Pages

Search

What are the available plug-ins for Project? Microsoft Project

What are the available plug-ins for Project? Microsoft Project


What are the available plug-ins for Project?

Posted: 14 Jul 2005 06:09 PM PDT

No, sorry.
Have you considered scheduling in powerpoint?
I end up doing that on occasion (today for example)
--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
"j_fo" <microsoft.com> wrote in message
news:com... 
menu 
timescale 
work 
limiting. 
will 
Something 
to 
the 
exactly 
bunch 
is 


resource start date problems

Posted: 14 Jul 2005 11:21 AM PDT

Hello Rob,

"RobR" <com> a écrit dans le message de
news:%phx.gbl... 

Did you create a finish to Start (FS) link from A to B ?
If yes, and B still doesn't move, check that B has not any Real Start nor %
Complete. Erase these 2 values.
 

Run a resource leveling : Tools / Level Resources... / Leveling can adjust
individual assignments on a task / Level now

Hope this helps,

--
Gérard Ducouret [Project MVP]


Line Feeds in Text Fields - How?

Posted: 14 Jul 2005 10:53 AM PDT

Larry,
You can do that for the Task Name : with the mouse, draw downward the lower
line of the row.
Gérard Ducouret

"Larry N" <microsoft.com> a écrit dans le message de
news:com... 
entered 
by 

how do 


Resource usage shows 200%, but actual hours only 10

Posted: 14 Jul 2005 09:51 AM PDT

My fault, had the wrong setting. It was on peak units and not percent
allocation.

"Evan" wrote:
 

Project: Split task duration

Posted: 14 Jul 2005 08:51 AM PDT


You're welcome, :-)

Mike Glen
MS Project MVP


training wrote: 



Can I assign resource in hrs to milestone in MSProject

Posted: 14 Jul 2005 08:24 AM PDT

In article <com>,
"Alka" <microsoft.com> wrote:


Alka,
Sure, why not? Normally however milestones should simply be an "zero
time" event that signals the completion of a group of performance tasks.
Even if the "milestone" is a meeting or major review (e.g. Critical
Design Review), the actual effort involved with that activity should
really be its own separate task and the real milestone is the "0"
duration completion of the tasks leading up to and the review itself.

Hope this helps.
John
Project MVP

Project 2003 Standard on Terminal Server

Posted: 14 Jul 2005 06:25 AM PDT

I was finally able to get it working. We were running Office 2000 on our
Citrix farm, and the default location for Project was within that folder. I
removed Project and reinstalled in it's own directory under program files,
and all worked well.

Thank you for your help, and i will check out the newsgroup that you
specifed for further instruction.

Brian

"Mike Glen" wrote:
 

Question about resources who don't work 100% of time on a project

Posted: 14 Jul 2005 03:25 AM PDT

There's no single answer to your question on which task type, fixed work or
fixed duration, is proper. The task type is not truly a property of the
task in most cases and in any case it only effects the project when you edit
something that changes one of the three variables of work, duration, or
units. The "prime directive" is W=D*U. When you edit a resource assignment
or task, you can instruct Project to hold any one of those variables
constant while you change a second so that Project will recalculate the
third. The task type is the variable you want to be held constant in *this*
instant edit. Next time you change something about this task, another task
type might be appropriate - it all depends on what you are changing, why you
are doing it, and what the end result should be. For example, I'm painting
a room and have the painter assigned. Working full time it will take him
one week so the work is 40 man-hours. I realize I have another task I need
him to work on at the same time so I'm going to free him up part of each day
by reducing his assignment to 50%. It still will take 40 hours of work to
paint the room, the room didn't suddenly get smaller, but now he's only
working an average of 4 hours a day on it, doing something else the other 4.
Task type Fixed Work, edit the units, and the duration goes to 10 days. Now
consider, same room and same guy. He's on it 100% for 1 week. I realize
it's really a smaller room than I thought it was so the work is only 20 man
hours. I still want him done ASAP so task type is fixed units, edit the
work, and the duration becomes 2.5 days. Same scenario, I realize the room
is smaller than originally thought but I still don't need it done before the
end of the week. Task type Fixed Duration, edit the Work, and Project
resets the units to 50% freeing him up half of each day if I need him.


--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"me" <microsoft.com> wrote in message
news:com... 

Filtering for 100% Predecessors

Posted: 14 Jul 2005 01:15 AM PDT

You're welcome!

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"TanyaE" <microsoft.com> schreef in bericht
news:com... 
predecessors 


Project forms

Posted: 13 Jul 2005 04:20 PM PDT

Yes, we do this sometimes with VBA. Users just click an icon, and a nice
form pops up that they can fill in. The form can also display logos, as well
as non-editable calculated values.

It really makes data input a lot friendlier than a flat table, and it also
aids in analysis.

--
Reid McTaggart
Alegient, Inc., Houston
Project Server Experts
Microsoft Certified Partner


"Glen" wrote:
 

Field formula

Posted: 13 Jul 2005 12:37 PM PDT

Thanks for your help. It helped me out. After a test run I made a slight
change for a typo in the first statement:

IIf([Date1]<[Date2] And [Date1]<[Date3] ... (instead of date 2 again)

and now it runs perfect

Thanks again
Dave


"Gérard Ducouret" wrote:
 

Top Level Task Report

Posted: 13 Jul 2005 11:55 AM PDT

Thank you Brian...it worked exactly as I needed.

"Brian K - Project MVP" wrote:
 

Constant crash

Posted: 13 Jul 2005 11:43 AM PDT


Hi George,

Welcome to this Microsoft Project newsgroup :-)

If you suspect a corrupt file, you could try the suggestions in FAQ Item:
43. File Bloat? - Might be Corruption.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/.

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP


Reid McTaggart wrote: 



Resource Usage View - Some tasks greyed out, some not

Posted: 13 Jul 2005 10:08 AM PDT

That is possible. I was looking from a resource perspective so I think if I
looked at all the greyed out tasks, they would be from the same sub schedule.

The problem resolved itself when I reopened the master schedule a few times
down the road, so I am guessing that is what happened.

Of course now I have other questions for another thread!

Thanks you for the reply.

"Jan De Messemaeker" wrote:
 

Linux Email Server with Project Server

Posted: 13 Jul 2005 08:40 AM PDT

As far as I'm aware, no automated emailing will work from Project Server as
it uses MAPI.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more


"Susan" <microsoft.com> wrote in message
news:com... 


to send automatic updates to outlook from project professional

Posted: 13 Jul 2005 08:01 AM PDT

Search this forum with "birchler outlook",
I have posted vba code here before that maintains Outlook calendar
appointments, with reminders (if you wish). Perhaps that may help?

"thushara" wrote:
 

Text in task bars

Posted: 12 Jul 2005 11:28 AM PDT

Thank you Dave. Is it possible to centre the text inside the bar? The
normal alignment icons don’t seem to be available.

"davegb" wrote:
 

Overtime internal mechanisms

Posted: 12 Jul 2005 03:44 AM PDT

Dear Gary,
Thank you for your detailed answer. I think I understood the internal
behavior.
You are right that I should have mentioned that the task type was
fixed-duration.

I played again with my example under this new light and would like to
summarize:
a) when you increase overtime, MS Project keeps the unit (and moves work
forward).
b) when you decrease overtime, MS Project distributes work flat over the
duration and reduces unit accordingly.

The second behaviour seems more natural.
Indeed I didn't want to change the contour and only wanted to increase the
cost of the project (with overtime rate).

Thanks,
Your MVB (Most Valuable Beginner)


"Gary L. Chefetz [MVP]" <gary AT chefetz DOT org> wrote in message
news:phx.gbl... 
that 
rates. 
rules 
these 
with 
assigning 
percentage 
days 
work 
2.5 
the 
like 
situation 

situation 
Project 
behaviour?