Gantt Chart Display Microsoft Project

Gantt Chart Display Microsoft Project


Gantt Chart Display

Posted: 15 Mar 2006 07:30 AM PST

Thank You

"Jan De Messemaeker" wrote:
 

Varying Fixed Costs over Multiple Years

Posted: 15 Mar 2006 07:30 AM PST

John,

As a matter of fact, I did create a Summary Task called Overhead for each
customer area, and created subtaks for each year I need fixed costs for under
those. I just wanted to know if there was a better, more prefeered meathod,
and based on your response, there is not.

I thank you for your response(s), and I will proceed along those lines.

Again, thanks.

Sid1962

"John" wrote:
 

Cobra (WelcomHome) import/export MS Project

Posted: 15 Mar 2006 06:56 AM PST

In article <googlegroups.com>,
"Cole" <com> wrote:
 

Cole,
Sure. To see the various import formats supported go to File/Open and
look at "Files of type" selection box at the bottom of the Open window.
You can also read more about importing in the Project Help file. Then if
you have a specific question, post again.

John
Project MVP

Resource/Task View

Posted: 15 Mar 2006 06:53 AM PST

Hi,

As I said in my first post, it is in my signature - just below here.

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Pooja" <microsoft.com> schreef in bericht
news:com... 
have 
view. 
all 4 
in 
work. 


Resource Usage Reporting

Posted: 15 Mar 2006 06:06 AM PST

John,

Thanks a million. First of all, the FAQ# 51 explanation make it very clear
now as to know how views are working. I do not use MSP 2003 but will in about
1 week. Until then, I have tried the macro to transcribe Text29 field from a
Task to Resource table. Thank You again. This has made my day and a lot of
other people as well!

Regards,

Big_Bad

"John" wrote:
 

Multiple text to the right of Gannt Bars

Posted: 15 Mar 2006 01:32 AM PST


Concatenate means sticking the two text strings together with a "&" in the
formula in the text field like:

= first text string&" "&second text string

You need the " " to insert the space between.

No, you cannot have them in different colours.

"Helge Svee" <microsoft.com> wrote in message
news:com... 


How do I create two 'independent' resource pools for one project?

Posted: 14 Mar 2006 11:53 PM PST

Hi,

The cell Resource Names has that capability built-in
Much more function is available from the Assign Resources window activated
by the button on the toolbar.
HTH

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Jakob Espersen" <microsoft.com> schreef in
bericht news:com... 
manually? 
file 
its 
and 
is 


How to compare project versions when source project is not same

Posted: 14 Mar 2006 12:09 PM PST

I wrote a similar macro years ago, in which the user specified the "common"
field. I could probably dig it up if anyone needs it.
Rick Williams
non-MVP

"John" <com> wrote in message
news:microsoft.com... 


Adjusting Resource Allocations as availability Changes

Posted: 14 Mar 2006 11:48 AM PST

Hi Ronn,

Click the Assign resources button on the toolbar
Select all tasks
Select the resource
Click replace
Again select the resource, specifying 50%.
HTH

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"RonnBlack" <microsoft.com> schreef in bericht
news:com... 
at 


Is there a way to put the priority column in a usage view?

Posted: 14 Mar 2006 11:18 AM PST

Hi Michelle,

Install and run the following Macro:

Sub CopyPriority()
dim Job a task
dim Whodunit as assignment

for each job in activeproject.tasks
if not job is nothing then
job.number1=job.priority
for each whodunit in job.assignments
whodunit.number1=job.priority
next whodunit
end if
next job
end sub

Of course, you have to rerun this when the priorities or the assignments
change.
HTH


--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Michelle Moulliet" <microsoft.com> schreef in
bericht news:com... 
was 
resource 
combined 
to 
task usage 


adding tasks in large plan

Posted: 14 Mar 2006 11:01 AM PST

To have this new task be part of a summary or section as you called it: you
can drag and drop it between other task in that section. You should be able
to cut and paste also between 2 task in that section.

"Mel Hayes" wrote:
 

Determining new finish date when ahead of schedule.

Posted: 14 Mar 2006 10:08 AM PST

Hello Jim,
Have a look at the calculations options :
Tools / Options / Calculation
- Move end of completed parts after after status date back to status date
- Move start of remainning parts before status date forward to status date
NB : set these settings *before* entering traking data.
Hope this helps,

Gérard Ducouret

"Jim Stoaks" <microsoft.com> a écrit dans le message
de news:com... 
the 


Why won't dates import from Excel to the "Finish" field?

Posted: 14 Mar 2006 08:47 AM PST

Hi,

Also import a column called Constraint Type and put it to Must Finish On
Then import the date in the column Constraint Date.
HTH

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"JLP" <microsoft.com> schreef in bericht
news:com... 
receive 
expected 
plan 
expected 
Than, 
the 
finish 
to 
complete 
project? 


PWA Security

Posted: 14 Mar 2006 07:15 AM PST

Thanks and great answers. I thought I had published under server....not sure
what happened:).


"Dale Howard [MVP]" wrote:
 

How to spread short task to be completed over a longer period

Posted: 13 Mar 2006 12:19 PM PST

In article <com>,
Jessaqua <microsoft.com> wrote:
 

Jessaqua,
You're welcome. I think Jan addressed your new question. If not, post
again.

John
Project MVP