Displaying WBS of another task in task name Microsoft Project |
- Displaying WBS of another task in task name
- how can you display initials allocated to a resource
- Where can I get Microsoft Project 2003 viewer freeware?
- Unit Allocation
- Change resource assignments Auto / leveling
- Can I set up an autodelete for completed tasks in Gantt view?
- .Net Framework 1.0 vs. 1.1 on client?
- Pasting from Excel into Project 2003
- Re-using old MPP files
- Summary tasks adding work
- TOTAL COST COLUMN (IN TASK USAGE VIEW)
- need help asap
- Leveling How To
Displaying WBS of another task in task name Posted: 06 Oct 2004 03:22 AM PDT I know this doesn't answer your question directly but perhaps a shift in thinking about the project structure would render the problem moot. The classic definition of a project's phases includes Initiation, Planning, Execution, Control, and Closeout (though I personally tend to think of Execution and Control to be two interwoven and interacting process streams within the same phase of the project). Thus Project Initiation is not a single activity, although crossing a go/no-go decision point would certainly be shown in the plan as a single milestone task, but initiation itself is a broad phase, represented by a summary task with potentially many additional subtasks underneath it. I would say your presentation and the other "aritfacts" are *components* of the Project Initiation phase as a whole, not something that comes before it. Thus phase 1 in toto would be Project Initiation. Early in the phase you're preparing the business case, feasibility studies, early schedule and budget estimates, supporting documents, etc. At the end of initiation there would be a milestone marking the decision to proceed and you'd continue on to the Planning Phase where you prepare the detailed project plan, including the schedule and working budget and define the other management and controlling processes that will be used in carrying out the project. When the plan and all its components and supporting documentation is completed, you pass another milestone marking the transition from project planning into the project execution phase. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Michael" <com> wrote in message news:118201c4ab8e$73d4d410$gbl... |
how can you display initials allocated to a resource Posted: 06 Oct 2004 02:29 AM PDT Hi Jonathan, I think you then have to select which column to insert - in this case it wouild be the Resource Initials field. But that won't show up in the Ganttbar without doing as I suggested. Mike Glen Project MVP Jonathan Yong wrote: |
Where can I get Microsoft Project 2003 viewer freeware? Posted: 06 Oct 2004 12:27 AM PDT Hi Siva, Welcome to this Microsoft Project newsgroup :-) Please see FAQ Item: 16. Project Viewer. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/ Hope this helps - please let us know how you get on :-) Mike Glen Project MVP Siva Prasad Kuppala wrote: |
Posted: 05 Oct 2004 01:03 PM PDT Can you be more specific? Project doesn't just arbitrarily change assignments. What are you doing or editing when you see the change? What are the task types you have set and what fields have you manually input for them before assigning resources? How are you going about making the assignments? -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "projuser" <microsoft.com> wrote in message news:com... |
Change resource assignments Auto / leveling Posted: 05 Oct 2004 12:53 PM PDT Hi tball, You may even ask it a third time, the answer will still be no, sorry :-) -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "tball" <microsoft.com> schreef in bericht news:com... levels |
Can I set up an autodelete for completed tasks in Gantt view? Posted: 05 Oct 2004 10:53 AM PDT But you still run into what sorts of tasks and activities each is optimized to do. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message news:phx.gbl... |
.Net Framework 1.0 vs. 1.1 on client? Posted: 05 Oct 2004 09:19 AM PDT Project server does that. -Jack "~Lenny" <microsoft.com> wrote in message news:com... so client set running see |
Pasting from Excel into Project 2003 Posted: 05 Oct 2004 09:12 AM PDT Yep - you're right. One of those odd ball fields. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "JackD" <momokuri@gmail> wrote in message news:%phx.gbl... |
Posted: 05 Oct 2004 07:54 AM PDT Try removing any actual dates and progress on the tasks. -Jack "Phil" <microsoft.com> wrote in message news:283901c4aaeb$30fe1190$gbl... |
Posted: 05 Oct 2004 06:41 AM PDT No resources existed on summary task. What I just did was to outdent detail tasks - that made Work editable on old summary - changed work to zero and then indented detail again. Now summary task reflects the proper work. Thanks for reply. "Jan De Messemaeker" wrote: |
TOTAL COST COLUMN (IN TASK USAGE VIEW) Posted: 05 Oct 2004 05:18 AM PDT Hi John Thanks for your answer. Not sure if it will help though. Let me explain rather what we are trying to do here. (Perhaps I shouldn't have asked about Overtime Rate, because I don't think this field is going to help me anyway) In the task view the total cost column is giving me answers for the standard rate x by hours worked in Rands (we have worked out a cost rate and a charge out rate for each resource and from that we want to work out % profitability). - Task usage view only shows total cost column (our standard rate which is our cost rate x by number of hours worked) - I want to add in another column which will show me total revenue (our charge out rate x by number of hours worked) and then; - I want to add in another column which will show me Revenue less cost and then; - I want to add in another column which will show me % profit. I can do all this using custom fields in the resource sheet, but I want to see the cost at a task level not at a resource level. In the past we have been copying from Task usage sheet into excel template which has all the formulas in it, but it seems silly to do it that way when MS Project carrys these fields and fields can be customised. I'll go back and try your suggestions though. Please investigate further for me. Kind regards Adele base rate to be field will then A custom field you want is straightforward if more complicated indeed your file at FAQ 37 - tasks, my short macro to develop a apply it as value can be put |
Posted: 04 Oct 2004 02:02 PM PDT Hi Ashley, Inserting Projects into a master only provides a common view on tasks, it does not consolidate resources. To consolidate resources you need to connect the projects to a resource pool. Lookup the help on resource sharing or resource pools. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Ashley" <com> schreef in bericht news:01f801c4aa55$77396a10$gbl... |
Posted: 01 Oct 2004 09:13 PM PDT See my other reply on to you on this topic. From a strictly computational standpoint, perhaps your problem appears simple. Actually it is not simple at all. From a business context standpoint it is a highly complex problem that goes beyond the ability of any software to resolve. That's why humans are still in the loop. Just because Bill is only being used 50% on task X and isn't assigned anything else in the project that day and you sure could stand to have that task done sooner, doesn't automatically mean you can increase him to 100%. There are many other strategies possible in addition to simply bumping up his assignment and only a human expert - that's you - can know which of them is the optimum and which just aren't possible to do in this specific case. Even finishing the project in the shortest possible time isn't always the best business strategy. Would you take resources away from a product rollout intended for this year's Christmas shopping season in order to shorten the development time on a project creating a product intended to be introduced for NEXT year's Christmas season and would be done by next September without the increased resources anyway? -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "tball" <microsoft.com> wrote in message news:com... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |