Gant Chart ! Microsoft Project |
- Gant Chart !
- MS Project 2002 High Level now created detailed one
- Salaried Resources
- Task Duration in Seconds?
- How to reduce resource units from 135% to 100%
- auto left justify gantt bars?
- Showing critical path
- Unhiding Columns
Posted: 08 Jul 2004 01:03 PM PDT Hi John, I figured out how to fix it, but thanks anyway. The reason why is was doing that is because I had assigned a resource calendar (24hr shift) to the resource that I was using for that task, which was different from the standard task calendar(7:30 PM to 5:00 PM). When I assigned the standard calendar including the oprion of "Scheduling ignores resource calendars" in the advanced tab of task information dialog box, it fixed fixed the gantt bar problem. I realized that I had a few other cases with the same problem. Now my question is: Is there a way to delete a resource calendar that has been created? Thanks again! AK "John" wrote: |
MS Project 2002 High Level now created detailed one Posted: 08 Jul 2004 12:41 PM PDT Hi Jack, Can you give me a further breakdown and more detailed explanation. I would appreciate your advice. Cheers "JackD" <see sig for details> wrote in message news:<#tw3#phx.gbl>... |
Posted: 08 Jul 2004 11:29 AM PDT IMO, you're mixing up "resource costs" with "project costs." Project calculates the marginal cost of doing the project, not the costs to the firm of employing the resource and in terms of the costs of actually doing the project work, prorating employment costs to an hourly rate and multiplying it by the man-hours the resource actually works of project tasks is the correct way to figure them. If I have Bob for one month (160 work hours) at a cost to the the firm of $5000 in salary, etc for that month, and I use him 100% (all 160 of them), he has cost my project budget $5000. But if I only use him 50%, 80 hours, he has been doing something else for those other 80 hours. My budget should reflect $2500 and whoever used those other 80 hours should have the other $2500 in their budget, not mine. If he wasn't doing anything at all, then we need to put the $2500 into the general overhead costs of the firm and have a serious talk with the HR manager about our staffing practices. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Steve" <sympatico.ca> wrote in message news:q2wHc.71350$nbnet.nb.ca... my same hours are nice I |
Posted: 08 Jul 2004 09:55 AM PDT Thanks for the ideas! I am currently doing the minutes-to- seconds conversion. Thought someone might have other ideas. Also have a rather clumsy Excel program that does work in seconds. However it is no where near as flexible as Project. can assume that "a le message de machinery. A Project |
How to reduce resource units from 135% to 100% Posted: 08 Jul 2004 08:47 AM PDT Hi, I may have good news for you. Sometimes Project SHOWS a number of units calculated from a value entered as actual work for a period (this would be for instance 10.8 hours on an 8 hours day) yet the work values for the remaining work are calculated based on the original units. If this is the case, do nothing (it is admissible that you cry in silence over such curious logic). :-)) HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Tapas Guha" <Tapas microsoft.com> schreef in bericht news:com... |
Posted: 08 Jul 2004 07:59 AM PDT Thanks Gérard, knew there had to be a better way even if it isn't completely automatic... - sjb - (a white finger dans le message de possible myself I |
Posted: 07 Jul 2004 11:02 PM PDT Fredrik, Summary lines should NOT show up on the critical path because they are not performance tasks, or at least should not be performance tasks. Normally, (except in very specific circumstances), summary lines do not have resources assigned and therefore there is no work performed on them. That being the case the summary line is not part of the critical path. Summary lines should also NOT have predecessors or successors. Although Project allows it, putting links on summary lines will cause more problems (mostly unintended results) then it is worth. Hope this helps. John |
Posted: 07 Jul 2004 09:38 AM PDT Hi, In Project as well, you can set column with to zero (to really "hide" the column) and grab it again later. -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Steve" <microsoft.com> schreef in bericht news:27c8301c46440$e158bc30$gbl... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |