RESOURCE SCEDULING Microsoft Project |
- RESOURCE SCEDULING
- Scrolling the Calendar View
- How to show percentange of delay in individual tasks in MS Projec.
- Changing timescale in Network diagram
- Project 2003 wants Safe Mode when installed on Terminal Services?
- Project: Can I link only the top-line task, w/o showing subtasks
- Publishing to a category
- Exporting to Excel (Project 2002)
- Summary Task Availability
- resouce availability for a project
- summary task dates not updating
- Scalable Fonts - Plotting
- Macro manage projects
- Indentation
- Why non-summary tasks not shown in Calendar view?
- Changing default published fields
Posted: 18 Jan 2006 07:44 AM PST You can create the resource hierarchy by leveraging a custom resource outline code: - Tools --> Customize --> Fields... - Custom Outline Codes Tab - Select Resource radio button - Rename an unused outline code - Define the code mask (how many levels in the hierarchy, the format, and the separator value) - Define the valide values in the hierarchy You can then assign each resource to a node within this hierarchy. This can be done by adding the new field to one of the resource views or by double-clicking the resource and setting the value on the Custom Fields tab of the resource information window. To set the capacity/availability of each resource, you have a two places: - Set the overall unit availability on the General tab of the resource information window. - Update the resource calendar to define the working times for the resource on the Working Time tab of the resource information window. To view the planned work (demand) relative to the resource availability (supply) you can then use the resource usage views. To roll-up the information based on your hierarchy, you can group the resources by the outline code: - Project --> Group By() --> Customize Group By... - Select your custom outline code in the field name section At this point, you can customize the timescale usage section of the screen to display unit availability, work availability or remaining availability in addition to work...based on what your preference is. You can also split the screen and use the resource graph on the lower pane to visualize the data that you select on the top pane. This will probably require some playing around on your behalf to find your favorite view. Good luck! John M. "N Smith" <microsoft.com> wrote in message news:com... |
Posted: 18 Jan 2006 05:51 AM PST Hi Greggy, Welcome to this Microsoft Project newsgroup :) Have you tried Format/Layout... and select to Attempt to fit as may rows as possible? FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Greggy wrote: |
How to show percentange of delay in individual tasks in MS Projec. Posted: 18 Jan 2006 02:35 AM PST Hi Prashanth , Welcome to this Microsoft Project newsgroup :) You coud try the Tracking Gantt, or have a look at the help pages for Variance. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Prashanth wrote: |
Changing timescale in Network diagram Posted: 18 Jan 2006 01:50 AM PST Hi Mike , Thank you very much for reply! I think my quastion was in bad sentence. I want to change my "Date format" to day of year. But in data template definition we haven't this option in "date format". Anyway I can see this option in Format.../ Time scale.../ Label ---> (day of week) in gantt chat view. And now I want this in network view! I want to show what day of year is my task start date in network diagram. please help me if there is any answer. Best regards. "Mike Glen" wrote: |
Project 2003 wants Safe Mode when installed on Terminal Services? Posted: 17 Jan 2006 06:20 PM PST Ahh, I didn't know that! I feel a $245 expenditure coming on. Ray "Mike Glen" <glenATmvps.org> wrote in message news:phx.gbl... |
Project: Can I link only the top-line task, w/o showing subtasks Posted: 17 Jan 2006 03:44 PM PST That actually did answer my question (FAQ 48). Thanks for your help. "John" wrote: |
Posted: 17 Jan 2006 03:27 PM PST You're welcome, Chuck :-) Then post on the server newsgroup, as the Desktop stand-alone version doesn't publish to anything. Mike Glen MS Project MVP Chuck wrote: |
Exporting to Excel (Project 2002) Posted: 17 Jan 2006 09:24 AM PST In article <dql048$65n$co.uk>, "MikeD" <com> wrote: Mike, You're welcome and get those "bright young things" a workin'. John Project MVP |
Posted: 17 Jan 2006 09:23 AM PST Perhaps you can clarify what your client (and therefore you) want to accomplish regarding resource management. There may very well be a way to meet this need. As to the original question, I will just add the clarification that asking for Remaining Availability for a task, summary task, or project fundamentally doesn't make sense. This piece of information relates to resources and and is visible at that level only...which is probably part of your "doesn't get it" comment. John "IbanezJem" wrote: |
resouce availability for a project Posted: 17 Jan 2006 09:05 AM PST Not to give you too many choices for how to accomplish the same result...but you could also set the maximum units for the resources = 0.75. This field should be on the basic Resource Sheet view, or you can double-click on the resource and then set the value in the Resource Availability section of the General Tab. This section allows you to quickly vary the availability over time (e.g. .75 up to March 31,2006 then 1.00 thereafter). This doesn't prohibit you from assigning the resource to work 8 hours in a day, but the default assigned units will be 0.75 and if you load the resource to 8 hours it will be shown as being overallocated. John "com" wrote: |
summary task dates not updating Posted: 17 Jan 2006 08:39 AM PST Hi Mike and Haris, Thanks for your help. The reason why the summary task was showing duration is that it is calculating the leg time, rather then just the number of the actual days. Is there a way to set this up so it does not ad up all the working days in the week during the task lenght, but just the actual days. I am not sure if I was clear with my question (I managed to confuse myself). Thanks Regards Figen "Mike Glen" wrote: |
Posted: 17 Jan 2006 07:38 AM PST Well, that's it then! If the preview is correct and you've got the latest driver, then there is nothng more we can do :( Mike Glen Project MVP KJROBBI wrote: |
Posted: 17 Jan 2006 07:23 AM PST John wrote: Too many companies are perpetually behind, usually because of poor or no planning, then rush everything to catch up, and only make things worse. Taking the time to do things right is often considered a "luxury" these days, one they can't afford. |
Posted: 17 Jan 2006 06:37 AM PST You're welcome, Jane :-) Mike Glen MS Project MVP JaneH wrote: |
Why non-summary tasks not shown in Calendar view? Posted: 17 Jan 2006 02:44 AM PST Hi Melissa, Welcome to this Microsoft Project newsgroup :) I don't know why, but expanding one row expandes them all. Looke further down to see if there's a week with more bars. In any case, the best I can offer is to try Formal/Layout/Attempt to fit as many tasks as possible. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Melissa wrote: |
Changing default published fields Posted: 16 Jan 2006 02:03 PM PST Thanks for the reply. This is one of several issues I've had to confront to which the answer has been the same (yes in 2003, no in 2002), I just have to extend my thanks again to Mr. Gates on the robust life cycle of 2002, and the great licensing obsticles in 2003. I have usually found an acceptible approach using 2002 without requiring users to pay the price. I'm trying to provide a cost effective, robust, primarily web based solution and the release of 2003 just months after my purchase of 2002 would get me hung by management if I were to ask for money for an upgrade especially with the requirement of professional on the desktop to publish in 2003 environment. Thanks Mr. Bill (right!!!) But truly thanks to you Dale!!! |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |