Keeping End Date Always in View Microsoft Project |
- Keeping End Date Always in View
- group by dropdown in Project Professional 2003
- Actual start based on Status Date update of duration vs start date
- moving task bars
- New task in existing plan to start LATER
- Project 2003 Professional vs Standard?
- Remove a combination view
- i need a project planner for my pocket pc
- Indenting tasks/Duration issue
- work entered in seconds
- Difficulty downloading Project Trial
- Problems with assigning calendars
- i have problems with outdenting tasks and summary bars
- General
- Project Summary Form in Project2000
- could not log on to PWA other than Administrator in project12
- How do I print a schedule on one page in Project?
- Tracking different cost categories
Keeping End Date Always in View Posted: 23 Feb 2006 07:01 AM PST In article <com>, "Dann" <microsoft.com> wrote: Dann, Great and you're welcome. John |
group by dropdown in Project Professional 2003 Posted: 23 Feb 2006 06:31 AM PST Hi Steve, AFAIK groups are saved in the project itself so once defined it will stay available in teh project after dsaving and reopening. -- Jan De Messemaeker, Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ For FAQs: http://www.mvps.org/project/faqs.htm "steve" <microsoft.com> schreef in bericht news:com... group. |
Actual start based on Status Date update of duration vs start date Posted: 23 Feb 2006 06:29 AM PST It sounds like you have a constrant on your start date or logic is holding the date out. Add a column for Actual Start or add the ICON for Update Task. You'll need to tell the task when it started and possible revise your logic. "Bryan" wrote: |
Posted: 23 Feb 2006 01:23 AM PST Hi, May I first quote you? By my logic the alap tasks should only finish at the start of the following tasks that were set as asap Wel, by my logic as well, and I've been asking for that development over the past 5 years or so, but to no avail. An ASAP task becomes critical and is "stronger" than any asap following, causing those to become critical as well. -- Jan De Messemaeker, Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ For FAQs: http://www.mvps.org/project/faqs.htm "Nils214" <microsoft.com> schreef in bericht news:com... asap the were case...illogical logic the did Now task, date. I the project rescheduled |
New task in existing plan to start LATER Posted: 22 Feb 2006 09:27 PM PST Thanks. That's what I do now. I was hoping for something else! This task really isn't a successor to any particular one. When I do this, if the linked task lags, it pushes this new task out in the schedule, and I don't really want that to happen. In a big project, I might miss that I did that to the task and it then doesn't get started when it needs to. The other method I've used is to put a date constraint on it, but that has it's negatives too. Oh well. Thanks again! "Rod Gill" wrote: |
Project 2003 Professional vs Standard? Posted: 22 Feb 2006 07:47 PM PST Hi, Was this a mistype or a misread? Project Professional is significantly more expensive than Standard! -- Jan De Messemaeker, Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ For FAQs: http://www.mvps.org/project/faqs.htm "Robert" <microsoft.com> schreef in bericht news:com... |
Posted: 22 Feb 2006 07:24 PM PST Many thanks, Dale. I actually did find it eventually at about 10 pm - and proves that I'm an entirely unproductive person after 9pm at night. But it is good to have this as a vehicle to answer questions and I appreciate your response. Kind Regards "Dale Howard [MVP]" wrote: |
i need a project planner for my pocket pc Posted: 22 Feb 2006 01:41 PM PST Hi Harry, Look at Project Plan from Twiddlebit, go to www.twiddlebit.com. As Rod mentioned though there are limitations around what is visible and that is obviously a function of the PDA size. Hope this helps Regards DavidC "harry graves" wrote: |
Indenting tasks/Duration issue Posted: 22 Feb 2006 11:18 AM PST Hi Felix, thanks for the reponse. The time period between the tasks is only 1 day. I've pasted the contents below. The last two are indented into the first one. Kinda funny, if I paste them into a new project the times show up correctly. Project is very frusturating... Task Name Duration Start Work Finish Move Servers 14 days Thu 3/16/06 0 hrs Fri 3/17/06 Install DHCP 2 hrs Thu 3/16/06 0 hrs Thu 3/16/06 Move servers 2 days Fri 3/17/06 0 hrs Fri 3/17/06 "Felix" wrote: |
Posted: 22 Feb 2006 11:08 AM PST I have to ask - Why would you want to schedule in seconds? "Nelson" wrote: |
Difficulty downloading Project Trial Posted: 22 Feb 2006 10:15 AM PST Thanks for the tip. "DavidC" wrote: |
Problems with assigning calendars Posted: 22 Feb 2006 09:35 AM PST Thanks for the responses, I have found the problem, tasks that are not assigned as of 'fixed duration' will not resize themselves according to the calendar. "Nils214" wrote: |
i have problems with outdenting tasks and summary bars Posted: 22 Feb 2006 09:35 AM PST In article <com>, "Nils214" <microsoft.com> wrote: Nils214, See responses below. Yes. When setting up a hierarchy in Project care must be used. Sometimes the user may have to go an extra step to correct an erroneous indent or outdent. There have been several comments over the years about the single undo of Project. I don't recall for sure, but the level of undos "might" be expanded in Project 12. Nonetheless, what it means for existing versions is that the user must be careful and perform regular saves and/or backups - but then that's just smart computing with any application or OS. Powerpoint is a very slick application but it isn't worth a darn when it comes to planning and scheduling. John Project MVP |
Posted: 22 Feb 2006 08:42 AM PST Thank you Jan "Jan De Messemaeker" wrote: |
Project Summary Form in Project2000 Posted: 22 Feb 2006 06:29 AM PST In article <com>, "Peter Allanach" <microsoft.com> wrote: Peter, The things you describe look like they are out of Project Server, which you mentioned in your original post. Project 2000 does not have that functionality built-in although customized data could be created with a VBA macro or SQL queries. It all depends on how much effort you want to invest versus upgrading to Server. John Project MVP |
could not log on to PWA other than Administrator in project12 Posted: 21 Feb 2006 10:46 PM PST madhur: A couple of things: You're discussing a product version that is not available to many people. More importantly, you're discussing subject matter that may be under non-disclosure agreement with your company and could place both your job and your company's relationship with Microsoft in jeopardy. With that said, I've seen the problem you describe, even with domain admins, and I can't offer you a resolution. Please redirect your inquiries to your points of contact at Microsoft or the partner organization you're working with. -- Gary L. Chefetz, MVP "We wrote the books on Project Server" http://www.msprojectexperts.com For Project Server FAQs visit http://www.projectserverexperts.com For Project FAQs visit http://www.mvps.org/project "madhur" <com> wrote in message news:googlegroups.com... |
How do I print a schedule on one page in Project? Posted: 21 Feb 2006 02:20 PM PST Look at Format>Timescale. You can adjust the type of scale yoy need here - Days, Weeks, Months..... "JB" wrote: |
Tracking different cost categories Posted: 21 Feb 2006 01:41 PM PST Thank you. I did discover the FAQ, will try it out. I suspected some part of the answer involved VBA and exportation of data. I don't know where to start with VBA, sigh. Most disappointing is the inability to do timescaled representation of a custom field. Since my tracking granularity for some of these other categories is monthly, maybe I could define a number of custom fields, one for each month, and export those out to Excel for summation. While somewhat artificial, it would allow me to at least maintain the data in a single tool (Project) and use Excel to present that data. Thanks again. I am grateful for your advice. |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |