How can I make the Finish date change based on the % complete Microsoft Project |
- How can I make the Finish date change based on the % complete
- Longhorn?
- Day starts 1hr late
- Is there a problem with backward compatibility in MS Project 2003
- Issue with MS project connecting to the SQL database
- How do I differentiate "Highlighted" and "Marked" tasks?
- Hammock Tasks in Templates
- Timescales
- how do i show long duration but few hours per day in project
- Baseline's
- Are there sample projects available for MSP2003?
- Copying resources
- Analyze Toolbar With Project 2002?
How can I make the Finish date change based on the % complete Posted: 01 Jul 2005 10:07 AM PDT When you entered the tasks, did you enter the start and finish dates or did you let Project calculate them for you? While we don't have enough information about your exact situation to know if this is the problem in your case, a very common cause of sucessor tasks not moving when their prdecessors get shorter is that they have "Start No Earlier Than" constraints on them. Those constraints will automatically be set if you manually enter task start dates instead of letting Project freely calculate them (as you should). FYI, % Complete always refers to duration so it's impossible for a task that is scheduled for 40 hours to be 80% complete after working only 16 hours. By definition, that would make it 40% complete. What your engineer is saying is that you overestimated the time required and that's why Dale's suggestion is the correct method to follow. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Dammika" <microsoft.com> wrote in message news:com... |
Posted: 01 Jul 2005 05:21 AM PDT Ready for what? -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. "socorro signorile" <com> wrote in message news:bc4a7$42c5355c$d99c5301$com... |
Posted: 30 Jun 2005 05:38 PM PDT Hi Ron, Welcome to this Microsoft Project newsgroup :) Project/Project Information.../Start Date - include the start time eg 01 August 2005 07:00. If you wish the times to show, Tools/Options/View tab - select a Date Format to include the time of day. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/ Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Ron DeGregorio wrote: |
Is there a problem with backward compatibility in MS Project 2003 Posted: 30 Jun 2005 04:21 PM PDT I understand that theoretically there is a full compatibility between them, but there seems to be some kind of bug. I have had the same problem. Project saved in MSP2000 was working OK both in 2000 and 2003, until at a certain point (after one more save in MSP2000) everyone using MSP2003 started missing the resources info from the file. I even receive a message when opening the file stating "The operation cannot be completed because the source file contains invalid project data or the total number of rows would exceed the limit of 1.048.000 rown is a project". No need to mention that the file works perfectly under MSP2000. Mark "Gérard Ducouret" wrote: |
Issue with MS project connecting to the SQL database Posted: 30 Jun 2005 03:27 PM PDT Steve -- In that case, try posting your problem in the microsoft.public.project.server newsgroup and let the SQL experts hammer on your problem. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com http://www.projectserverexperts.com "We wrote the book on Project Server" "Steve" <microsoft.com> wrote in message news:com... |
How do I differentiate "Highlighted" and "Marked" tasks? Posted: 30 Jun 2005 01:57 PM PDT Hi ycm, Welcome to this Microsoft Project newsgroup Tasks can be highlighted when you apply a filter - Project/Filtered for.../More Filters/select the filter you want and then the Highlight button. Insert/Column/select Marked. Then select the tasks you want marked by changing the No default to Yes. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/ Hope this helps - please let us know how you get on Mike Glen MS Project MVP ycm wrote: |
Posted: 30 Jun 2005 08:42 AM PDT Hi, you can integrate in the template a little macro that creates the OLE Links when the template is opened for the first time. Regards, Renke -- Allocatus - Linking MS Project with Outlook and Notes http://www.allocatus.com Das neue Buch zu MS Project und MS Project Server http://www.holert.com/project/profibuch "Tartaglia" <microsoft.com> wrote in message news:com... |
Posted: 30 Jun 2005 08:15 AM PDT That's what I thought. Thanks for getting back so quick. Piper5150 "JackD" wrote: |
how do i show long duration but few hours per day in project Posted: 30 Jun 2005 05:40 AM PDT Setting few hours per day for resources can be done in the "resource sheet" view under column units. You can decrease the % of units available for each resource. However I don't think setting the hours for resources to be less than the typical 8 hour day will address your primary problem on your title. Long duration can be managed from a different angle. If you want to set a task to take 20 days in duration but only have the resource work 2 hours per day for the 20 days than you simply need to assign the resource to the task and adjust the % percentage to 25%. "microwave man" wrote: |
Posted: 30 Jun 2005 03:40 AM PDT I think of them as being there to hold an audit trail in the event you have to change baselines due to scope changes. There is one and only one functional baseline, the record of the project plan that you intend to work saved as a record before posting actual performance. If someone comes in half-way through the project with a change that materials makes this a different project, we should update the baseline with the new tasks. Before saving the new basleine however, I want to archive a copy of the original for comparison purposes, if for no other reason than to CYA 'cause I know the boss is going to want an explanation of why we're slipping over budget. So I copy the original over to one of those vacant baseline slots and then save a corrected version into the "operational" baseline. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Paul_Willie78" <microsoft.com> wrote in message news:com... |
Are there sample projects available for MSP2003? Posted: 29 Jun 2005 03:05 PM PDT You're welcome, Carey :-) Mike Glen MS Project MVP CH wrote: |
Posted: 29 Jun 2005 09:46 AM PDT Terry, Ok, so... are you saying that you would define a placeholder called "Java Team 1" and drag it across several tasks (i.e. task 1 - task 10) and later you would need to replace "Java Team 1" in Task 1 and Task 5 with John Doe and Jane Doe but Task 2 and/or Task 4 would need James Doe and Jill Doe? Therefore you are trying to use a "very" generic placeholder that can then take the form of a mix group of resources and depending on which task you are working with you may replace the placeholder with 1 and/or several other resources? If this is indeed the case, I don't really know a way that you can quickly do a global change, however the best I can offer is to define multiple placeholders for all proposed team members (i.e.Java Developer 1, Java Developer 2, Java Developer 3, Java Developer 4, etc.) and drags these down. Once you get to another set of tasks where you need to use a different combination of resources for the Java Team, you may use Java Developer 10, Java Developer 11, etc. Then when you get ready to update the place holders with real people's names, you can simply go back to the resource sheet and update the place holders accordingly. Sorry, this is the best I can do for now. Hope this helps. "Terry S." wrote: |
Analyze Toolbar With Project 2002? Posted: 29 Jun 2005 08:55 AM PDT Turns out I didn't have the proper admin rights to view this (and other features) of Project. Seems kind of odd that the feature would be disabled to certain users, but perhaps my account was never set up properly to begin with.? Anyway, just wanted to share my answer with anyone else experiencing this problem. "Matt_NewProjectUser" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |