Change a resource's max availability and see its effect Microsoft Project |
- Change a resource's max availability and see its effect
- Task Name Format
- assign start dates to tasks
- PWA CAL Licensing
- No Printer Selection Printing from Print Preview in Project
- looking for a resume cover letter for relocating
- Calendar doesn't work in MS Project 2K3
- Can I constrain 2 tasks not to occur simultaneously?
- Showing task splits in Gantt view
- Need to create a reocurring task that will take place twice a mon.
- Assign a task to a certain hour
- Duration vs. Work
- Comparing Dates of 2 projects
- print calender
- How to print a daily report of today's tasks?
- Views Post
- Global.mpt location
- project should include summary tasks in in workgroup update, assi.
- Print formatting
- group
- My wrapped text does not print.
Change a resource's max availability and see its effect Posted: 17 Nov 2004 07:32 PM PST Explaining Jan's answer a bit - FYI, changing max units in the resource information only sets a new cutoff above which the resource is considered overallocated and also the default assignment level for new assigments for the resource. It doesn't go back and change any currently existing assignments as you've discovered. Leveling only functions to delay one or more out of a set of conflicting tasks when a resource on them is booked for a total usagethat is higher than the max allowed for him, resolving the overallocation. It never changes the assignment level on individual tasks. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Tim" <microsoft.com> wrote in message news:com... |
Posted: 17 Nov 2004 06:19 PM PST Please don't feel stupid. Not terribly intuitive to call it outline numbers! ;-) Let us know if we can help again. Best regards, Julie "Gary Mitchell" wrote: |
Posted: 17 Nov 2004 11:15 AM PST If the start date cannot change either forward or backward, put a Must Start On constraint on Task 1 under each job. FYI - this is contrary to the usual use of MS Project, which is to determine when the tasks would be able to take place. Generally speaking you don't tell Project the dates when tasks will take place; instead, it calculates the schedule based on what needs to be done, how long each task will take, and when the resources required would be available and then tells you the dates you can have. But there can be exceptions where external conditions impose a start or end date and applying constraints is how they can accomplished in the schedule. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Julie" <microsoft.com> wrote in message news:com... |
Posted: 17 Nov 2004 08:33 AM PST Thanks. Spoke with an MVP yesterday and he confirmed what we were thinking. He suggested a good way to lock-down the number of PWA users is by placing the unlicensed users in a specific group in PWA called "Unlicensed" and deny this group the ability to login to PWA. "JackD" wrote: |
No Printer Selection Printing from Print Preview in Project Posted: 17 Nov 2004 07:58 AM PST Hi Steve it's a project thing .. don't really know why but there's nothing wrong with your install - we all suffer from the same limitation (AFAIK - if anyone has an alternative please let me know too) :) Cheers JulieD "steve" <com> wrote in message news:google.com... |
looking for a resume cover letter for relocating Posted: 17 Nov 2004 07:54 AM PST Brandi, This NG is dedicated to the Microsoft Project software. You'll have better luck getting an answer elsewhere, like maybe an MS Word NG. Sarah |
Calendar doesn't work in MS Project 2K3 Posted: 17 Nov 2004 04:36 AM PST Hi Bobby personally i agree with you ... but i've learned to live with it - however, if you've got project 2000 or newer you can "fill down" the project calendar - so you assign it to the first resource and then just drag down using the fill handle (little black cross bottom right hand corner of the cell). Cheers JulieD "Bobby" <com> wrote in message news:de... |
Can I constrain 2 tasks not to occur simultaneously? Posted: 16 Nov 2004 02:15 PM PST Ahhh ... simple cost tracking or Earned Value calcs? Hmmm. The machine I'm on right now has P98 and doesn't know about materials so I can't say. If you set the resource or material to have a value or rate of $0 then you shouldn't have an impact on your total costs or on cost variances. Your schedule variance could be a different matter. But since you're moving lots of "task groups" (for lack of a better phrase) around you're probably not concerned about schedule variances, you just want to make certain the stuff gets done (and whether that's this shift or three shifts from now is not a driving concern.) That's the long answer. Short answer: don't know; try both ways <grin>; report back. "KellyB" wrote: |
Showing task splits in Gantt view Posted: 16 Nov 2004 02:12 PM PST Hi KellyB, I'm afraid I'm all out of thoughts. I assume you want to show the "split" (tasks stopping during non-working time) for both the day shift and the night shift in a single view. As you can only display one non-working time as the background of your gantt, I don't believe there is a solution. The task usage view (zoomed in of course) will show the hours for each resource as they are distributed, but I don't think you'll get want you want from the Gantt. You could customize the Gantt bars with colors based upon the resource's base calendars, but that's about all I can come up with. So sorry. Julie "KellyB" wrote: |
Need to create a reocurring task that will take place twice a mon. Posted: 16 Nov 2004 12:39 PM PST If you called the Recurring task Meeting then you will end up with "Meeting 1" twice; "Meeting 2" twice ... I'd use different task names ("Mid-month" and "End-of-month"). Other than that, you are spot on in both your suggestions. (BTW ... Ti-Cats can always wait until next year. Again.) "Steve House [MS Project MVP]" wrote: |
Assign a task to a certain hour Posted: 16 Nov 2004 09:47 AM PST Thanks Jan, I found my answer about two seconds after I hit the post button. You have to have the field formatted correctly with date and time before it will allow to type in the time. Thanks again for your time. "Jan De Messemaeker" wrote: |
Posted: 16 Nov 2004 09:14 AM PST I think Jan meant times and not types:) Mike Glen Project MVP Jan De Messemaeker wrote: |
Posted: 16 Nov 2004 05:44 AM PST Hi John, Well, my post above is timed on my laptop at 21:41 in answer to your post timed at 21:48, ie I answered your post before it arrived! Maybe it's something to do with Outlook Express' timer? Mike Glen Project MVP John wrote: |
Posted: 16 Nov 2004 02:43 AM PST Hi Moradi, Just to clarify: do you want to print out the definition of your base calendar (working times, holidays etc) or do you want to print your tasks in the calendar view? If you want to print just the definition, in View --> Reports --> Overview--> Working Days the pages after page one show all the base calendars you have defined. (Each base calendar will be on its own page.) To edit a calendar, go to Tools --> Change Working time, select your base calendar from the drop-down and edit away. Hope this helps. I apologize if I have misunderstood your question. Julie "com" wrote: |
How to print a daily report of today's tasks? Posted: 15 Nov 2004 02:44 PM PST Thanks for the suggestion. I've set up my report as a Task Report, grouped on 1 Day. I've changed my Resource Group field to indicate Daytime workers and Nightime workers, then I filtered using the Resource Group field. By filtering for either Resource Group = D or = N, I can create a report for the day shift tasks, or the night shift tasks. Thanks. "Sarah" wrote: |
Posted: 15 Nov 2004 02:34 PM PST Jim, It sounds like you already have your custom views set up, correct? If this is the case, then go to Table>More Tables and select the Entry table for tasks. Click Copy. Rename the table to something appropriate for its new purpose, edit the fields so that only the ones you want to print are listed, and click OK. Then go to View>More Views and select your print view. Click Edit and in the Table field, select the table you just created. Click OK and this table will always be used for that view. Sarah kikos@(removethis)nationwide.com |
Posted: 15 Nov 2004 02:19 PM PST Hi, Disregard the message. A "project1" is opened with that global anyway. The message is totally irrelevant (even wrong) HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Sam" <microsoft.com> schreef in bericht news:com... to on global.mpt |
project should include summary tasks in in workgroup update, assi. Posted: 15 Nov 2004 12:38 PM PST Hi Sarah True: I wasn't referring to the workgroup messages specifically, but generallly throughout projects if you need to show their origin. Mike Glen Project MVP Sarah wrote: |
Posted: 15 Nov 2004 08:41 AM PST Julie, That would then become a training issue. If you set up a global view that everyone understands is ONLY to be used for printing for the Sr. VP, then they should understand that they must not make any changes to it. I've operated this way at prior companies, and it works well. Sarah |
Posted: 15 Nov 2004 03:24 AM PST Hi parastoo mousavi, Sorry, after more thought - you will want to modify the "Assignments keeping outline structure" group to include the Group field (resource) as the first line. Then you should see what you are looking for. Julie "JulieS" wrote: |
My wrapped text does not print. Posted: 14 Nov 2004 07:34 AM PST You're welcome, Cindy:-) Mike Glen MS Project MVP cindyclayton wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |