suitable merge key Microsoft Project |
- suitable merge key
- 2 questions - Project 2000 - Work scheduled is half of duration an
- analyze time scaled data in excel
- Project 98 - Installing?
- Can I do this in project?
- How do I limit Outline Number to exclude level 1?
- Display Predecessor and Successor Task Names
- Is Project worth it?
- Using effort-driven work, want durations and dates calculated....with no slacking!
- Schedule
- Multiple Work Calendars and Duration
- primavera format
- Interim tasks: tasks that span a flexible gap
Posted: 07 Nov 2004 08:51 PM PST i have 3 sheet in excel file. the first sheet contains task information and the merge key is task id . the second one contains resource information and the merge key is resource id . the last one contains assignment information.it has task name field, resource name field ,resource id field , task id field ,and work field. what is the suitable merge key for assignment. i want to import the data at the same time. "Rob Schneider" wrote: |
2 questions - Project 2000 - Work scheduled is half of duration an Posted: 07 Nov 2004 10:28 AM PST You're welcome, Monica. Let us know if you get it fixed - good luck! :-) Mike Glen MS Project MVP Monica wrote: |
analyze time scaled data in excel Posted: 07 Nov 2004 01:44 AM PST Hi Parastoo , Welcome to this Microsoft Project newsgroup :-) There are three palces where you can change the date format and when you go between software programs they must be the same. So: 1. Control Panel - find the Regional and Language Options, which is probably set up for your country and note the Date format set up for your computer. 2. Excel - select all the columns containing dates and go to Format/Cells/Date and select the same format. 3. Project - Tools/Options.../ View tab and select the same Date format. However, it is possible that the date format for your country is not available in Project. If this is so, then you will have to accept an alternative in Project and then reset Excel to match. If that still doesn't work, you may have to select a different setting for your Region. FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :-)) Mike Glen MS Project MVP mousavi wrote: |
Posted: 06 Nov 2004 03:01 PM PST You're welcome, Sapper, and thanks for the feedback :-) Mike Glen MS Project MVP Sapper wrote: |
Posted: 06 Nov 2004 09:01 AM PST You can do it in Project but it seems like hunting flies with an elephant gun to me. I have a task that will take 20 man-hours of work. I want to complete it by Christmas, 7 weeks from now. I work on average 40 hours per week, 8 hours per day. There are 35 working days, 280 working hours between now and Christmas. Therefore I need to spend 20/35 hours per day or something between 30 and 45 minutes a day working on it. That's exactly the same calculation Project does but at this scale of complexity I don't need hundreds of dollars worth of software to do it. At this level all you need is a calendar, pencil, and scratch paper; a middle-tech solution would be the Outlook calendar and Windows calculator; or you can go really high-tech and use Excel. If you do want to use Project anyway, perhaps so you get the pretty Gantt chart pictures, you'd list yourself as a resource (the only resource?) in the resource sheet and input the tasks and the durations within which you'd like to complete them. Split the screen and mark the tasks fixed duration. Assign yourself to the tasks as the resource working them. Enter the work estimate for the task and Project will calculate the percentage of your working time you'll need to devote to accomplish that much work within the duration specified. To play with the date, switch the task type to fixed work and when you edit duration Project will recalculate the effort, the percentage of your time, accordingly. If you look at the resource sheet and see your name listed in red, it means you've scheduled yourself for more total work in a day than your calendar says you want to do overall. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Keith Henderson" <keithatdvsolutions.teevee> wrote in message news:phx.gbl... |
How do I limit Outline Number to exclude level 1? Posted: 05 Nov 2004 12:02 PM PST Didn't quite say you couldn't input your own numbers - that's what the WBS code in the Project, WBS is for. You can name level 1 task AAA, or 100, or antythhing you choose. But what you can't do is display the WBS for some of the tasks in a view without displaying it for others. The display of a given field, ie, column in a table, is either on for all of the tasks in a view or for none of them. That means no matter what code you use, all the tasks in the view will show their codes if any of them do. You still can't have some of them at outline level 1 displaying your custom WBS code and others at level 1 not showing it. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "MOE Ken" <microsoft.com> wrote in message news:com... |
Display Predecessor and Successor Task Names Posted: 05 Nov 2004 10:56 AM PST Hi one method i use when the blue lines just get all too confusing is to format the gantt bar chart to show the predecessor numbers on the left and the successor numbers on the right (format / bar styles - text tab) and then i turn off the arrows (format / layout). It's a bit of a pain having to hunt for the predecessors / successors by number but it's a lot easier than trying to follow the lines! Cheers JulieD "tdbcalif" <microsoft.com> wrote in message news:com... |
Posted: 05 Nov 2004 09:58 AM PST Excellent discussion! As I put it to my classes - you don't need to understand all the tricks and techniques of a professional writer to know all there is to know about using MS Word but to use Project effectively you also need to understand the discipline of professional project management. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "JLB" <microsoft.com> wrote in message news:com... |
Using effort-driven work, want durations and dates calculated....with no slacking! Posted: 05 Nov 2004 08:36 AM PST Hi Julie, The full link is in the Links and Downloads page: http://www.mvps.org/project/links.htm . I think I'll add the full link to the Tiny one as it seems the Tiny one is unreliable. Thanks for your input Mike JulieD wrote: |
Posted: 04 Nov 2004 01:15 PM PST Hi if you assign to meetings to the same resource, whether it be a room or a person, then it will show in red in the resource sheet (known as "overallocated") to see why a resource is overallocated you can use the resource allocation view. However, Project won't WARN you that you're trying to overallocate a resource in the assignment stage. Hope this helps Cheers JulieD "Iconoclast" <com.ph> wrote in message news:phx.gbl... |
Multiple Work Calendars and Duration Posted: 03 Nov 2004 02:04 PM PST The base unit of duration is the minute. "Days" are allowed in user input and display for convenience but are converted to and from hours, thus minutes, according to the conversion factor on the Tools Options Calendar page. If it helps, start thinking of "day" as meaning "workday," a single normal 8-hour work shift, rather than a calendar day and when estimating durations think in terms of the number of shifts the tasks will require. Thus a one calendar day task lasting 24 hours start-to-finish, starting Monday at 8am and finishing Tuesday at 8am, takes 3 8-hour shifts or 3 consecutive workdays to complete. If entering and keeping track of the tasks is becoming too complicated, start estimating work efforts in hours to begin with. You say you are hoping for duration to be equal to the physical number of calendar days. Sorry, you just can't have that. Project time is measured in either elapsed time or duration time. Elapsed time is the sort of time watches and conventional calendars measure. The month of November has 30 days, 720 hours. But duration is specifically defined as the number of working time units between two points (see PMBOK definitions) and any non-working time is explicitly excluded from the measure. In the US and assuming a normal 8 hour workday, the month of November has 20, 21, or 22 work days (22 weekdays minus 1 or 2 day Thanksgiving holiday) giving it a duration of 160, 168 hours, or 174 hours depending on where you are. I'd suggest examining your 24 hour calendar resources to see if that's really accurate. The 24 hour calendar means that once the resource starts work, that specific individual worker doesn't take a break until the work is done, regardless of whether the task takes hours, days, weeks, or even months to complete. People just don't do that. I'll bet what you're thinking here is that you have, say, a group of 10 welders, some on days, some of swing, some on graveyard with a base calendar of the 24 hour calendar assigned to the group. You have a welding task that will take one person 24 hours to do so you're putting 1 day shift, 1 swing shift, and 1 graveyard guy on it, each one relieving the guy before him and working until the task is done. There are all kinds of problems with that - calendar problems are one but also resource allocation and tracking max allocations as well. I'd suggest a possible better way is to have 3 separate resource listings - Day Shift Welders, max 400%, base calendar 8am-5pm; Swing Shift Welders, max 300%, base calendar 3pm-12mid; Night Shift Welders, max 300%, base calendar 11pm-8am. You have a task that will take 24 man-hours work and you need to get it done in one continuous stretch of work going on steadily from start to finish so it gets done ASAP. Enter the task with 3 days duration. Use the split screen to assign the resources. Enter all three resources -- Day, Swing, & Grave -- with an assignment of 100% meaning one guy from each of the 3 shifts and give them 8 hours work each. Duration will still be 3 days, ie, 3 shifts, but the task will go 24/7 until done and take 1 calendar day in the schedule. Hope this helps -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Jens" <microsoft.com> wrote in message news:com... |
Posted: 02 Nov 2004 11:09 AM PST P3 will read .mpx, but not .mpp. The newer programs that have replaced P3 will read both .mpx and .mpp. And also with the ability to tailor the data when importing. (Data can even be stored inside the Primavera database and be part of a value-added bigger environment, whil being used as "normal" by MS-P.) Which doesn't help if it has to be P3, I know. If you can convert it to .mpx, the client may accept it, although there's a lot more potentially to even P3 data so that depends on their detailed requirements. "Ed" <microsoft.com> wrote in message news:com... |
Interim tasks: tasks that span a flexible gap Posted: 02 Nov 2004 10:44 AM PST Thanks! This was just the information I was looking for. Out of curiosity, what is the internal updating approach for links? I noticed that changes aren't always immediately reflected after moving controlling tasks, but may be postponed until several tasks have been manipulated. JulieS wrote: ----== Posted via Newsfeeds.Com - Unlimited-Uncensored-Secure Usenet News==---- http://www.newsfeeds.com The #1 Newsgroup Service in the World! >100,000 Newsgroups ---= East/West-Coast Server Farms - Total Privacy via Encryption =--- |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |