You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #2, at this site: http://tinyurl.com/2xbhc or
this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

fnnaw wrote: 



Viewing Overallocations

Posted: 26 Aug 2005 05:20 PM PDT

Hi Andrew,

I assume you are not using Project Server (which is what Dale assumes) so
here is the "native" approach.

The simplest solution is (from a task view) to go to Window, Split
Click on the lower pane
In the View Bar select Resource Sheet

Now you no longer have the need to switch windows, they are both there!
And when you allocate a resource, and it gets overallocated, it immediately
turns red in the lower pane.

You can have the indication in the task view itself but that would resuire
some VBA programming.

Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Andrew" <microsoft.com> schreef in bericht
news:com... 
has 

task, 

view. 
am 
seem 


Using Project in Small Office and on Multiple Projects/Tasks

Posted: 26 Aug 2005 02:29 PM PDT

Thanks for your response.

Do you have any suggestion of what to use in place?

The problem is that many of the task will be in a project for product
development, however, some of the required tasks are pretty small.


Chris


"davegb" wrote:
 

% Complete not Rolling Up to Summary Task

Posted: 26 Aug 2005 08:51 AM PDT

Calculate is set to "automatic". I initially only entered % complete in the
"% Physical Complete" column. Then I went back and entered % complete for
each task in the "Task Information - General" tab, in the % complete box. I
thought this would correct the problem but it did not.

Any ideas?

Thanks,
Anna

"Steve House [Project MVP]" wrote:
 

Column Width in Project 2002 To Do List Report

Posted: 26 Aug 2005 08:07 AM PDT

Hi Steve,

Glad to have helped and thanks very much for the feedback.

Julie

"Steve" <microsoft.com> wrote in message
news:com... 


Hours worked by resource by task

Posted: 26 Aug 2005 08:00 AM PDT

Bonjour Helen,

La réponse à votre question se trouve dans l'affichage Utilisation des
Tâches plutôt que Utilisation de ressources!
In English, you need the Task Usage view rather than the resource usage
view; It gives you resource on each tak and a total by task.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Helen" <microsoft.com> schreef in bericht
news:com... 
they 
the 


Float/Slack Time

Posted: 26 Aug 2005 06:03 AM PDT

..... not if he fixed the milestone

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Steve House [Project MVP]" <send.hotmail.com>
schreef in bericht news:phx.gbl... 
slack 
the 
linked 


date range missing

Posted: 25 Aug 2005 06:20 AM PDT

In article <com>,
"Majid" <microsoft.com> wrote:
 

Majid,
Something has apparently happened to Global file if you only have 3 of
the default filters. Here are a couple of things to try. First, go to
Help/Detect and Repair.

If that doesn't restore the filters, you can trash your active Global
and Project will create a new one, hopefully with all the default stuff.
Before trashing your existing Global however, you need to use the
Organizer to transfer any custom views, reports, modules, etc. to a
temporary file so they can be restored once the new default Global is
generated.

If neither of the above works then the only other option I know of is to
re-install Project.

Hope this helps.
John
Project MVP

Custom Task Usage Report

Posted: 23 Aug 2005 02:30 PM PDT

I just realized that I never said thank you for this advice....thank you!

The Task Usage view is working just fine. :)