What are the available plug-ins for Project? Microsoft Project |
- What are the available plug-ins for Project?
- resource start date problems
- Line Feeds in Text Fields - How?
- Resource usage shows 200%, but actual hours only 10
- Project: Split task duration
- Can I assign resource in hrs to milestone in MSProject
- Project 2003 Standard on Terminal Server
- Question about resources who don't work 100% of time on a project
- Filtering for 100% Predecessors
- Project forms
- Field formula
- Top Level Task Report
- Constant crash
- Resource Usage View - Some tasks greyed out, some not
- Linux Email Server with Project Server
- to send automatic updates to outlook from project professional
- Text in task bars
- Overtime internal mechanisms
What are the available plug-ins for Project? Posted: 14 Jul 2005 06:09 PM PDT No, sorry. Have you considered scheduling in powerpoint? I end up doing that on occasion (today for example) -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. "j_fo" <microsoft.com> wrote in message news:com... menu timescale work limiting. will Something to the exactly bunch is |
Posted: 14 Jul 2005 11:21 AM PDT Hello Rob, "RobR" <com> a écrit dans le message de news:%phx.gbl... Did you create a finish to Start (FS) link from A to B ? If yes, and B still doesn't move, check that B has not any Real Start nor % Complete. Erase these 2 values. Run a resource leveling : Tools / Level Resources... / Leveling can adjust individual assignments on a task / Level now Hope this helps, -- Gérard Ducouret [Project MVP] |
Line Feeds in Text Fields - How? Posted: 14 Jul 2005 10:53 AM PDT Larry, You can do that for the Task Name : with the mouse, draw downward the lower line of the row. Gérard Ducouret "Larry N" <microsoft.com> a écrit dans le message de news:com... entered by a how do |
Resource usage shows 200%, but actual hours only 10 Posted: 14 Jul 2005 09:51 AM PDT My fault, had the wrong setting. It was on peak units and not percent allocation. "Evan" wrote: |
Posted: 14 Jul 2005 08:51 AM PDT You're welcome, :-) Mike Glen MS Project MVP training wrote: |
Can I assign resource in hrs to milestone in MSProject Posted: 14 Jul 2005 08:24 AM PDT In article <com>, "Alka" <microsoft.com> wrote: Alka, Sure, why not? Normally however milestones should simply be an "zero time" event that signals the completion of a group of performance tasks. Even if the "milestone" is a meeting or major review (e.g. Critical Design Review), the actual effort involved with that activity should really be its own separate task and the real milestone is the "0" duration completion of the tasks leading up to and the review itself. Hope this helps. John Project MVP |
Project 2003 Standard on Terminal Server Posted: 14 Jul 2005 06:25 AM PDT I was finally able to get it working. We were running Office 2000 on our Citrix farm, and the default location for Project was within that folder. I removed Project and reinstalled in it's own directory under program files, and all worked well. Thank you for your help, and i will check out the newsgroup that you specifed for further instruction. Brian "Mike Glen" wrote: |
Question about resources who don't work 100% of time on a project Posted: 14 Jul 2005 03:25 AM PDT There's no single answer to your question on which task type, fixed work or fixed duration, is proper. The task type is not truly a property of the task in most cases and in any case it only effects the project when you edit something that changes one of the three variables of work, duration, or units. The "prime directive" is W=D*U. When you edit a resource assignment or task, you can instruct Project to hold any one of those variables constant while you change a second so that Project will recalculate the third. The task type is the variable you want to be held constant in *this* instant edit. Next time you change something about this task, another task type might be appropriate - it all depends on what you are changing, why you are doing it, and what the end result should be. For example, I'm painting a room and have the painter assigned. Working full time it will take him one week so the work is 40 man-hours. I realize I have another task I need him to work on at the same time so I'm going to free him up part of each day by reducing his assignment to 50%. It still will take 40 hours of work to paint the room, the room didn't suddenly get smaller, but now he's only working an average of 4 hours a day on it, doing something else the other 4. Task type Fixed Work, edit the units, and the duration goes to 10 days. Now consider, same room and same guy. He's on it 100% for 1 week. I realize it's really a smaller room than I thought it was so the work is only 20 man hours. I still want him done ASAP so task type is fixed units, edit the work, and the duration becomes 2.5 days. Same scenario, I realize the room is smaller than originally thought but I still don't need it done before the end of the week. Task type Fixed Duration, edit the Work, and Project resets the units to 50% freeing him up half of each day if I need him. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "me" <microsoft.com> wrote in message news:com... |
Filtering for 100% Predecessors Posted: 14 Jul 2005 01:15 AM PDT You're welcome! -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "TanyaE" <microsoft.com> schreef in bericht news:com... predecessors |
Posted: 13 Jul 2005 04:20 PM PDT Yes, we do this sometimes with VBA. Users just click an icon, and a nice form pops up that they can fill in. The form can also display logos, as well as non-editable calculated values. It really makes data input a lot friendlier than a flat table, and it also aids in analysis. -- Reid McTaggart Alegient, Inc., Houston Project Server Experts Microsoft Certified Partner "Glen" wrote: |
Posted: 13 Jul 2005 12:37 PM PDT Thanks for your help. It helped me out. After a test run I made a slight change for a typo in the first statement: IIf([Date1]<[Date2] And [Date1]<[Date3] ... (instead of date 2 again) and now it runs perfect Thanks again Dave "Gérard Ducouret" wrote: |
Posted: 13 Jul 2005 11:55 AM PDT Thank you Brian...it worked exactly as I needed. "Brian K - Project MVP" wrote: |
Posted: 13 Jul 2005 11:43 AM PDT Hi George, Welcome to this Microsoft Project newsgroup :-) If you suspect a corrupt file, you could try the suggestions in FAQ Item: 43. File Bloat? - Might be Corruption. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/. Hope this helps - please let us know how you get on :-) Mike Glen Project MVP Reid McTaggart wrote: |
Resource Usage View - Some tasks greyed out, some not Posted: 13 Jul 2005 10:08 AM PDT That is possible. I was looking from a resource perspective so I think if I looked at all the greyed out tasks, they would be from the same sub schedule. The problem resolved itself when I reopened the master schedule a few times down the road, so I am guessing that is what happened. Of course now I have other questions for another thread! Thanks you for the reply. "Jan De Messemaeker" wrote: |
Linux Email Server with Project Server Posted: 13 Jul 2005 08:40 AM PDT As far as I'm aware, no automated emailing will work from Project Server as it uses MAPI. -- Rod Gill Project MVP Visit www.msproject-systems.com for Project Companion Tools and more "Susan" <microsoft.com> wrote in message news:com... |
to send automatic updates to outlook from project professional Posted: 13 Jul 2005 08:01 AM PDT Search this forum with "birchler outlook", I have posted vba code here before that maintains Outlook calendar appointments, with reminders (if you wish). Perhaps that may help? "thushara" wrote: |
Posted: 12 Jul 2005 11:28 AM PDT Thank you Dave. Is it possible to centre the text inside the bar? The normal alignment icons donât seem to be available. "davegb" wrote: |
Posted: 12 Jul 2005 03:44 AM PDT Dear Gary, Thank you for your detailed answer. I think I understood the internal behavior. You are right that I should have mentioned that the task type was fixed-duration. I played again with my example under this new light and would like to summarize: a) when you increase overtime, MS Project keeps the unit (and moves work forward). b) when you decrease overtime, MS Project distributes work flat over the duration and reduces unit accordingly. The second behaviour seems more natural. Indeed I didn't want to change the contour and only wanted to increase the cost of the project (with overtime rate). Thanks, Your MVB (Most Valuable Beginner) "Gary L. Chefetz [MVP]" <gary AT chefetz DOT org> wrote in message news:phx.gbl... that rates. rules these with assigning percentage days work 2.5 the like situation ? situation Project behaviour? |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |