Create a new Enterprise Project Posted: 15 Jul 2004 10:40 PM PDT Hi Dave, This sounds like a developer-type question to me. Try posting on the developer newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/. Mike Glen Project MVP davegrr wrote: |
Gantt Bar Sizes Posted: 15 Jul 2004 03:00 PM PDT Hi Brian, Welcome to this Microsoft Project newsgroup :-) Bar Styles give the option of 6 shapes, 10 patterns and 16 colours gives 960 combinations, and there aren't any more :( FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :-)) Mike Glen MS Project MVP Brian wrote: |
Project duration and dates Posted: 15 Jul 2004 01:05 PM PDT It sounds like you're confusing hours of work with hours of duration. The duration is the amount of (working) time between when the task begins and when it ends. If we work a normal default work schedule of an 8 hour workday (that's how Project knows what minutes out of the day count as working time) a task that starts Monday at 8am and is finished Friday at 5pm is 40 hours of duration by definition, period, end of story, and it CAN'T be anything else. So if you say a task has a *duration* of 24 hours and starts Mon at 8, it simply must end Wednesday at 5, there is no other option. You cannot say a task starts Mon at 8, ends Fri at 5, and has 20 hours duration UNLESS the workday itself is defined at 4 hours per day. Work is the number of man-hours the resource is actually doing something during that duration time period. The ratio of the two is the resource allocation percentage of the resource assignment. If I say I have a task budgeted for 20 hours, I'm usually thinking of man-hours of work. I could do that work over a 20, 40, 60, 217, or whatever hour duration. (I can't do it over LESS than 20 hours duration unless I get someone else to work with me because I can't be two places at once.) If I do 20 hours of work over a 20 hour duration I'm working 100%. If I do it over a 60 hour duration I'm working at 33% allocation, and so forth. Fixed dates are a major issue because all too often those dates have been determined without any regard to whether they are realistic or do-able. The notion behind ALL project scheduling software, not just MS Project, is that you are using the tool to develop a model of the project in order to determine what dates things should be scheduled for so as to meet the overall business objectives. When you start the process you know that you'll be able to start as of a certain date (or can assume one), perhaps you know you need to finish by a particular deadline, and you know what you need to get accomplished and who's available to do it. But you *don't* have a clue what dates all the tasks should be scheduled for - figuring all that detail out is why you're using the software in the first place. Even specifying start and finish dates when you enter tasks into the Gantt chart table doesn't really give you truly fixed dates. Entering a start date gives a Start No Earlier Then constraint while entering a finish date gives a Finish No Earlier Than constraint. There can only be one constraint so which you get will be determined by whether you specify the start of the finish date first - the last one entered will govern. But that's not to say the tasks won't get moved LATER in the plan if a predecessor link or resource unavailability or conflict drives them later. Here's a possible solution, workable if you're very careful. Set the default task type to fixed units and enter your tasks. You should never, ever, input start and finish dates except for those few tasks where a constraint is actually required by the nature of the task itself but if you really have no choice in the matter, when you set those dates the duration they represent will be calculated. I'd actually do it in the order finish date then start date because a SNET constraint makes more sense than a FNET constraint if you have to have one at all. The duration between those two dates is fixed and that's not something you can control, period. Now enter your resources in the resource list. Back to the Gantt chart. Split the screen (Window Split) and use the Task Form in the bottom window to assign your resources. For each task in turn, first switch the task type to fixed duration, click ok, then in the resources section enter the resource name, leave the percentage blank, and enter the number of hours budgeted for that task. When you click ok, the resource(s) will be assigned at whatever percentage produces the budgeted hours of work over the duration represented by the start and end dates you've specified. If any resource gets allocated at over 100% you've now got a political problem to solve because it means that the boss who gave you those fixed dates is requiring people to do more work in a workday than is humanly possible to do and something has got to give or the project is virtually guaranteed to fail. Hope this helps, let us know how it goes... -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Lisa" <microsoft.com> wrote in message news:com... can't figure out how to allot resources so that neither the amount of hours at which I've sent the duration nor the dates move. |
How difficult is Project Server to Implement? Posted: 15 Jul 2004 12:27 PM PDT I agree. The tool is just part of the problem. Defining and getting agreement on a standard process and training the users is quite an effort in a large group. -Jack "Rob Schneider" <net.net> wrote in message news:phx.gbl... |
How are percentages calculated? Posted: 15 Jul 2004 12:12 PM PDT The best thing to do is look in Help, and ask the question "how is percent complete computed" and you'll see the article "Percentage and number fields" and there you can see how these fields are computed. Hope this is useful to you. Let us know. rms JeremyE wrote: |
Linking tasks into master project Posted: 15 Jul 2004 12:07 PM PDT Hi Robin, If you expand the sub-project files within the master, you can link tasks in the normal way: eg select the 2 tasks an click the Link tool. Mike Glen Project MVP Robin wrote: |
build customized application for MS Project Posted: 15 Jul 2004 06:40 AM PDT You could also keep it simpler by using, if available in the company, Outlook's Task Request process. Customers ask a request of the manager who in turn delegates it out. Project would be great if the tasks are true projects ... but if "just" tasks, you might find the overhead/complexity is too much. There are also some very nice open source products available for free that do this sort of thing. Check out Source Forge et. al. Hope this is useful to you. Let us know. rms aj wrote: |
Link Summary or not? Posted: 15 Jul 2004 06:39 AM PDT You might want to look for an article by Robert Cooper about Stage-Gate processes (phases and gates) particularly the stuff he wrote about "Fuzzy" gates... some thoughts on lifecycles and phases.... This probably won't answer your question regarding linking of phase summary task (though I recommend against it) ---- Turns out most companies have lifecycles with phases and gates - however many gates are "90% there" (from an old Arnold Palmer quote about trees and golfing). Think about it, perhaps you have a deliverable of a specific tool made by an outside vendor. That tool is complicated and will take 6 months to produce. According to your lifecycle, that tool is not due until phase 3 - which is typically 2 months long and should happen 4 months from now. Do you wait until phase 3 to start work on the tool? Hell no! - you start thinking and acting on that deliverable ASAP.... SO here a phase 3 deliverable is actually being worked on during phase 1 and phase 2.... Mark -- __________________________________________________ _______ Mark Durrenberger, PMP Principal, Oak Associates, Inc, www.oakinc.com "Advancing the Theory and Practice of Project Management" __________________________________________________ ______ The nicest thing about NOT planning is that failure comes as a complete surprise and is not preceded by a period of worry and depression. - Sir John Harvey-Jones "maarkr" <microsoft.com> wrote in message news:2d9c601c46a71$37f8fdd0$gbl... |
Can't remove program Posted: 14 Jul 2004 08:47 PM PDT Have some kind of corruption on primary HD as could not reinstall, remove or change features when attempting to reload Project, reinstalled MS project to different HD and was able then to remove program. Thanks for your reponse. Steve Brown Sounds like that the uninstaller Whenever I not bar and Since |
Printing in Microsoft Project 2002 Posted: 14 Jul 2004 05:26 PM PDT Hi Catherine, Welcome to this Microsoft Project newsgroup :) You might like to have a look at my series of Microsoft Project lessons in the TechTrax ezine, particularly Lesson 8 - Printing Reports and Views, at this site: http://tinyurl.com/2xbhc (Perhaps you'd care to rate it before leaving the site, :) Thanks.) If that doesn't help, I would suspect corruption and you could try the suggestions in FAQ Item: 43. File Bloat? - Might be Corruption. FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP Catherine wrote: |
Website Project Plan Posted: 14 Jul 2004 04:22 PM PDT FYI, a project plan is a collection of documents. MS Project can be used for the WBS, schedule, resource plans, effort and duration estimates (and other documents) which are all PART OF the project plan. You'll also need things like roles and responsibilities, project success criteria, project justification, project charter ... If I were to do a Web sit project plan these would be the hyperlinks I'd consider: Project Charter One page scope document WBS Activity Effort estimates Activity duration estimates Resouce requirments/resource plans Team members and roles Risks and risk response plans Communication plan (built on the list of key stakeholders) Assumptions Network logic diagram performance measurement baseline (for earned value) By building this web site, you will know more about your project than you ever thought possible... Mark -- __________________________________________________ _______ Mark Durrenberger, PMP Principal, Oak Associates, Inc, www.oakinc.com "Advancing the Theory and Practice of Project Management" __________________________________________________ ______ The nicest thing about NOT planning is that failure comes as a complete surprise and is not preceded by a period of worry and depression. - Sir John Harvey-Jones "Ann" <com> wrote in message news:google.com... |
TO DO CRASHING FROM PROJECT Posted: 14 Jul 2004 03:35 PM PDT Start with the critical path(s). Do what you can to shorten it. Then when the new critical path(s) emerge, shorten them and so on and so on... Look at your plan and figure out what can be done in parallel but be aware of the risks as you "parallelize" work "We can start coding even though the design is not done however we risk rework once the design is finished" are you willing to take that risk? What is the risk/reward trade-off? (is the risk worth the reward?) Best of luck... Mark -- __________________________________________________ _______ Mark Durrenberger, PMP Principal, Oak Associates, Inc, www.oakinc.com "Advancing the Theory and Practice of Project Management" __________________________________________________ ______ The nicest thing about NOT planning is that failure comes as a complete surprise and is not preceded by a period of worry and depression. - Sir John Harvey-Jones "student" <microsoft.com> wrote in message news:2d04b01c469f2$d49149b0$gbl... |
Printing only Working Days Posted: 14 Jul 2004 11:47 AM PDT Thanks Steve, I figured this was the case, but I just wanted an expert opinion on the matter. thanks for the assistance, and keep up the great work. Jason cancelled because you message are sheets? |
Assignments not appearing in Project Server Task Timesheet Posted: 14 Jul 2004 11:42 AM PDT Diane -- Do you see errors in the application log on the server? -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "Diane Skoll" <edu> wrote in message news:2d89c01c46a5e$c09448b0$gbl... |