Custom Numer Fields Microsoft Project |
- Custom Numer Fields
- Project Sumary Task
- Display additional fields in an MS Project Calendar view.
- Rollback Not working correctly in Trigger on MSP_TASKS
- Customised Fields - naming
- duration vs. elapsed time
- autosize row in Project file with Visual Basic
- Working with Customized fields
- Issue with FF and SS external dependencies
- creation dates with templates
- Installing MS Project trial version
- Document Access
- Project 2003 Resouce Issue
- task in outlook
- Assigning resources at the summary level
- Removing duration from the calendar view
Posted: 13 Oct 2005 11:26 AM PDT Thank you so much. Sometime you look at something for so long it will never some to you. Thanx again!!!! "Dale Howard [MVP]" wrote: |
Posted: 13 Oct 2005 10:25 AM PDT You're welcome Neal and thanks for the feedback. (The option to make the Project Summary Task appear always has long been on my list of wishes.) Julie "Neal" <microsoft.com> wrote in message news:com... |
Display additional fields in an MS Project Calendar view. Posted: 13 Oct 2005 09:45 AM PDT You are very welcome and thanks for the feedback. Julie "kwasky" <microsoft.com> wrote in message news:com... |
Rollback Not working correctly in Trigger on MSP_TASKS Posted: 13 Oct 2005 09:12 AM PDT Deepak Mahadevan wrote: Yikes!!! It is really a bad idea to have this kind of thing going on against Project's tables. you are pretty lucky that it did not really up your project. You would be best served enforcing these rules within an application level VBA event. http://techrepublic.com.com/5100-10878_11-5032122.html# This shows how to use these events. The example here looks at changes and asks for a password but you can change the code to your own needs. -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com |
Posted: 13 Oct 2005 08:51 AM PDT In article <#phx.gbl>, "JackD" <momokuri@gmail> wrote: Jack, As usual you are right. I just didn't look closely enough at that possibility. To verify my answer I used a file that had the custom fields renamed and I assumed that is what Steve had also. Bad assumption. John |
Posted: 13 Oct 2005 08:08 AM PDT Brian, Thank you so much for your prompt and accurate adivce. Once I got the proper view, it was smooth sailing. Thanks again...NYLA "NYLA" wrote: |
autosize row in Project file with Visual Basic Posted: 13 Oct 2005 07:25 AM PDT Thanks John. "John" wrote: |
Working with Customized fields Posted: 13 Oct 2005 06:32 AM PDT Brian is absolutely correct. Custom field formulas can only reference the task they are based on. You can't reference other tasks. And he is right that I have some code for this. Check out the "Ready to Start" macro here: http://masamiki.com/project/macros.htm You need to adjust the 80% to 100%, but it sounds like it does what you are asking. -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. "Brian K - Project MVP" <com> wrote in message news:microsoft.com... for |
Issue with FF and SS external dependencies Posted: 12 Oct 2005 09:38 PM PDT Hi Brian, We have the issue even if the dates have not changed. If the PM creates the link, saves the schedule and immediately reopens it, he/she gets the dialog box. Again, this issue is for FF and SS links only. For FS links it works fine. Chris "Brian K - Project MVP" wrote: |
Posted: 12 Oct 2005 12:05 PM PDT Thanks for the reply. No the template is not in a project file. It is an enterprise template. |
Installing MS Project trial version Posted: 12 Oct 2005 10:57 AM PDT Hi Justin and ed1671, Sorry the only further advise I can suggest would be to order the trial CD from Microsoft. The information is in the link below. http://www.microsoft.com/office/project/prodinfo/trial.mspx Hope this helps. Julie "Justin" <microsoft.com> wrote in message news:com... |
Posted: 12 Oct 2005 10:28 AM PDT Mark -- In the future, please post your Project Server questions to the microsoft.public.project.server newsgroup, as this newsgroup is devoted to the use of only the Microsoft Project desktop application. To answer your questions, team members are not added to the project's SharePoint subweb until they have been assigned to at least one task in the project. This is by design and it is how the system is supposed to work. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com http://www.projectserverexperts.com "We wrote the book on Project Server" "Mark" <microsoft.com> wrote in message news:com... |
Posted: 12 Oct 2005 09:20 AM PDT Hi Andrew, You are most welcome and thanks for the feedback. Julie "Andrew" <com> wrote in message news:googlegroups.com... |
Posted: 12 Oct 2005 05:20 AM PDT You're welcome Richard and thanks for the feedback. Julie "Richard Martin" <com> wrote in message news:phx.gbl... |
Assigning resources at the summary level Posted: 11 Oct 2005 06:59 PM PDT In article <com>, Robert <microsoft.com> wrote: Robert, This issue has been brought up many times in this newsgroup. You can do a search on the subject and get all kinds of opinions. Generally, linking to Summary Lines is a bad idea because the user needs to be extremely diligent and careful to avoid two major pitfalls. The first is creation of circular relationships. The second is unexpected changes in the schedule (i.e. normal links on performance tasks are fairly easy to see and predict but Summary Line links can cause some "sneaky" things to happen). If you are familiar with circuit ysis in electronics, Summary Line links are like sneak circuit paths. If you have successfully used links on Summary Lines in the past, you are either extremely lucky or very cognizant of their quirks. John Project MVP |
Removing duration from the calendar view Posted: 11 Oct 2005 04:14 PM PDT In article <com>, dave <com> wrote: Dave, To be honest, I don't know. I never use the Calendar view but playing with it a little it might be possible to do what you want but it certainly won't be pretty (i.e. very readable). What I ended up doing is to set up a separate 1 day task on the Finish date of each task. Then I filtered the view so only the one day tasks were visible. Finally I set the Format/Bar Styles for a line bar type (noncritical task). Like I said, not very "pretty". Project isn't all that flexible when it comes to presenting the data in certain ways and the Calendar view is one of them. John Project MVP |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 1600 Amphitheatre Parkway, Mountain View, CA 94043, United States |