Show outline - without the parent summary Microsoft Project |
- Show outline - without the parent summary
- Different number of printed pages when opened by another user
- Display Problem with Project 2003
- Assigning fixed cost for a contractor?
- Master/Consolidated file stays linked/creates duplicate external l
- Custom Variance fields
- Duration 1 month = 1 calendar month
- Filtered To Do Lists
- Ressource calender
- accountable resources
- Resources confusion
- Simple Report / View
Show outline - without the parent summary Posted: 16 Feb 2006 08:20 PM PST Hi, Since I cannot discover any logic in what you want, you'll have to decide manually what you want to show Insert a flag field that you set to yes for the tasks you want to see and make a filter based on that flag field equals yes. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "John B" <com> schreef in bericht news:com... a purposes. summary |
Different number of printed pages when opened by another user Posted: 16 Feb 2006 02:26 PM PST Thanks for responding: My understanding is that the defaults are taken from the project that you open. What is happening is that I save the project by removing the Gantt portion by pushing the view bar all the way to the right, eliminating the Gantt, just leaving the tasks and few other columns. It shows 10 pages by print preview. When another user opens it, it shows exactly how I saved it except the print preview shows 100 pages, which they then print and 90% is tossed itn the recycle. "Mike Glen" wrote: |
Display Problem with Project 2003 Posted: 16 Feb 2006 01:31 PM PST Hi Mike I'm now able to get into Project and the files show up fine. I'm not exactly what all I did, but when the program froze on startup, I used the office applicaton recovery tool to try and shut it down. It didn't quite shut down...I still had to use the task manager to close it down, and for some reason I was able to get in. I closed project again and tried to get in and it froze again and I had to use the task manager to shut it down. Then I used office "save my settings wizard" and was able to get the program to prompt to work offline or connect to project server. When I choose offline, I get in fine...when I try to connect, that's when the program freezes. So it seems that the problem is related to project server and the connection...so on to that newsgroup to see what might be causing that. Thanks for your help. "ltsolis" wrote: |
Assigning fixed cost for a contractor? Posted: 16 Feb 2006 11:49 AM PST Here's another option if the task equates to the job. The contractor is paid for the job. In the rates of the resource sheet enter zero for the contractor's standard and OT rates and his cost for the job in the "cost per use" field. This a a good way to handle piece-work since the cost-per-use is charged to the budget once ach task the resource is assigned to. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Pat" <pkelecy at insightbb dot com> wrote in message news:phx.gbl... |
Master/Consolidated file stays linked/creates duplicate external l Posted: 16 Feb 2006 09:07 AM PST In article <com>, "Mimi" <microsoft.com> wrote: Mimi, OK, write me direct at this address and I'll give you full details. jensenj6atatcomcastdotdotnet (remove obvious redundancies) john |
Posted: 16 Feb 2006 08:09 AM PST In article <com>, "Michelle Moulliet" <microsoft.com> wrote: Michelle, You're welcome. John |
Duration 1 month = 1 calendar month Posted: 16 Feb 2006 07:52 AM PST In article <com>, "Matt Schiemer" <microsoft.com> wrote: Matt, You're welcome. If enough people request a feature, I'd say there is a good change a future version will incorporate it. John |
Posted: 16 Feb 2006 07:16 AM PST Select Project, Filtered For then More Filters. Here you can edit and copy Filters. Create or edit a filter to show what you want then select that Filter in your report. Safest thing is to copy the report and change the copy so the original is untouched and the same as every one else's. Ditto with Filters. Don't edit existing Filters, copy them and edit the copy. -- Rod Gill Project MVP Visit www.msproject-systems.com for Project Companion Tools and more "MXC" <microsoft.com> wrote in message news:com... |
Posted: 16 Feb 2006 06:20 AM PST thanks fot the reply Gerard. |
Posted: 16 Feb 2006 12:28 AM PST Hi, Yes you can use a text field, why not? You can customize it with a value list showing the resources. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "rathan" <microsoft.com> schreef in bericht news:com... of resource. |
Posted: 15 Feb 2006 02:04 PM PST Hi Jojo From your information the total time shown is 28 hours 6, 6, 6, 6, 4 not 20. You would need to create a calendar for that resource setting the resources hours, this would then properly allocate the time. Obviously your project is showing as 1 week and the base calandar will have been set for the working hours, individual resource times can be set by creating their own calander, thereby properly allocating the time across the project without affecting the project timings. Ken "jojo" wrote: |
Posted: 15 Feb 2006 09:37 AM PST I have no idea what a sharer file is. We run 20 projects on MS Project Server 2003. It is linked to Project Web Access. What I need is: 1. A report showing me the total hours an employee submitted in February for project X. (I'd like to generate the report in MS Project) 2. A report showing the total hours planned for an employee working on project X tasks. "JulieS" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |