bulk assignments Microsoft Project |
- bulk assignments
- Problem w/ duration cal. incorrectly when applying multiple resour
- Bloat
- Managing multiple, concurrent project
- Duration, work, and calendar changes
- Problem with duration dates miscalculation
- enumerate projects sharing resources
- Holiday dates
- Automatic calculation w/ add duration to "planned start/finish" da
- MySQL or ODBC
- Task % of total work
- How to print a few tasks of a project
Posted: 07 Mar 2006 04:26 PM PST Thanks Rod, let's say I have a spreadsheet with several resources on them that are already in the enterpise resource pool. I'm trying to get all of these resources assigned to the same project all at once. Is there a quick way of doing this and still keep them in the enterprise pool rather than making them local resources? In short I'm trying to assign several resources to the same project, but not one at a time and not as local resources. Thanks again "Rod Gill" wrote: |
Problem w/ duration cal. incorrectly when applying multiple resour Posted: 07 Mar 2006 11:39 AM PST This is a case where I would use the split screen to assign the resources. Enter Task X, duration 15 days. Assign resource R1 at 100%. Total Work is calculated at 120 man-hours. Now with the task selected split the screen. In the bottom window you'll see R1 already assigned. With the task set to effort driven and the task type as Fixed Units, use the pulldowns under the existing resource to add R2, entering 75% in the units column, and R3 with units set to 50%. Click the "OK" button. You'll see the work gets distributed between all three resources in a 4:3:2 ratio with R1 getting 53.33 hours, R2 getting 40 hours, and R3 getting 26.67 hours while the duration goes to 6.67 days. Now the question remains, why don't you have R2 and R3 devote their full attention to their work and assign them 100%? Have 'em all give it their full efforts and just git 'er done ASAP. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "com" <microsoft.com> wrote in message news:com... |
Posted: 07 Mar 2006 11:36 AM PST In article <googlegroups.com>, "textron.com" <textron.com> wrote: Bruce, Wow I thought, what was it that I said in my last comment that was so offensive.... and then I read my response again. OK, you're not translating back and forth - that's good. Well, I tell you what, unless the .csv file has a lot of complex data (which I doubt), the code to implement my "fix" should be very simple. That means it is no cost to you, despite your large employer who hasn't been able to figure it out for you yet. I understand, its called "corporate bloat". It's part of their mentality division. I know, I worked for a large corporation too. If you want to contact me, send me a note and we'll go from there. John jensenj6atatcomcastdotdotnet remove obvious redundancies |
Managing multiple, concurrent project Posted: 07 Mar 2006 11:09 AM PST Hi, One more original situation (in case you prefer one file) could be to attach to each task a task calendarshowing work for A 8-12, for B 13-15 and for C 15-17. Then you can assign all resources @100% and durations will be planned correctly as soon as you give in work. Hope this helps, -- Jan De Messemaeker, Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ For FAQs: http://www.mvps.org/project/faqs.htm "KK" <microsoft.com> schreef in bericht news:com... projects, these We're work down times would all. only tackle change the priority for % Any hesitant any |
Duration, work, and calendar changes Posted: 07 Mar 2006 11:03 AM PST Thanks both for your comments -- got me going in the right direction. I mistakenly assumed that decreasing the work days for a specific resource in a resource calendar (and not changing the base calendar) would somehow manifest as a difference between effort and duration. "bam" <com> wrote in message news:phx.gbl... |
Problem with duration dates miscalculation Posted: 07 Mar 2006 05:20 AM PST Thanks for the reply . I checked the calendar for weekends, extended hours etc, 5 days week, no weekend working, 8 hours days, 40 hours weeks but nothing helped. I could email project to you if you could spare the time to take a look? Let me know your email (com is mine) " D" wrote: |
enumerate projects sharing resources Posted: 07 Mar 2006 03:43 AM PST Hi John, Problem. The way I handle this is to show the window I talked about, break ALL links with the Sendkeys method and re-connect the right ones. Hope this helps, -- Jan De Messemaeker, Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ For FAQs: http://www.mvps.org/project/faqs.htm "John the PM" <microsoft.com> schreef in bericht news:com... list so resource |
Posted: 07 Mar 2006 01:07 AM PST Hi Peter, Welcome to this Microsoft Project newsgroup :) FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm. Look for Housatonic in the Companion Products, who have an Outlook/MS Project Tool which, I think, does this. There's a free trial on offer: http://www.projectviewercentral.com/ Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Peterl wrote: |
Automatic calculation w/ add duration to "planned start/finish" da Posted: 06 Mar 2006 11:50 PM PST Sounds like what you're describing is the baseline start and finish dates. Before you begin to post actuals, save a baseline. Your original plan is preserved there. Then when you enter an actual start date, the planned duration is added to it to come up with a projected finish. When you record the task as finished, project either transforms that projected finish into an actual or, if the actual duration differs from the planned, it records the new finish date as you've inout it. But the baseline you saved records all of the original start, duration, and finish info for comparison purposes. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "jrunner" <microsoft.com> wrote in message news:com... |
Posted: 06 Mar 2006 11:19 AM PST Seems to work except for when it wants to use the type "longchar" for at least one of the fields. MySQL does not support this field type. Is there a work around? |
Posted: 06 Mar 2006 06:06 AM PST In article <googlegroups.com>, "Eanna" <ie> wrote: Eanna, You're welcome. The "60" converts minutes to hours. Project stores all time based data in minutes so unless the user is working in minutes, formulas using time based data (e.g. Work) must be converted. I think most users enter work in hours so I made that assumption. If your value from step 3 is in weeks, then the factor should probably be "2400" (i.e. 60 x 40, assuming 40 hours per week). John Project MVP |
How to print a few tasks of a project Posted: 05 Mar 2006 11:17 PM PST Feel free to wonder, but there isn't. Tables decide which columns show and filters determine which "rows" show. "Sultan A. Ameen" <microsoft.com> wrote in message news:com... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |