Show outline - without the parent summary Microsoft Project

Show outline - without the parent summary Microsoft Project


Show outline - without the parent summary

Posted: 16 Feb 2006 08:20 PM PST

Hi,

Since I cannot discover any logic in what you want, you'll have to decide
manually what you want to show
Insert a flag field that you set to yes for the tasks you want to see and
make a filter based on that flag field equals yes.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"John B" <com> schreef in bericht
news:com... 

purposes. 
summary 


Different number of printed pages when opened by another user

Posted: 16 Feb 2006 02:26 PM PST

Thanks for responding:
My understanding is that the defaults are taken from the project that you
open. What is happening is that I save the project by removing the Gantt
portion by pushing the view bar all the way to the right, eliminating the
Gantt, just leaving the tasks and few other columns. It shows 10 pages by
print preview. When another user opens it, it shows exactly how I saved it
except the print preview shows 100 pages, which they then print and 90% is
tossed itn the recycle.

"Mike Glen" wrote:
 

Display Problem with Project 2003

Posted: 16 Feb 2006 01:31 PM PST

Hi Mike

I'm now able to get into Project and the files show up fine. I'm not
exactly what all I did, but when the program froze on startup, I used the
office applicaton recovery tool to try and shut it down. It didn't quite
shut down...I still had to use the task manager to close it down, and for
some reason I was able to get in.

I closed project again and tried to get in and it froze again and I had to
use the task manager to shut it down. Then I used office "save my settings
wizard" and was able to get the program to prompt to work offline or connect
to project server. When I choose offline, I get in fine...when I try to
connect, that's when the program freezes.

So it seems that the problem is related to project server and the
connection...so on to that newsgroup to see what might be causing that.

Thanks for your help.



"ltsolis" wrote:
 

Assigning fixed cost for a contractor?

Posted: 16 Feb 2006 11:49 AM PST

Here's another option if the task equates to the job. The contractor is
paid for the job. In the rates of the resource sheet enter zero for the
contractor's standard and OT rates and his cost for the job in the "cost per
use" field. This a a good way to handle piece-work since the cost-per-use
is charged to the budget once ach task the resource is assigned to.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Pat" <pkelecy at insightbb dot com> wrote in message
news:phx.gbl... 

Master/Consolidated file stays linked/creates duplicate external l

Posted: 16 Feb 2006 09:07 AM PST

In article <com>,
"Mimi" <microsoft.com> wrote:
 

Mimi,
OK, write me direct at this address and I'll give you full details.
jensenj6atatcomcastdotdotnet
(remove obvious redundancies)

john 

Custom Variance fields

Posted: 16 Feb 2006 08:09 AM PST

In article <com>,
"Michelle Moulliet" <microsoft.com>
wrote:
 

Michelle,
You're welcome.
John

Duration 1 month = 1 calendar month

Posted: 16 Feb 2006 07:52 AM PST

In article <com>,
"Matt Schiemer" <microsoft.com> wrote:
 

Matt,
You're welcome. If enough people request a feature, I'd say there is a
good change a future version will incorporate it.

John 

Filtered To Do Lists

Posted: 16 Feb 2006 07:16 AM PST

Select Project, Filtered For then More Filters. Here you can edit and copy
Filters. Create or edit a filter to show what you want then select that
Filter in your report. Safest thing is to copy the report and change the
copy so the original is untouched and the same as every one else's. Ditto
with Filters. Don't edit existing Filters, copy them and edit the copy.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more


"MXC" <microsoft.com> wrote in message
news:com... 


Ressource calender

Posted: 16 Feb 2006 06:20 AM PST

thanks fot the reply Gerard.

accountable resources

Posted: 16 Feb 2006 12:28 AM PST

Hi,

Yes you can use a text field, why not?
You can customize it with a value list showing the resources.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"rathan" <microsoft.com> schreef in bericht
news:com... 
of 
resource. 


Resources confusion

Posted: 15 Feb 2006 02:04 PM PST

Hi Jojo

From your information the total time shown is 28 hours 6, 6, 6, 6, 4 not 20.

You would need to create a calendar for that resource setting the resources
hours, this would then properly allocate the time.

Obviously your project is showing as 1 week and the base calandar will have
been set for the working hours, individual resource times can be set by
creating their own calander, thereby properly allocating the time across the
project without affecting the project timings.

Ken

"jojo" wrote:
 

Simple Report / View

Posted: 15 Feb 2006 09:37 AM PST

I have no idea what a sharer file is. We run 20 projects on MS Project Server
2003. It is linked to Project Web Access. What I need is:

1. A report showing me the total hours an employee submitted in February
for project X. (I'd like to generate the report in MS Project)
2. A report showing the total hours planned for an employee working on
project X tasks.

"JulieS" wrote: