Tasks have uneccessary slack time & don't update. Microsoft Project |
- Tasks have uneccessary slack time & don't update.
- two questions
- Displays incorrect year in calendar view?
- auto predessecors
- Duration set to actual calendar days?
- Does Microsoft Project have a mobile component?
- MS Project 98 and 2003 installed give error when open file
- I can't seem to outdent a subtask once it has indented -Project 2
- Project Web Access add-in for Outlook
- Black progress line in the Project Center
- Lost by Global.MPT, and my settings
- Outlook and dates
- How do I Set reminder within Project XP to appear in Outlook
Tasks have uneccessary slack time & don't update. Posted: 22 Jun 2005 08:53 AM PDT Thanks for the response. I tried it the way I described it, and it works fine, so it most be something specific to my timeline. Tasks B and C are composed of many smaller tasks which are gathered under a summary task, and portions of task C can't be completed until task B is completed. Calculation is automatic, and nothing changes if I press the "Calculate" button. Aha! I found it. Some of the tasks have a percent complete greater than 0%. If I set it to 0%, they move as I anticipated. "JulieS" wrote: |
Posted: 22 Jun 2005 07:46 AM PDT Thank you for the help, Julie. Do you know if the '% Complete' field can be found in MSProject 2003? I didn't notice it but I will look again since maybe I missed it. -- Jack "JulieS" wrote: |
Displays incorrect year in calendar view? Posted: 22 Jun 2005 07:02 AM PDT Hi Jackiebp, I haven't seen this one before but here are a couple of suggestions to check: 1) Are you running SP-1 for MS Project 2003? Check Help > About Microsoft Project to see. If you have not installed SP-1 you can download it from http://www.microsoft.com/downloads/details.aspx?familyid=1b04c073-e58f-4f42-b76d-6b565a45cdc3&displaylang=en 2) What is the start date of your Project? Check Project>Project Information. 3) Have you inadvertantly added a task that has a start date in 1987? Sort the Gantt chart by Start Date to check. Hope this helps. Let us know how you get along. Julie "jackiebp" wrote: |
Posted: 21 Jun 2005 09:25 PM PDT thanks very much. -- Boris "Rod Gill" wrote: |
Duration set to actual calendar days? Posted: 21 Jun 2005 03:23 PM PDT Thor correctly told you how you can prefix the duration unit to turn it into elapsed time that ignores the working time calendar. 2 weeks on the wall calendar is 14ed but 10d. But before you do that, consider a couple of factors. First and formost - the duration of a task is not the time frame within which the task needs to be accomplished. If I have to wax 100 widgets, I can do 10 widgets per hour, I have them on hand and could start any time I want and they are due in 2 weeks, that task is NOT a 2 week duration task - it is a 10 hour duration task with a deadline 2 weeks away. The duration is an estimate of the time it will take to complete the task once it begins and reflects the actual working time expended on it by a resource. But work ONLY takes place when there is a warm body present to do it, hence the only time that gives you credit against the required work time and so counts for managing the project are those minutes during the day where there is qualified resource physically present and available to work. Non-working time is completely irrelevant when it comes to managing the project's work schedule to get it completed on time. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "ckelly2451" <microsoft.com> wrote in message news:com... |
Does Microsoft Project have a mobile component? Posted: 21 Jun 2005 12:10 PM PDT No, sorry. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Jbridges" <microsoft.com> wrote in message news:com... |
MS Project 98 and 2003 installed give error when open file Posted: 21 Jun 2005 09:09 AM PDT Debbie, Also you might try going to where the programs are located to find the 98 version, or go to the menu for "installs & uninstalls" it should be listed there. "Debbie G" wrote: |
I can't seem to outdent a subtask once it has indented -Project 2 Posted: 21 Jun 2005 06:36 AM PDT It's a bug in Proj 2003 Standard. Get the update at: http://www.microsoft.com/downloads/details.aspx?displaylang=en&FamilyID=1b04c073-e58f-4f42-b76d-6b565a45cdc3 "Shiv" <microsoft.com> wrote in message news:com... |
Project Web Access add-in for Outlook Posted: 21 Jun 2005 01:06 AM PDT Kevin, Have you enabled sharepoint services? I had a problem similar to this and no one could really help me, but once sharepoint services were enabled on our server, the outlook add-in began to work. Steve Budzynski "Kevin McC" wrote: |
Black progress line in the Project Center Posted: 20 Jun 2005 01:51 PM PDT texasroy -- Are you seeing errors in the application event log? -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com http://www.projectserverexperts.com "We wrote the book on Project Server" "texasroy" <microsoft.com> wrote in message news:com... |
Lost by Global.MPT, and my settings Posted: 20 Jun 2005 01:36 PM PDT Mike, I usually set the Project Start Time as the earliest date of the import file and 6:00. I did set it to the earliest date and 0:00 and tried 0:00 without a date, and still have it processing the odd finish date and time, based on the following day at 8:00 and duration. I seem to remember (a couple years ago) that the setting isn't in the calendar, it's another option. Is it a setting on Tools/Options/Schedule? Michael "Mike Glen" wrote: |
Posted: 20 Jun 2005 07:28 AM PDT You're welcome, Jitesh :-) Mike Glen MS Project MVP Jitesh wrote: |
How do I Set reminder within Project XP to appear in Outlook Posted: 20 Jun 2005 04:16 AM PDT Hi Scarab, You are welcome for the assistance and thanks for the feedback. Just to clarify, the instructions included with the URL was a "one-time" only process. After you have enabled the workgroup feature, you should be able to send the tasks and request updates as you do in Project 2000. Julie "Scarab" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |