Is there a way to reorder groups manually other than ascending an. Microsoft Project |
- Is there a way to reorder groups manually other than ascending an.
- Default link type
- Change default link type
- Configuring tasks in weeks not days
- How do I rename a project after it's been published?
- How do you print Gant Schedule?
- Readonly Fields??
- Multiple Project Calendars - Project 2003
- Dose the longest task start first by default?
Is there a way to reorder groups manually other than ascending an. Posted: 09 Nov 2004 12:10 PM PST Steve, I am using task groups keying off of a customized number field. "Steve House [MS Project MVP]" wrote: |
Posted: 08 Nov 2004 06:50 PM PST Hi Makyla i'm hoping that some of the other people to this forum stop by to give their opinions ... however, here's mine: - you CAN schedule from a finish date (project / project information - schedule from & then put the finish date in), in this way you can still use the default link types and still achieve what you're after. However, there has been a number of posts saying that scheduling from a finish date can product unreliable results and it is always better to schedule from a start date ... and see what you need to change to achieve the desired finish date. Unfortunately, i don't know the ins and outs of the topic but it has something to do with how the critical path is calculated. When it comes to SF relationship types there is also a problem with how this relationship type works when you have more than one predecessor - try this for an example (scheduling from a start date) set up a project file as follows: task 1 - 1d task 2 - 2d order materials - 2h task 5 - 2d - predecessor task 1 FS task 6 - 2d - predecessor task 2 FS now what we want to achieve is the ordering of materials to be done before the start of task 5 or 6 - which ever one comes first .. so we can use a SF relationship with Task 5 as the predecessor and order materials as the sucessor .. .and as you notice, project will schedule the order materials before task 5. Change the predecessor of order materials to task 6 and project will move order materials to the start of task 6 - all good .. now make 5 & 6 both predecessors to the order materials task and notice that project moves it to the start of the latest one not the start of the earliest one as one would (possibly) expect. so basically taking all these things into consideration the recommendation is that you always schedule from a start date using FS relationships (and SS / FF & SF were really applicable) and then you look at your project schedule ... if you're finishing before your deadline, change the start date .... everything will automatically "adjust", if you're finishing after your deadline - display the critical path and do what you need to do to bring it in line. Hope this helps Cheers JulieD "makcam" <microsoft.com> wrote in message news:com... |
Posted: 08 Nov 2004 06:47 PM PST You don't need to do that and actually it is strongly advised not to. First of all, the links describe logical process relationships between your tasks. Whether you are scheduling from start date forward or finish date backwards, you have to put up the walls before you put on the roof because the law of gravity says you can't build the roof in midair and then stuff the walls in under it. Physics drives it, not convenience or desired timing or even schedule mandates. "Erect Walls" is the predecessor and "Apply Roof" is the successor and the relationship is FS because of the inherent nature of the building construction process and that's just the way it is. Now, as for scheduling for a specific finish date. The behavior you say you want is built right into Project without having to "get creative" with the links. In the Project menu, you can select Project Information and there you can designate "Schedule from finish date" and it will set up your tasks just as you say you want. Now, the problem with that is that it will schedule all your tasks to occur as late as possible to meet your required finish date. Unfortunately that also makes ALL tasks in your project critical and you have no margin for error (and there are ALWAYS unforseeable errors). If just ONE of your tasks takes any longer to complete than you thought it would or starts later than you'd planned on because, say, a resource called in sick, you'll miss your required finish date. The far better way is to schedule from the earliest practical start date forward, set a deadline of your required finish date, and then tweak the schedule so you meet the deadline. You'll probably find some tasks are critical and others not, allowing you to concentrate your management skills where it really counts. You can then make an informed decision "Do we start 1 Dec which gives us a 2 week cushion at the end or do we start 15 Dec and make sure Tasks 10, 17, and 22 don't run late at any cost, ready to pull people off of Task 19 (which has a lot of float) if it turns out that one critical task runs late and we need to move 'em to the delayed task to get it done back on schedule?" -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "makcam" <microsoft.com> wrote in message news:com... |
Configuring tasks in weeks not days Posted: 08 Nov 2004 10:39 AM PST Simply enter the durations in weeks. An entry of 3m is minutes, 3h is hours, 3d is days, 3w is weeks, and 3mon is months. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "BumbleBee" <microsoft.com> wrote in message news:com... |
How do I rename a project after it's been published? Posted: 08 Nov 2004 09:54 AM PST We're using 2003. I downloaded and ran the tool but keep getting an error: "The server did not recognize your request" I can only seem to log in by checking the "Trusted Connection" checkbox, but that works fine and shows a list of all projects on Project Server. When I click "Rename" and enter a new name (or eventhe same name) I get the error msg above. Also tried this connected to the server itself so that projectserver could be accessed at "localhost" which the tool seemed to want, but no luck. "Dale Howard [MVP]" wrote: |
How do you print Gant Schedule? Posted: 08 Nov 2004 09:09 AM PST You display the view you want to print hard copy of and then print it. The limitations you're probably seeing on page size are not a function of MS Project - that information comes from the printer driver. If you want to print a page that is a 24x36 or 30x42 ANSI standard Architectural size for example, you need to have a printer or plotter connected that accomodates that paper size. If all your printer can output is regular letter or legal sized pages, printing the views you want will extend over multiple sheets and you'll need to get out the tape or glue and paste them on a poster board. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "jpt" <microsoft.com> wrote in message news:com... |
Posted: 08 Nov 2004 06:30 AM PST Glenn, So..right now you cannot make any change in that field (the one you are saying is read only) and you want that field to be editable right? In that case..you need to change the column definition for that particular column. double click on the title for that column and if the field name in the column definition window is ID that's why is is read only. You need to change the field name either to text or number whatever you demand is for that column. Then you can enter your own data in there. Hope it helps.. "Glenn" wrote: |
Multiple Project Calendars - Project 2003 Posted: 05 Nov 2004 02:01 PM PST Hi Julie Many thanks for your response. My 24 hr resources are servers, and we tend to treat them a little less respectfully than our manpower. I am beginning to come to the realization, I will have to define "work" in hours. I have just been trying to understand what the task specific project calendar controls (in the task details dialogue boxes). Regards Jens "JulieD" wrote: |
Dose the longest task start first by default? Posted: 03 Nov 2004 03:18 PM PST Hi Gerard, Thank you very much. Yes, I was using the automatic Leveling. I believe this is the default. Is it common to turn it off? Mike. "Gerard Ducouret" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |