete countable events (like "Design" work) so percent complete is way too subjective... I'd encourage "Done/non done" reporting and report out slippage against major milestones... HTH Mark -- __________________________________________________ _______ Mark Durrenberger, PMP Principal, Oak Associates, Inc, www.oakinc.com "Advancing the Theory and Practice of Project Management" __________________________________________________ ______ The nicest thing about NOT planning is that failure comes as a complete surprise and is not preceded by a period of worry and depression. - Sir John Harvey-Jones "Mani" <microsoft.com> wrote in message news:com... measure would track are necessary... asking for my 20 my |
Posted: 23 Aug 2004 02:59 AM PDT "Rod Gill" wrote: Thanks very much. Will do. Jason |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |