How do I spread a 5 day duration over a 30 day time span Microsoft Project |
- How do I spread a 5 day duration over a 30 day time span
- Function definitions in customized fields
- Roll Back Completed Tasks to show complete before project starts -
- Copying a filtered view from Project 2003
- Eval expired
- need to copy import export maps from old pc to new pc
- Formatting task text
- Multiple views of a single project plan
- Multi-line resource name or text fields?
- Redistribution of effort on adding new resource
- Off Topic: Capturing Requirements
- Licensing Info
- Changing the number of days in a week
- BCWP Incorrect Summary Tasks
How do I spread a 5 day duration over a 30 day time span Posted: 05 Oct 2005 09:08 AM PDT In article <com>, "Kimi" <microsoft.com> wrote: Kimi, OK, don't get confused about Duration time and Work time - they are two separate entities in Project. Duration is the time span (normally measured in working days between the task Start and Finish) and Work, (normally expressed in hours), is the amount of effort one or more resources will need to complete the task. If a resource is assigned to work on the task 100%, then Work hours WILL equal Duration hours. You may or may not want a fixed duration type task, it depends on whether the task is effort driven or not. Let's assume you do want a fixed duration task, that can be set in one of two ways. If you want all your tasks to be fixed duration (the default is fixed units, i.e. fixed resource assignment allocation) go to Tools/Options/Schedule tab and change the "Default task type". If you only want a particular task to be fixed duration, select the task and hit the Task Information icon or menu item. On the Advanced tab change the "Task Type" and uncheck the "effort driven" box next to it. Once the above is done, enter the 30 days (I'll assume you want working days instead of calendar days) into the Duration field. Assign your resource or resources. Then in the Work field, (you will probably need to add that to whatever view you are using), enter 40 hours. You should see the resource allocation change to 17% in the Resources Name field. Now you have a task of 30 days duration with an assigned resource who will spend 40 hours sometime during that 30 day period working on the task. Hope this helps. John Project MVP |
Function definitions in customized fields Posted: 05 Oct 2005 07:57 AM PDT In article <com>, "Andrew K" <microsoft.com> wrote: Andrew, You're welcome. The most likely cause, (if the word "ERROR" didn't appear in the field column), is that Project is not set for automatic calculation. Either hit "F9" (manual calculate) or go to Tools/Options/Calculation tab and set calculation to automatic. Hope this helps. John Project MVP |
Roll Back Completed Tasks to show complete before project starts - Posted: 05 Oct 2005 06:55 AM PDT Hallo, Yes, definitely. Have you tried working with an earlier project start date? -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Michael Balda" <microsoft.com> schreef in bericht news:com... (Project, won't through bericht completed date is day complete issue shows 10-16-05 -- need |
Copying a filtered view from Project 2003 Posted: 05 Oct 2005 02:49 AM PDT Hi Jude, You're welcome and thanks for the feedback. Julie "Jude" <microsoft.com> wrote in message news:com... |
Posted: 04 Oct 2005 01:40 PM PDT Thanks for the info. I will give 'em a call. "JackD" wrote: |
need to copy import export maps from old pc to new pc Posted: 04 Oct 2005 12:27 PM PDT Thanks so much, this worked great. "Jan De Messemaeker" wrote: |
Posted: 04 Oct 2005 11:16 AM PDT Dominic: Yes, this makes perfect sense. We will try using a new view with the formatting. Thanks so much. -- Barbara Lindsey Contractor McNeil Consumer & Specialty Pharmaceutical "Dominic Moss" wrote: |
Multiple views of a single project plan Posted: 04 Oct 2005 08:31 AM PDT In article <com>, dsm <microsoft.com> wrote: dsm, By "high level tasks" I assume you mean the Summary Lines. First filter out the Summary Lines by only showing lines where the Summary field is equal to "no" (also remember to uncheck the box at the bottom of the filter definition window for showing related Summary lines). Then sort by Start Date. Hope this helps. John Project MVP |
Multi-line resource name or text fields? Posted: 04 Oct 2005 07:12 AM PDT In article <googlegroups.com>, com wrote: Dave, Your're welcome but it sounds like you found your own solution anyway. I assume you had them set the list separator under their regional and language settings from "," to " ", otherwise the word wrap idea won't work. John |
Redistribution of effort on adding new resource Posted: 04 Oct 2005 02:44 AM PDT Amit wrote: To come up with a formula, I'd have to do a series of these types of events, then figure out how project is doing the calculation. But when I first looked at the numbers, without having Project available, it looked reasonable because when you added the third resource, the work of the other 2 decreased in "reasonable proportion", as did the duration (roughly a third). Which is what I expect with an effort driven task. How project handles these things doesn't always make sense to many of us. But once you understand what it does, it's usually fairly predictable, given you know the "rules" by which it operates. Hope this helps in your world. |
Off Topic: Capturing Requirements Posted: 04 Oct 2005 01:28 AM PDT You're welcome, Hardip - good luck in your search :-) Mike Glen MS Project MVP wrote: |
Posted: 03 Oct 2005 11:35 PM PDT You need an SQL licence for every user/device (depending on licencing mode) that derives information from the SQL Server. In your case it is dependent on the hardware configuration of the SQL server what would be the best value to either aquire between 70 and 120 more SQL CALS "or" switch over to a per processor licence. This is a concept called multiplexing and it has been discussed here and resides in the google groups archives now. http://groups.google.ca/group/microsoft.public.project.server/browse_frm/thread/6b0345a602ddd789/2e792e5a4f02f654?q=multiplexing+&rnum=1&hl=en#2e79 2e5a4f02f654 Two Things 1.) Most Microsoft people have not known much about PS licencing. 2.) Watch out for buying SQL 2000 and then needing to go to 2005 when your business application or Project Server suggests it. You don't want to have to buy twice in a short period of time so you may want to consider a software assurance situation. "Mike Glen" <glenATmvps.org> wrote in message news:phx.gbl... |
Changing the number of days in a week Posted: 03 Oct 2005 09:51 AM PDT See my previous post "calendar durations (again)" where I had the same problem. |
Posted: 02 Oct 2005 07:49 PM PDT hi Brad, I applied manual calculations and the BCWP should be 19,868 as you have stated. However we still need to cosider the Duration and the timephased costs. Note that Project calculates BCWP at the task level differently than at the assignment level. See: http://www.ksu.edu/InfoTech/epm/training/msproject2002/19%20Earned%20Value.doc. Regards, -- Haris http://www.manage-systems.com ------------------------------------- "beldredge" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |