consolidated project files Microsoft Project |
- consolidated project files
- Adjust Work Based on Skill Level
- Actual Work and Task Finish Date
- Dependencies - is there a best practice when creating the plan?
- Duration in "ewks"
- Project Calender
- Resource Hours
- How to customize Timeline values or labels?
- Layout of links
- Is there a way to customize reports?
- Project 2003 Professional and email collaboration
Posted: 23 Aug 2004 05:10 AM PDT Hi Jan thanks ... just trying to figure out the best way to approach a problem. Cheers JulieD "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message news:phx.gbl... looking |
Adjust Work Based on Skill Level Posted: 21 Aug 2004 12:03 PM PDT Hi, Try the following macro. Attention, depending on task type and effort driven there is an effect on task duration but I hope you know all that. Put "standard" work (in hrs) in the number 1 field of the assignment (assignment lines are the detail lines in a Usage view), and the correction factor in the number1 field of the resource: Sub Skillwork dim job as task Dim ass as assignment dim slave as resource for each job in activeproject.tasks if not job is nothing then for each ass in job.assignments set slave=activeproject.resources(ass.resourceid) ass.work=ass.number1*60*slave.number1 next ass end if next job end sub HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "DellaCroce" <net> schreef in bericht news:er#phx.gbl... about Estimated |
Actual Work and Task Finish Date Posted: 20 Aug 2004 04:35 PM PDT Thanks, Steve. That does explain why the numbers looked odd to me. Jim Williams, PMP Norfolk, VA On Sun, 22 Aug 2004 06:00:12 -0400, "Steve House" <send.hotmail.com> wrote: |
Dependencies - is there a best practice when creating the plan? Posted: 19 Aug 2004 02:07 PM PDT thank you "Mark Durrenberger" wrote: |
Posted: 19 Aug 2004 12:37 PM PDT Corey -- The designation "ewks" refers to "elapsed weeks." An elapsed week is seven 24-hour days, thus, it will ignore the project calendar. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant Denver, Colorado http://www.msprojectexperts.com "We wrote the book on Project Server" "Corey" <microsoft.com> wrote in message news:92c201c48624$06455c10$gbl... |
Posted: 19 Aug 2004 10:11 AM PDT You're welcome, Andy :-) Mike Glen MS Project MVP Andy wrote: |
Posted: 19 Aug 2004 08:06 AM PDT You have a couple of options. IMO, if the task requires his full attention from start to finish and once started will take take him 6 hours to complete, it is a 6 hr duration task, not a 1 day task. If you estimate that it will take 4 to 6 hours, since durations are estimates, not certainties, until the work is actually done, split the difference and plan for it as a 5 hour duration task or 6 hours if you want to allow a bit of cushion. Another way to do it is to assign him at less than 100% allocation - again, split the difference and since he needs to accomplish an estimated 5 hours of work over the course of an 8 hour duration, his assignment for that task is 5/8's or about 65%. That means over the span of an 8 hour work day, he will be doing the equivalent of 5 hours of actual work on this particular task. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "AJ" <microsoft.com> wrote in message news:8f8801c485fe$1c475200$gbl... |
How to customize Timeline values or labels? Posted: 19 Aug 2004 07:27 AM PDT Oops, sorry - I meant Project not outlook.... It was late at night after a big weekend. They are using kludging gantt charts in Excel and want to move to Project... "Steve House" <send.hotmail.com> wrote in message news:phx.gbl... and use other of appointment approach issue the the in see and exporting |
Posted: 19 Aug 2004 03:03 AM PDT Hi Morten, Welcome to this Microsoft Project newsgroup :-) Not possible, sorry :( FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :-)) Mike Glen MS Project MVP Morten Esmann wrote: |
Is there a way to customize reports? Posted: 18 Aug 2004 06:25 PM PDT Hi yes, you can customise (most) reports to a greater or lesser degree ... instead of going to Current Activities, choose View / Reports / Custom, click on Completed Tasks and then click on the EDIT button ... give the report a new name, and then you can play with the filter options (choose Incomplete rather than Complete) and the table that the data comes from ... i didn't have a look at what your options were here but you might be able to get the fields that you want by changing the table. If you can't get exactly what you want using this report, post back with details of what you actually want to see on the report and hopefully someone will come up with a way to achieve it. Hope this helps Cheers JulieD "LordLaLa" <microsoft.com> wrote in message news:com... % to |
Project 2003 Professional and email collaboration Posted: 18 Aug 2004 04:05 PM PDT JulieS -- Thanks! :) -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "JulieS" <microsoft.com> wrote in message news:953e01c48629$f4027780$gbl... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |