Setting Default Cost Rate Table Microsoft Project |
- Setting Default Cost Rate Table
- Project 2003 is missing network diagram layout options (like Hori.
- Weird Fixed Duration Calculation!
- How do I identify existing schedule conflicts in MS project
- Dumb question start date
- project management courseware
- True Consulting Cost/Benefit
- How do I manage/balance resources where one reasource is leading .
- Empty lines at end of schedule
- MSProject: Allow durations in years and also calendar months.
- Problem with Updating Actual Work
- Changing number of workdays in a week
- Project Flashes and Calculates
- Tasks Submitted by Resources
- Rebuild improperly constructed schedule?
- Trial Version of MS Project 2000 Not working
Setting Default Cost Rate Table Posted: 07 Oct 2004 09:45 AM PDT Thanks Steve! "Steve House [MVP]" wrote: |
Project 2003 is missing network diagram layout options (like Hori. Posted: 07 Oct 2004 08:05 AM PDT Hi, In the Network diagram, via Format, Layout, check "Allow Manual Box Positioning" HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Frank Lee Stunned" <Frank Lee microsoft.com> schreef in bericht news:com... one |
Weird Fixed Duration Calculation! Posted: 07 Oct 2004 03:51 AM PDT As Jan said, probably a bug. But if you leave out manually entering the duration, and just put in the assignment units and the work required it will calculate duration correctly. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Simon" <co.uk> wrote in message news:google.com... |
How do I identify existing schedule conflicts in MS project Posted: 06 Oct 2004 08:15 PM PDT If by schedule conflicts you mean resources being double booked, just go look for the red names on the resource sheet. Red means they're overallocated, which means that at some point in the project they're booked to be doing more work than their maximum allowed usage. Usually this means you've put them to be in two places at once, ie, working on two or more concurrent tasks that should require their full attention each. To identify the specifc areas of conflict, switch to one of the usage views and use the [Alt][F5] hotkey to jump from overallocation to overallocation. Look for work hours in red. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Garry Collins" <Garry microsoft.com> wrote in message news:com... |
Posted: 06 Oct 2004 03:37 PM PDT You are welcome. -Jack "Terrell Miller" <microsoft.com> wrote in message news:0bcb01c4ac7a$cf557b90$gbl... |
Posted: 06 Oct 2004 02:32 PM PDT Sybex's book "IT Project + Study Guide" by Heldman and Cram is a good overview, esepcially if you're in the IT industry. It's oriented toward preparing for the Comptia certification exam but still is a good general discussion of PM principles with application regardless of the industry you're in. Element K Press has courseware available to prep for both the Comptia IT Project + and the PMP exams that could be useful as well, albeit somewhat limited in scope. All of these require between 5 to 10 class days to deliver the material. Element K also has courseware for a 1-day "Project Management Fundamentals" course but it is very light-weight in my opinion. As a preliminary day before 2 or 3 days training on MS Project it's ok but about all it really does is expose the students to some basic vocabulary and general PM concepts. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "need help" <microsoft.com> wrote in message news:04bd01c4abeb$ea851130$gbl... |
Posted: 06 Oct 2004 02:05 PM PDT Thank you. That is what I think I am looking for and I will give it a try. "Steve House [MVP]" wrote: |
How do I manage/balance resources where one reasource is leading . Posted: 06 Oct 2004 02:05 PM PDT I'd do it like this. It sounds like resource 2 is supervising while resource 1 is actually doing the work. When the supervisor is actively interacting with the worker he can't be doing something else but on the whole watching over this task is only going to occupy a portion of his workday. Estimate how much time is going to be consumed by his oversight duties, for illustration lets say he's going to spend about 1 hour per day coaching the worker actually doing the task. Enter the task, 2 day duration, and assign the full-time resource actually doing the work to it 100%. Make the task non-effort driven for the moment. Assign the supervisor at 12% - this represents him spending about 1/8 of his workday doing whatever he does related to this task leaving him free for 7 hours a day to be elsewhere. Another possibility. Resource 2 needs to be there to get resource 1 up and running but then his work is done and resource 1 can continue on by himself to finish the task. For illustration, figure it's going to take 1 hour to get the worker doing the task up to speed. Enter the task, again with a 2 day duration and assign Resource 1 to it 100%. Split the screen. In the bottom window assign Resource 2 with 1 hour of work, effort 100%. This indicates when he's there he's there full-time but it is only for one hour of the total task time. For that one hour he can't be anywhere else without being overallocated but after that he's free to be assigned elsewhere. If you really need to do it, the Resource Schedule form in the bottom window would even allow you to specify just WHEN his one hour of work would occur. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "TecMan" <microsoft.com> wrote in message news:com... |
Empty lines at end of schedule Posted: 06 Oct 2004 12:49 PM PDT Peggy, Nothing comes to mind at the moment but you could try a brute force approach. Select all the desired tasks and copy them to a new project. Unless there is something funny going on with your printer settings, there must be some extraneous data in the file that should be eliminated with a copy/paste. Or, here's another suggestion. Try saving the file as a Project database and then opening it up again. Maybe during all the tweaking you did to the file, some corruption crept in and this method might just help. You might also try the MVP webpage at: http://www.mvps.org/project/faqs.htm and look at FAQ 43 - file bloat? - might be corruption If no one else jumps in with other suggestions and neither of the above helps, if you can, send me the file via e-mail and I'll take a look at it. If it contains sensitive information I can provide you a macro that will desensitize it or you can go to Jack Dahlgren's website (Jack is another MVP) at: http://masamiki.com/project/macros.htm and look for his "scrub" macro. It does basically the same thing. If you send the file, be sure to zip it. Hope this helps. John |
MSProject: Allow durations in years and also calendar months. Posted: 06 Oct 2004 10:45 AM PDT Only trouble is that screws up your work values. With the default calendars there are 8 working hours in a duration day but 24 working hours in an elapsed day. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "John" <microsoft.com> wrote in message news:com... |
Problem with Updating Actual Work Posted: 06 Oct 2004 10:04 AM PDT Hi, How would Project know when your updates are complete and it can shift the remaining work? You have to tellit "go" There is a button on the tracking toolbar to do it so it doesn't take much time. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Bob" <microsoft.com> schreef in bericht news:01e201c4abc9$2bcc9320$gbl... |
Changing number of workdays in a week Posted: 06 Oct 2004 09:27 AM PDT Jan, Thanks for the help !! /Lars "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message news:OZW7uf%phx.gbl... the the chart message for below |
Project Flashes and Calculates Posted: 06 Oct 2004 08:19 AM PDT Sounds like something else might have used that field in its calcalation. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "luvgreen" <microsoft.com> wrote in message news:com... |
Posted: 06 Oct 2004 07:05 AM PDT Project Server. stand alone project in message and |
Rebuild improperly constructed schedule? Posted: 06 Oct 2004 06:46 AM PDT Steve - Thanks for your insight. I misspoke when I said making changes resulted in "incorrect" dates - what I meant was basically what you said, that the changes result in different dates. They are 'incorrect' in the sense that they don't agree with the original start/finish dates, but I digress. I'm about to try your baselining suggestion, and I appreciate the tip. Thanks Dave "Steve House [MVP]" <send.hotmail.com> wrote in message news:<phx.gbl>... |
Trial Version of MS Project 2000 Not working Posted: 05 Oct 2004 07:15 PM PDT Hi Andy, Welcome to this Microsoft Project newsgroup :-) I don't think anyone knows! :( It sounds like a corrupt installation and I can only suggest you uninstall it, shut down the PC and then re-install again. FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :-)) Mike Glen MS Project MVP Andy wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |